Weeks Dredging & Contracting, Inc. v. United States

34 Cont. Cas. Fed. 75,356, 13 Cl. Ct. 193, 1987 U.S. Claims LEXIS 160
CourtUnited States Court of Claims
DecidedAugust 28, 1987
DocketNo. 694-84C
StatusPublished
Cited by38 cases

This text of 34 Cont. Cas. Fed. 75,356 (Weeks Dredging & Contracting, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Weeks Dredging & Contracting, Inc. v. United States, 34 Cont. Cas. Fed. 75,356, 13 Cl. Ct. 193, 1987 U.S. Claims LEXIS 160 (cc 1987).

Opinion

OPINION

REGINALD W. GIBSON, Judge:

I. Introduction

This is a Type I differing site condition case. However, it is not one in which the differing conditions primarily relate to the character or nature of the subsurface materials encountered versus such materials depicted in the contract documents. To the contrary, the conditions averred to have been encountered here, and which are allegedly materially different from contract depictions, relate to excess quantities of gravel, eutaw, and unanticipated sizes of gravel. See The Arundel Corporation v. United States, 515 F.2d 1116, 207 Ct.Cl. 84 (Ct.Cl.1975). In short, we find that plaintiff, in its effort to prove its claim(s) of differing site conditions, has failed to properly compare the quantum of certain subsurface materials allegedly depicted by contract documents, within the maximum pay template, with the quantum of all such materials actually dredged from within that same site. As is explained infra, plaintiff’s affirmative obligation to do so, we feel, is an imperative in order to enable this court to determine — whether there are any material quantum differences (between anticipated and actual dredged materials) within the same contract site (i.e., the maximum pay template). Jurisdiction in this court is premised on § 1491, Title 28 U.S.C.

Our opinion embodies the court’s final decision on all issues and claims raised by the plaintiff’s, Weeks Dredging & Contracting, Inc.’s (Weeks), petition of December 26, 1984. This decision follows an exhaustive five-week trial (August 7 — September 10, 1986) which resulted in well over 5,000 pages of transcript and almost two hundred exhibits — many of which consisted of multiple pages. Several interlocutory orders1 have also been issued, tracing an equally exhaustive period of pre- and post-trial motions and briefs. We now address the substantive issue(s) raised during said trial and concomitantly refer the reader to the more detailed account of proce[196]*196dural events found in Weeks Dredging & Contracting, Inc. v. United States, 11 Cl.Ct. 37 (1986).

Weeks, the plaintiff-contractor, seeks, in the first of its two causes of action, an equitable adjustment in the aggregate amount of $3,599,171.72 based on three distinct differing site conditions it allegedly encountered in the performance of a multimillion dollar dredging contract with the U.S. Army Corps of Engineers (Corps). Said contract was for channel and harbor virgin dredging on the now completed Tennessee-Tombigbee Waterway (Ten-Tom)2 in the southeastern United States. Plaintiff seeks to prove (as its first cause of action) that, while performing on contract number DACW 01-79-C-0125 (awarded April 2, 1979), it encountered (1) quantities of gravel, (2) quantities of eutaw,3 and (3) sizes of gravel, all materially in excess of what was reasonably discernible from the contract boring logs4 furnished by the Corps with the Invitation For Bids (IFB).5 As a consequence of the foregoing, plaintiff claims that it took an additional 195 dredging days in which to complete the contract beyond the 413 dredging days that the job should have taken had the subsurface conditions been as depicted by the contract boring logs. The excess cost allegedly incurred for these additional 195 days is the $3,599,171.72 claimed as an equitable adjustment.

As its second and last cause of action, Weeks seeks to recover interest only, pursuant to the Contract Disputes Act, 41 U.S.C. § 601 et seq (1982) (CDA), on a separate differing site condition claim, also arising out of the Ten-Tom project, which Weeks previously settled with the Corps in June, 1984.6 This previously-settled differing site condition claim was based on delays due to unanticipated stumps and logs found at the project dredging site. In settlement of said claim, the Corps paid Weeks interest on the equitable adjustment running from July 7,1983 to June 24, 1984, the date of settlement, on the theory that the stump claim was not properly certified, pursuant to the CDA, until July 5, 1983. Before this court, Weeks seeks additional interest, with respect thereto, running from a previous date it claims to have properly certified said claim, i.e., October 29, 1982, until the date of certification currently acknowledged by the Corps as July 5, 1983.

At the trial, the defendant’s opposition strategies centered around proving two fundamental defensive theories: first, that certain and various debilitating circumstances surrounding Weeks’ own performance were the actual as well as the concurrent causes,of-the-i95=day~delayr and secondly, that there were in fact no site conditions encountered reasonably and materially differing from those depicted in the Invitation For Bids and specifications. With regards to concurrent causes for delay, defendant stressed: (a) that plaintiff failed to conduct a reasonably adequate pre-bid site investigation; (b) that Weeks failed to reasonably interpret the contract documents, including the contract boring logs; and (c) that Weeks utilized an inexperienced and poorly-qualified work force, poor dredging technique, as well as substandard dredging equipment. In opposing plaintiff’s differing site condition claim(s), defendant also [197]*197relied on its own post-dredge test pit study to call into question the reasonableness of plaintiffs visual estimates of the quantities of the various .materials actually dredged.7

At closing arguments, the defendant focused its primary argument(s) from the foregoing (while not abandoning the same) and now emphasizes what it perceived to be a more fundamental failure of proof by the plaintiff. According to defendant, it is a simple fact that plaintiffs case is fatally flawed in that all of plaintiffs proof relates to an alleged differing site condition occurring at the wrong site. Instead of posturing its differing site condition claim by comparing the various estimated materials within the contract site {i.e., the maximum pay template) with the same categories of materials actually dredged in that same contract site (as it must), plaintiff erroneously compared, avers defendant, the categories of estimated materials within the maximum pay template, with the categories of materials actually dredged in the contract site plus an area of admitted 20 to 25% overdredging occurring outside of the contract site.8 Plaintiffs failure to factor out the quantum of “non-pay” materials it dredged outside the maximum pay template, from the “pay” materials it dredged within the contract site, leaves the court with no relevant comparative basis by which to test for the existence of any material differing site condition occurring within the relevant contract site.

Defendant also posits three barriers to the plaintiffs claim for additional interest on the now-settled stump claim. First, defendant claims that plaintiffs alleged certification in October of 1982 was faulty as a matter of law.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Optimum Services, Inc.
Armed Services Board of Contract Appeals, 2015
weston/bean Joint Venture v. United States
115 Fed. Cl. 215 (Federal Claims, 2014)
Cent. Allied Ents., Inc. v. Adjutant General's Dept.
2010 Ohio 3229 (Ohio Court of Claims, 2010)
URS Group, Inc. v. Tetra Tech FW, Inc.
181 P.3d 380 (Colorado Court of Appeals, 2008)
Trafalgar House Construction, Inc. v. United States
73 Fed. Cl. 675 (Federal Claims, 2006)
Morales Sand & Soil, LLC v. KPI
923 So. 2d 1229 (District Court of Appeal of Florida, 2006)
Renda Marine, Inc. v. United States
66 Fed. Cl. 639 (Federal Claims, 2005)
Conner Brothers Construction Co. v. United States
65 Fed. Cl. 657 (Federal Claims, 2005)
Kiewit Construction Co. v. United States
56 Fed. Cl. 414 (Federal Claims, 2003)
W.M. Schlosser, Inc. v. United States
50 Fed. Cl. 147 (Federal Claims, 2001)
Comtrol, Inc. v. United States
49 Fed. Cl. 294 (Federal Claims, 2001)
Rice Lake Contracting Corp. v. Rust Environment & Infrastructure, Inc.
616 N.W.2d 288 (Court of Appeals of Minnesota, 2000)
Fru-Con Construction Corp. v. United States
44 Fed. Cl. 298 (Federal Claims, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
34 Cont. Cas. Fed. 75,356, 13 Cl. Ct. 193, 1987 U.S. Claims LEXIS 160, Counsel Stack Legal Research, https://law.counselstack.com/opinion/weeks-dredging-contracting-inc-v-united-states-cc-1987.