Trafalgar House Construction, Inc. v. United States

73 Fed. Cl. 675, 2006 U.S. Claims LEXIS 329, 2006 WL 3123011
CourtUnited States Court of Federal Claims
DecidedOctober 31, 2006
DocketNo. 99-363C
StatusPublished
Cited by8 cases

This text of 73 Fed. Cl. 675 (Trafalgar House Construction, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Trafalgar House Construction, Inc. v. United States, 73 Fed. Cl. 675, 2006 U.S. Claims LEXIS 329, 2006 WL 3123011 (uscfc 2006).

Opinion

MEMORANDUM OPINION AND ORDER

BRADEN, Judge.

To facilitate a review of this Memorandum Opinion and Order, the following outline is provided:

I. RELEVANT FACTS. [677]

A. In 1986, The Government Initiated A Plan To Construct A Job Corps Center In Charleston, West Virginia. [677]

B. On September 7, 1994, The Government Issued A Solicitation To Construct The Job Corps Center. [678]

C. On March 20, 1995, The Government Awarded Plaintiff A Contract To Construct The Job Corps Center. [678]

1. The Contract Contained Certain Definitions And Terms.

2. The Contract Incorporated Certain Federal Acquisition Regulation Provisions.

3. The Contract Incorporated Contract Drawings And The Project Manual.

4. The Contract Incorporated Two Geotechnical Reports.
D. Plaintiff Solicited Subcontractor Bids For The Earthwork. [681]
E. Problems At The Construction Site. [682]

1. Bedrock Was Encountered At Lower Elevations Than Depicted In The Contract Drawings.

2. Uncontrolled Fill Was Encountered.
3. The Amount Of Special Rock Fill On Site Was Not Sufficient.
4. The Sequence of Construction Was Disrupted.
F. Plaintiff’s Requests For Equitable Adjustment. [685]

1. On April 5, 1996, Plaintiff Filed A Request For Equitable Adjustment.

2. In September 1997, Subcontractor Kimberly Industries, Inc. Retained A Consultant To Review The Contract’s Requirements.

3. On August 20, 1998, Plaintiff Filed A Revised Request For Equitable Adjustment.

G. The Contracting Officer’s Review Of Plaintiffs Requests For Equitable Adjustment. [687]

1. The Contracting Officer Retained Warner Construction Consultants, Inc. To Evaluate Plaintiffs Request For Equitable Adjustment. [690]

2. The May 14,1999 Contracting Officer’s Final Decision.

a. Findings Regarding Subcontractor, Kimberly Industries, Inc.

b. Findings Regarding Plaintiff.

H. The Civil Case In The Circuit Court Of Kanawha, West Virginia. [690]

[677]*677II. PROCEDURAL HISTORY. [691]

III. DISCUSSION. [692]
A. Jurisdiction. [692]
1. Requirements Of The Tucker Act.
2. Requirements Of The Contract Disputes Act.

a. Plaintiffs April 5, 1996 And Revised August 20,1998 Request For Equitable Adjustment State A “Claim.”

b. Plaintiffs Certification Of The Request For Equitable Adjustment Was Technically Deficient.

c. Plaintiffs Subcontractors Are Not Authorized To File A Certification.

B. Standing. [697]
C. Standard For Decision Regarding A Differing Site Condition. [698]

D. The Court’s Disposition Of The Government’s Motion For Judgment On Partial Findings. [698]

1. On Plaintiffs Claim For Encountering Bedrock Lower Than Indicated. a. Plaintiffs Argument.

b. The Government’s Response.

c. The Court’s Resolution.

2. On Plaintiffs Claim For Removing Uncontrolled Fill.

a. Plaintiffs Argument.

3. On Plaintiffs Claim For Providing Special Rock Fill.

4. On Plaintiffs Claim For Project Delays On Account Of Site Conditions.

a. Plaintiff’s Argument.

IV. CONCLUSION. [704]

***

I. RELEVANT FACTS.1

A. In 1986, The Government Initiated A Plan To Construct A Job Corps Center In Charleston, West Virginia.

In 1986, the Department of Labor (“Government” or “DOL”) began to search for a suitable site to construct a new Job Corps Center in Charleston, West Virginia. See TR 80-81. In 1992, the Government contacted a local developer, John Wellford, to explore placing the Job Corps Center adjacent to an office park that he was developing in Charleston. See TR 80-82, 306. Mr. Well-ford did not want the Job Corps Center to be constructed in that location but offered to assist in identifying an alternative site. See TR 81, 306-07. Mr. Wellford identified another property, on top of a mountain, on the outskirts of Charleston. See TR 81, 304. This property was purchased by Corotoman, Inc. (“Corotoman”), a land holding company owned by Mr. Wellford. Id. Thereafter, Corotoman sold twenty-four acres of property to the city of Charleston, which, in turn, sold the land to the Government as the site of the proposed Jobs Corps Center. See TR 83, 304. Kimberly Industries, Inc. (“Kimberly”) constructed a road to the site and installed sewer and water lines. See TR 83-84. Mr. Wellford also was the President of Kimberly. Id. at 80.

On March 4,1993, the Government entered into a contract with ZMM, Inc. (“ZMM”) to provide architectural and engineering services for the Job Corps Center project. See TR 109. ZMM contracted with Chapman Technical Group (“Chapman”) to provide nec[678]*678essary civil engineering services. See TR 573-74. Chapman contracted with H.C. Nutting Company (“H.C.Nutting”) to conduct a geotechnical investigation of the site. See TR 574. In addition, DMJM/HTB Inc. was hired to provide engineering support and develop the scope of work. See TR 21,1030-32.

The initial Job Corps Center’s schematic site plan included eleven one- and two-story buildings, some hanging over steep slopes, without a perimeter roadway. See PX 3 (Project Plans and Drawings); PX 8 at 4. ZMM, however, determined that the level area on top of the mountain was not large enough to accommodate this plan, so the flat area was proposed to be increased by designing “sidehill fills” around the perimeter. See PX 3 at 16-25 (cross-sections of the project site depicting the existing grade and the proposed grade); see also PX 1, part 6 at 99-105/121 (six drawings of sidehill cross-sections A-A through G-G, depicting the existing bedrock, the proposed slopes, required engineering fill, and required special rock fill).

B. On September 7, 1994, The Government Issued A Solicitation To Construct The Job Corps Center.

On September 7, 1994, the Government issued Solicitation No. IFB-95-DAA-03-JC, incorporating by reference certain plans, specifications, and other documents necessary to construct the proposed Job Corps Center, including contract drawings, a project manual, and two geotechnical reports. See PX 1; PX 3; PX 70 at 2. On December 12, 1994 and January 5, 1995, the Government issued two amendments to the initial Solicitation. See PX 1, part 1 at 2-3/160.

C. On March 20, 1995, The Government Awarded Plaintiff A Contract To Construct The Job Corps Center.

On March 20, 1995, the Government awarded Contract No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Horn & Associates, Inc. v. United States
123 Fed. Cl. 728 (Federal Claims, 2015)
Roxco, Ltd. v. United States
77 Fed. Cl. 138 (Federal Claims, 2007)
Trafalgar House Construction, Inc. v. United States
77 Fed. Cl. 48 (Federal Claims, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
73 Fed. Cl. 675, 2006 U.S. Claims LEXIS 329, 2006 WL 3123011, Counsel Stack Legal Research, https://law.counselstack.com/opinion/trafalgar-house-construction-inc-v-united-states-uscfc-2006.