Trafalgar House Construction, Inc. v. United States

77 Fed. Cl. 48, 2007 U.S. Claims LEXIS 125, 2007 WL 1266924
CourtUnited States Court of Federal Claims
DecidedApril 30, 2007
DocketNo. 99-363C
StatusPublished
Cited by4 cases

This text of 77 Fed. Cl. 48 (Trafalgar House Construction, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Trafalgar House Construction, Inc. v. United States, 77 Fed. Cl. 48, 2007 U.S. Claims LEXIS 125, 2007 WL 1266924 (uscfc 2007).

Opinion

MEMORANDUM OPINION AND FINAL ORDER

BRADEN, Judge.

This case involves construction of a new Job Corps Center on a mountain located on the outskirts of Charleston, West Virginia by the Department of Labor (“Government” or “DOL”). See Trafalgar House Constr., Inc. v. United States, 73 Fed.Cl. 675, 677 (2006) (“Trafalgar House I ”). On March 20, 1995, DOL awarded a fixed price contract in the amount of $17,270,000 to Trafalgar House Construction, Inc. (“THC” or “Plaintiff’) for the construction of the new Job Corps Center. Id. at 678. On April 10, 1995, THC selected Kimberly Industries, Inc. (“Kimberly”) as the earthwork subcontractor. Id. at 682. Almost immediately thereafter, Plaintiff and Kimberly experienced construction problems at the job site. Id. at 682-85. Litigation ensued in the United States Dis[50]*50trict Court for the Southern District of West Virginia and the United States Court of Federal Claims.

On October 31, 2006, the court issued a Memorandum Opinion and Order resolving the breach of contract claims asserted in Plaintiffs June 7, 1999 Complaint in favor of the Government. See Trafalgar House I, 73 Fed.Cl. at 704. Remaining before the court are entry of a final judgment regarding Plaintiffs breach of contract claims and two pending counterclaims asserted by the Government.

I. JUDGMENT IS ENTERED IN FAVOR OF THE GOVERNMENT ON PLAINTIFF’S BREACH OF CONTRACT CLAIMS.

On October 31, 2006, the court issued a Memorandum Opinion and Order determining that the certifications submitted with Plaintiffs April 5, 1996 Request for Equitable Adjustment (“REA”) and Plaintiffs August 20, 1998 REA were deficient, because they did not comply with the requirements set forth in 41 U.S.C. § 605(c)(1) and 48 C.F.R. § 33.207(c). See Trafalgar House I, 73 Fed.Cl. at 693-94. In addition, the certification submitted with the August 20, 1998 REA was unsigned. Id. To enable the court to enter a final judgment, Plaintiff was afforded the opportunity, if possible, to file a non-defective certification. Id. at 694; see also 41 U.S.C. § 605(c)(6) (“Prior to the entry of a final judgment by a court ... the court ... shall require a defective certification to be corrected.”). On November 22, 2006, Plaintiff filed a corrected certification, i.e., the certificate was signed and included the required representations that the claim was made in good faith and the certifier was duly authorized to certify the claim. See Certification of Claim at 1, Trafalgar House Constr. v. United States, No. 99-363 (Fed.Cl. Nov. 22, 2006). Accordingly, the court is now authorized to enter a judgment in favor of the Government with respect to the breach of contract claims asserted in the June 7, 1999 Complaint. See Trafalgar House I, 73 Fed.Cl. at 698-704 (finding in favor of the Government on each of Plaintiffs four claims).

II. RESOLUTION OF THE GOVERNMENT’S COUNTERCLAIMS.

A. Relevant Procedural Background.1

The Government’s November 19, 1999 Answer and Counterclaim asserted a counterclaim seeking damages of $533,448, plus interest. See First Counterclaim 111177-84. The $533,488 amount claimed is the difference between the $1 million interim payment advanced by the CO to THC on February 20, 1997 and the CO’s May 14, 1999 Final Decision that THC should be awarded $466,552. Id. 1183; see also PX 70 at 6, 43.

From September 19-23, 2005, a trial was conducted by the United States Court of Federal Claims. The court subsequently determined that Plaintiffs breach of contract claims were without merit. See Trafalgar House I, 73 Fed.Cl. at 698-704. In response to the evidence adduced at trial, the Government revised its damages request to recoup the entire $1 million interim payment. See Am. Answer H at 1; see also Gov’t PT Brief at 17. In addition, on April 7, 2006, the court entered an Order granting the Government’s Motion to Amend the Answer to include an additional Counterclaim.2 On April 7, 2006, [51]*51the Government filed an Amended Answer and also filed an Additional Counterclaim under the False Claims Act, 31 U.S.C. § 3729. See Second Counterclaim Till 102-04.

B. Jurisdiction.

The United States Court of Federal Claims has “jurisdiction to render judgment upon any setoff or demand by the United States against any plaintiff[.]” See 28 U.S.C. § 1503; see also 28 U.S.C. § 2508 (“Upon the trial of any suit in the United States Court of Federal Claims in which any setoff, counterclaim, claim for damages, or other demand is set up on the part of the United States against any plaintiff making claim against the United States in said court, the court shall hear and determine such claim or demand both for and against the United States and plaintiff. If upon the whole case it finds that the plaintiff is indebted to the United States it shall render judgment to that effect, and such judgment shall be final and reviewable.”).

C. The Government’s Counterclaim To Recoup The February 20, 1997 Interim Payment Is Granted.

The Government’s First Counterclaim alleges that:

On February 20, 1997, [DOL] issued a modification to the contract that increased the value of the contract by $1,000,000. This modification did not represent a determination by [DOL] that [Plaintiff] was entitled to an additional $1,000,000, but rather was an advance interim payment upon [PlaintiffQ’s REA and was contingent upon the contracting officer determining that [Plaintiff] was actually entitled to an upward adjustment in contract price.
❖ *
On May 14, 1999, [DOL] issued a contracting officer’s final decision on [Plaintiff]’s claim. The contracting officer’s final decision determined that [Plaintiff] was entitled to an upward contract adjustment of $466,552. The contracting officer also determined that, because [DOL] had made an advance payment of $1,000,000, [Plaintiff] was required to repay the sum of $533,448 to the United States.

First Counterclaim 111181, 83.

At trial, the Government requested that the court award the Government $533,448, plus interest. Id. H 84. Based on this and other evidence adduced at trial, the Government now asserts that “[b]ecause [Plaintiff]’s claims are without merit, ... the Government is entitled to return of the [entire] provisional payment of $1 million.” Gov’t PT Brief at 17.

In response, Plaintiff asserts that the CO testified at trial that Plaintiff was entitled to recover $466,552, for the reasons set forth in the May 14, 1999 Final Decision. See PI. Opp. at 2-3. This testimony was corroborated by Mr. John McTyre’s testimony3

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
77 Fed. Cl. 48, 2007 U.S. Claims LEXIS 125, 2007 WL 1266924, Counsel Stack Legal Research, https://law.counselstack.com/opinion/trafalgar-house-construction-inc-v-united-states-uscfc-2007.