Miller v. United States

550 F.2d 17, 23 Cont. Cas. Fed. 81,036, 213 Ct. Cl. 59, 1977 U.S. Ct. Cl. LEXIS 38
CourtUnited States Court of Claims
DecidedFebruary 23, 1977
DocketNo. 59-71
StatusPublished
Cited by55 cases

This text of 550 F.2d 17 (Miller v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Miller v. United States, 550 F.2d 17, 23 Cont. Cas. Fed. 81,036, 213 Ct. Cl. 59, 1977 U.S. Ct. Cl. LEXIS 38 (cc 1977).

Opinion

Kunzig, Judge,

delivered the opinion of the court:

This suit is based on a contract between plaintiff-Miller Brothers (Miller)1 and defendant-United States Department of Housing and Urban Development (HUD) for the servicing of mobile homes in Plaquemines Parish,2 Louisiana. Plaintiff claims that the Government improperly withheld money due under the contract. Defendant counterclaims, stating (1) that it overpaid on sums already remitted to plaintiff, (2) that Miller’s claim is forfeit due to fraud,3 and (3) that Miller, in the course of performing the contract, violated the False Claims Act.4 The Government [62]*62further requests the statutory penalty of $2,000.00 for sixteen alleged violations of the Act.

After thorough examination of the testimony at trial, the documents submitted by the parties, and all briefs filed by counsel, we hold that Miller is entitled to recover in part. The amount is reduced, however, by the Government’s False Claims Act counterclaim, which we find meritorious, again in part. As to the remaining two counterclaims, the Government appears to have abandoned its claim for overpayment, so we do not consider it. The fraud claim, we deny.

[63]*63In reaching our decision, we have determined that the Trial Judge’s recommended findings of fact do not merit the normal presumption of correctness under Ct.Cl. Rule 147(b), and thereby substitute our own. We do this only with great difficulty upon being convinced by a thorough analysis of thé complete record that the Trial Judge misconstrued the evidence submitted in this case. See Ricci v. United States, 205 Ct.Cl. 687, 697-98, 507 F.2d 1390, 1392 (1974); Willett v. United States, 186 Ct.Cl. 775, 787-88, 406 F.2d 1346, 1353 (1969); Miller v. United States, 168 Ct.Cl. 498, 501, 339 F.2d 661, 662 (1964).

Facts

The facts of this case are complicated and require thorough elaboration. We begin with the incredible devastation wrought on Plaquemines Parish, where Hurricane Camille struck this southeastern part of Louisiana on August 17, 1969. Virtually surrounded by water (three sides by the Gulf of Mexico and split lengthwise by the Mississippi River), the Parish was inundated. Wind, water and tornado combined to destroy virtually 100% of all homes. The communities of Venice, Boothville, Triumph and Pilottown were completely ruined. Buras and Empire were 80% and 60% lost.

As a result, the Parish was declared a major disaster area by the Federal Government on August 19, 1969.5 As part of Government relief to the Parish, the Emergency Preparedness Administration made funds available to furnish housing for Hurricane Camille’s victims — some 15,000 homeless evacuees. With these funds, HUD began a program to provide temporary housing in mobile homes, arranging with a private contractor to bring in and set up HUD-leased mobile dwellings throughout the Parish. In total, approximately 1,800 trailers were moved in to provide disaster relief housing.

From its inception until December 1969, when the last victims of the disaster were assigned trailers, the Emergency Relief Housing Program was administered by regular [64]*64HUD employees from Houston and Fort Worth, Texas. After the regular HUD employees withdrew, the program was administered by Parish employees hired by HUD on a temporary basis. Kermit Ballay and Peter Turlich, both longtime Parish employees, were designated as Housing Manager and Assistant Housing Manager, charged with administering the housing program at the local level for HUD.

In December 1969, HUD issued an advertised competitive solicitation (VC-1-70) for repair and preventive maintenance on the approximately 1,800 mobile homes in the Hurricane Camille Disaster Area for the period December 23, 1969 or date of award (whichever was later) through August 18, 1970. The Miller brothers, as a partnership, were awarded the contract effective January 30, 1970.

The agreement contained provisions making the Service Contract Act, 41 U.S.C. §351 (1970), applicable. That Act requires the contractor to meet minimum wage standards and to maintain specified employment records. In addition, special provisions of the , contract required Miller to use only new parts and materials or rebuilt parts with prior Government approval. Further, the contractor agreed to perform all work with competent mechanics, experienced and qualified to work on the specified equipment.

The contract provided that Miller would make periodic inspections of the mobile homes to check, clean and adjust all equipment including plumbing, heating, electrical systems and furniture furnished with the mobile homes. During such inspection, the contractor would also check the level of the trailer, re-level as required, and make any other needed repairs or replacements subject to a $50.00 cost limitation.

The contract also called for Miller to make service calls on the mobile homes at the direction of the Housing Manager. Service calls were to include, but were not limited to, repair or replacement of mechanical equipment, plumbing, electrical equipment, wiring and household fixtures, and appliances covered under the HUD mobile home lease. Also included in service calls were repairs to carpentry, sheet metal, painting, floor covering and roofing items. Each call was to be made within ten hours after [65]*65notification. Service call costs, including labor and materials, were limited to $50.00. Service calls exceeding $50.00 required the prior approval of the Housing Manager or his assistant.

The Housing Manager, Ballay, and his assistant, Turlich, were authorized by the contract to administer its provisions on behalf of the Contracting Officer, Leonard E. Church, HUD Deputy Regional Administrator in Fort Worth, Texas. The authorization did not, however, allow Ballay, the Housing Manager, to modify any contract terms or specifications.

Performance under the contract began on January 31, 1970. Miller assigned workmen to make the periodic inspections. Not one of these workmen was qualified to make repairs. At the outset, this situation was not a problem, even though the contract specified that certain repairs were to be made in conjunction with periodic inspections. Mr. Ballay, it appears, initially instructed Miller not to make repairs during inspection visits. It should be noted that Mr. Ballay was without authority to alter the contract in this regard. In March or April of 1970, Mr. Ballay changed his instructions to conform to the contract.

Service calls were made by David Miller or one of his workmen upon receipt of a complaint form from the HUD Housing Office in Buras. HUD trailer tenants phoned in complaints to that office, where a complaint form was prepared. Miller picked up the forms daily from the Housing Office and distributed them to his workmen for action. The workmen supposedly made the requested repairs and listed the work done, materials used, and time expended.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

John Hendrix v. J-M Manufacturing Co., Inc.
76 F.4th 1164 (Ninth Circuit, 2023)
Mw Builders, Inc. v. United States
134 Fed. Cl. 469 (Federal Claims, 2017)
Rda Construction Corp. v. United States
132 Fed. Cl. 732 (Federal Claims, 2017)
Horn & Associates, Inc. v. United States
123 Fed. Cl. 728 (Federal Claims, 2015)
Veridyne Corporation v. United States
758 F.3d 1371 (Federal Circuit, 2014)
Chapman Law Firm, LPA v. United States
113 Fed. Cl. 555 (Federal Claims, 2013)
Kellogg Brown & Root Services, Inc. v. United States
728 F.3d 1348 (Federal Circuit, 2013)
Ulysses, Inc. v. United States
110 Fed. Cl. 618 (Federal Claims, 2013)
Hernandez, Kroone and Associates, Inc. v. United States
110 Fed. Cl. 496 (Federal Claims, 2013)
Veridyne Corp. v. United States
105 Fed. Cl. 769 (Federal Claims, 2012)
Grand Acadian, Inc. v. United States
105 Fed. Cl. 447 (Federal Claims, 2012)
Alcatec, LLC v. United States
100 Fed. Cl. 502 (Federal Claims, 2011)
Trafalgar House Construction, Inc. v. United States
77 Fed. Cl. 48 (Federal Claims, 2007)
Daewoo Engineering & Construction Co. v. United States
73 Fed. Cl. 547 (Federal Claims, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
550 F.2d 17, 23 Cont. Cas. Fed. 81,036, 213 Ct. Cl. 59, 1977 U.S. Ct. Cl. LEXIS 38, Counsel Stack Legal Research, https://law.counselstack.com/opinion/miller-v-united-states-cc-1977.