Bar Ray Products, Inc. v. The United States

340 F.2d 343, 167 Ct. Cl. 839, 1964 U.S. Ct. Cl. LEXIS 141
CourtUnited States Court of Claims
DecidedOctober 16, 1964
Docket382-61
StatusPublished
Cited by9 cases

This text of 340 F.2d 343 (Bar Ray Products, Inc. v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bar Ray Products, Inc. v. The United States, 340 F.2d 343, 167 Ct. Cl. 839, 1964 U.S. Ct. Cl. LEXIS 141 (cc 1964).

Opinion

PER CURIAM.

This case was referred pursuant to-Rule 57(a) to Herbert N. Maletz, a trial commissioner of this court, with directions to make findings of fact and recommendations for conclusions of law. The-case proceeded for adjudication on the-basis of the administrative record alone-without submission of further evidence- and such facts as are necessary to decision of the ease are found in the commissioner’s opinion which was filed on May 19, 1964. No exceptions to the commissioner’s opinion were filed by the parties; and on July 17, 1964, defendant filed a; motion to dismiss for default pursuant to Rule 63, to which plaintiff filed an-answer on July 23, 1964, setting forth that plaintiff accepts the report of the commissioner and agrees and consents; that judgment be entered in accordance-with his findings and recommendations..

Since the court is in agreement with the opinion, findings and recommendations of the trial commissioner, as hereinafter set forth, it hereby adopts the-same as the basis for its judgment ini this case without oral argument. Plain. *345 tiff is therefore not entitled to recover ■on its petition, which is dismissed subject to the condition that defendant make tender to plaintiff of all the units in question, as set forth in the opinion, which •defendant has in its possession.

In view of this dismissal of the petition, no action is required to be taken -on defendant’s motion to dismiss filed on •July 17, 1964.

OPINION OF COMMISSIONER

Plaintiff had contracts with the defendant for manufacture and delivery of -certain photographic processing tray sets. Several years after the units were delivered and accepted, and payment effected, defendant’s contracting officer found that they did not meet specification requirements and that their accept-ance had been induced by such gross mistake as to indicate fraud. The contracting officer offered return of the units -and demanded refund of the purchase price. Plaintiff took an appeal to the Armed Services Board of Contract Appeals (ASBCA) which was denied. Defendant thereupon again offered to return the units and repeated the demand for refund. When plaintiff refused to refund the purchase price, defendant withheld from it monies due under other ■Government contracts for which recovery is now sought here.

In view of the holding in United States v. Carlo Bianchi, 373 U.S. 709, 83 S.Ct. 1409, 10 L.Ed.2d 652 (1963), 1 the problem in this case — as stated by the court— is “to determine, on the basis of the administrative record and the provisions ■of the contracts, whether the decision of the Board of Contract Appeals meets the -standards of Public Law 356, 83d Cong., :2d Sess., 68 Stat. 81, 41 U.S.C. §§ 321-322 (the Wunderlich Act).” Bar Ray Products, Inc. v. United States, Ct.Cl. No. 382-61, decided July 12, 1963, slip op. p. 3. 2 Under that act an administrative determination on a question of fact made under the disputes clause of a Government contract is final and conclusive unless the determination is fraudulent, capricious, arbitrary, or so grossly erroneous as necessarily to imply bad faith, or is not supported by substantial evidence. Against this background, plaintiff has filed a statement in the nature of an assignment of errors challenging certain findings of the ASBCA as not being supported by substantial evidence — a contention which defendant denies. Thus the sole issue is whether or not the findings in question are supported by substantial evidence. 3

The facts leading up to the present controversy are as follows: Plaintiff, as low bidder, was awarded three contracts on April 9, April 16 and June 17, 1953, for manufacture and delivery of 22 portable field photographic processing tray sets, for a total price of $26,046. Each set was to be a composite unit consisting of a set of three trays, plus elements to provide heat or refrigeration to the solution in the trays. The unit of trays was made of stainless steel and consisted of three open trays arranged side by side and so constructed that by means of plumbing fixtures, water could be circulated through the space immediately beneath the trays. By controlling the temperature of the circulating water, the temperature of the solution in the open trays could be raised and lowered to, and held at, 68° F., which is the commonly accepted temperature for processing photographic products. The heating and refrigeration elements were required to *346 meet the following performance-type specifications:

“ * * * The cooler shall have sufficient capacity to cool the water in the trays from 100 degrees F. to 68 degrees F. in 1% hours when operating in an ambient temperature of 130 degrees F. and a relative humidity of 15 percent.
“ * * * The cooling unit shall become effective when the temperature of the circulating water exceeds 70 degrees F. and shall remain effective until the temperature of 68 degrees F. has been reached. The heating unit shall become effective when the temperature of the circulating water drops below 66 degrees F. and shall remain effective until a temperature of 68 degrees F. has been reached. The design of the thermostatic control shall be such as to prevent simultaneous operation of the heating and cooling units.”

Each contract contained inspection clauses which read in part:

“ (c) * * * Final acceptance or rejection of the supplies shall be made as promptly as practicable after delivery, except as otherwise provided in this contract; but failure to inspect and accept or reject supplies shall neither relieve the Contractor from responsibility for such supplies as are not in accordance with the contract requirements nor impose liability on the Government therefor.
“(d) The inspection and test by the Government of any supplies or lots thereof does not relieve the Contractor from any responsibility regarding defects or other failures to meet the contract requirements which may be discovered prior to final acceptance. Except as otherwise provided in this contract, final acceptance shall be conclusive except as regards latent defects, fraud, or such gross mistakes as amount to fraud.”

Each contract also contained the following guarantee clause:

“It is understood that the equipment herein specified shall be guaranteed for a period of one (1) year from date of final acceptance thereof against defective materials, design and workmanship. Upon receipt of notice from the Government of failure of any part during the guarantee period, the affected part or parts shall be replaced promptly by new parts by and at the expense of the contractor.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
340 F.2d 343, 167 Ct. Cl. 839, 1964 U.S. Ct. Cl. LEXIS 141, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bar-ray-products-inc-v-the-united-states-cc-1964.