Bender Gmbh v. Secretary of the Army

126 F. App'x 948
CourtCourt of Appeals for the Federal Circuit
DecidedMarch 21, 2005
Docket2004-1327
StatusUnpublished

This text of 126 F. App'x 948 (Bender Gmbh v. Secretary of the Army) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bender Gmbh v. Secretary of the Army, 126 F. App'x 948 (Fed. Cir. 2005).

Opinion

PER CURIAM.

Bender GmbH appeals the decision of the Armed Services Board of Contract Appeals, Docket No. 04-1327, denying Bender’s request for payment of its final invoice *950 under its contract with the Department of the Army and upholding the Army’s claim requiring Bender to refund an overpayment. We affirm.

I

In 1995 the Army awarded Bender a lump-sum fixed-price contract in the amount of DM187,246.57 to clean and close a sewage treatment plant in Babenhausen, Germany, including removing water and sludge from several tanks at the plant. In the course of performing the contract, Bender pumped water from the tanks onto a field, in violation of a contract term requiring Bender to haul the water away. An Army inspector reported the incident to local authorities and authorized Bender to send sludge samples from the tanks to be tested for contamination. The testing disclosed that the sludge was contaminated with heavy metals. Bender had performed 90 percent of the contract work at that point and had invoiced the Army for a corresponding amount of the contract price.

After it was discovered that the sludge was contaminated, Bender sent a proposal to the Army offering to dry and remove the contaminated sludge. Some months later, Bender followed up with a letter proposing to remove 120 cubic meters of contaminated material at a cost of DM739.40 per cubic meter. Bender’s first proposal to the Army to remove the contaminated sludge contained three line items. The first line item consisted of a charge for drying the sludge, while the second and third line items consisted of charges for loading and hauling away the sludge. Bender’s follow-up letter to the Army referred to the previous proposal, but contained only one line item for removing the contaminated sludge and did not break down the costs for drying, loading, and hauling into separate line items.

The Army issued a contract modification in response to Bender’s proposal and follow-up letter. Among other changes, the modification increased the price of the contract by DM88,728 for the removal of 120 cubic meters of sludge at DM739.40 per cubic meter. Shortly thereafter, Bender requested another contract modification increasing the quantity of contaminated material to be removed to 270 cubic meters at DM739.40 per cubic meter. The Army modified the contract to reflect the increased quantity in that request and made another modification in response to a further request to increase the amount to be removed, bringing the total to 430 cubic meters at DM739.40 per cubic meter. The modifications added two clauses to the contract that are pertinent to this case. Clause (b) provided that “[t]he additional quantity will be funded and definitized based on the price proposal and disposal certificates provided by the contractor.” Clause (d) provided that “[f]inal price determination of subject contract and modification will be subject to the GPCO [German Price Control Office] audit.”

Bender contracted with a subcontractor to remove the water and sludge at a price of DM260 per metric ton. The evidence showed that in the industry, a metric ton is regarded as the equivalent of a cubic meter of material. To facilitate pumping the sludge out of the tanks at the sewage plant, the subcontractor first added water and then mixed it with the sludge to soften it so that it could be pumped out of the tank. The subcontractor then pumped the mixture into compression chambers that squeezed the water out of the sludge. The subcontractor loaded the compressed sludge into containers and transported it to the disposal site where each container was weighed before and after it was unloaded. The disposal site weight slips showed that the subcontractor disposed of *951 229.12 tons of sludge, and the subcontractor invoiced Bender for removing that amount. When the sludge removal was complete, the Army inspected the sewage treatment facility and issued a Completion and Acceptance Certificate for the work.

During the contract modification period, Bender periodically invoiced the Army for the sludge removal, and on each invoice the Army stamped its standard certification that “services mentioned have been received and work performed is satisfactory and in conformance to the condition of this contract.” The Army paid those invoices before receiving the- disposal certificates required by clause (b) of the contract modification. Bender submitted its final invoice after all of the sludge was removed. The contracting officer, however, returned that final invoice, stating that the price audit had not been performed and that Bender had not provided the required disposal certificates. Bender then submitted the weight slips issued by the disposal facility, which showed that a total of 229.12 metric tons of material had been removed.

After receiving the weight slips, the Army ordered an audit, as provided for by clause (d) of the modified contract. The GPCO then requested information from Bender so that it could perform the audit to determine the proper amount to be paid for removing the sludge. Bender refused to supply the requested information because it contended the contract was a construction contract and therefore was exempt from audit on that ground. Bender subsequently argued that the contract was a fixed-price contract and therefore was exempt from audit on that basis. After several months, the Army withdrew its request for a price audit, because Bender would not cooperate with the GPCO. Shortly thereafter, Bender demanded the remaining amount due on the contract. The Army responded that Bender owed it money because Bender had disposed of 267 cubic meters of water by dumping it into the local sewer rather than by hauling it away. The contracting officer issued a decision on that matter, determining that the amount owed by Bender was DM11,869.37 more than the unpaid amount due on the contract. Bender filed an appeal of that decision with the Board.

Two months later, the contracting officer withdrew his first decision and advised Bender that a second decision would be forthcoming. At that time, the contracting officer also requested that Bender provide the disposal certificates required by clause (b) of the contract modification. Bender provided the weight slips it had given previously, indicating that its subcontractor had disposed of 229.12 metric tons of sludge. Consequently, the contracting officer issued a revised final decision asserting that Bender had overcharged the Army for 200.88 cubic meters of sludge that it did not remove. Based on that finding, the contracting officer concluded that Bender owed the Army a total of DM120,798.10. Bender filed an appeal of the revised decision. The Board affirmed the decision of the contracting officer, and this appeal followed.

II

Bender contends that the Board erred in three respects. First, Bender argues that the Board incorrectly found that when the parties modified the contract to include the price of removing the contaminated sludge, they changed it from a lump-sum fixed-price contract to one based on unit pricing. Second, Bender claims that the Board erred in determining that the quantity of sludge removed was based on the weight of compressed sludge as opposed to the weight of uncompressed sludge. Finally, Bender insists that in either case, the Army’s claim is barred because the war *952

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bar Ray Products, Inc. v. The United States
340 F.2d 343 (Court of Claims, 1964)

Cite This Page — Counsel Stack

Bluebook (online)
126 F. App'x 948, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bender-gmbh-v-secretary-of-the-army-cafc-2005.