Rda Construction Corp. v. United States

132 Fed. Cl. 732, 2017 U.S. Claims LEXIS 875, 2017 WL 3188428
CourtUnited States Court of Federal Claims
DecidedJuly 27, 2017
Docket11-555 C
StatusPublished
Cited by10 cases

This text of 132 Fed. Cl. 732 (Rda Construction Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rda Construction Corp. v. United States, 132 Fed. Cl. 732, 2017 U.S. Claims LEXIS 875, 2017 WL 3188428 (uscfc 2017).

Opinion

Accord and Satisfaction; Breach of Contract; Cardinal Change; Contract Disputes Act (“CDA”), 41 U.S.C. §§ 7101-7109; False Claims Act (“FCA”), 31 U.S.C. §§ 3729-3733; Federal Acquisition Regulations (“FAR”) 62.233-1 (Disputes), 62.236-2 (Differing Cite Conditions), 62.236-3 (Site Investigation and Conditions Affecting Work), 52.236-13(Acei-dent Prevention), 262.236-7001(Contract Drawings and Specifications), 62.249-10 (Default on Fixed-Price Construction Contract); Rule of the United States Court of Federal Claims (“RCFC”) 12(b)(1); Special Plea in Fraud, 28 U.S.C. § 2514; Tucker Act Jurisdiction over Contract Disputes, 28 U.S.C. § 1491(a)(2); United States Court of Federal Claims’ Jurisdiction to Adjudicate Government Set-Offs, 28 U.S.C. §§ 1503,2608.

POST TRIAL MEMORANDUM OPINION AND FINAL ORDER

SUSAN G. BRADEN, Chief Judge.

This post trial liability decision adjudicates a protracted dispute between RDA Construction Corp, (“RDA”) and the United States Department of the Navy, Naval Facilities Engineering Command (“the NAVFAC”), arising from an October 13, 2009 Contract, requiring RDA to demolish, remove, and construct a wharf at the Naval Station in Newport, Rhode Island (“Newport Naval Station”).

To facilitate review of this Post Trial Liability Memorandum Opinion And Order, the court has provided the following outline:

I.RELEVANT FACTUAL BACKGROUND.
A The Deteriorating And Dangerous Conditions At The Newport Naval Station Wharf.
B. On May 18, 2009, The Naval Facilities Command Issued Solicitation No. N40085-09-B-7002.
C. On June 4, 2009 and June 11, 2009, The Naval Facilities Command Conducted Two Site Visits Of The Newport Naval Station Wharf.
D. On June 30, 2009, RDA Construction Corp. Submitted A Bid.
E. On October 13, 2009, RDA Construction Corp. Signed Contract No. N40086-09-B-7002.
F. On November 18, 2009, The Apple-dore Report Was Disclosed To RDA Construction Corp.
G. On April 21, 2010, RDA Construction Corp, Filed A Certified Claim.
H. On May 17, 2010, The Naval Facilities Command Approved RDA Construction Corp.’s Baseline Schedule.
I. On August 31, 2010, RDA Construction Corp.’s April 21, 2010 Certified Claim Was Denied.
J. On September 20, 2010, RDA Construction Corp. Informed The Naval Facilities Command That Underground Obstructions Were Encountered, So Work Stopped.
K. On March 10, 2011, The Naval Facilities Command Instructed RDA To Submit A Cost Proposal To Remove The Obstructions And Continue Work.
L. In Late March 2011, RDA Construction Corp.’s Quality Control Manager And Site Safety Health Officer Quit.
M. On June 7, 2011 And August 19, 2011, The Naval Facilities Command Issued Contract Modifications 4 and 5 To The October 13, 2009 Contract.
N. On August 31, 2011, RDA Construction Corp. Filed A Complaint In The United States Court Of Federal Claims.
*742 O. On September 14, 2011, RDA Construction Corp. Experienced A Third Accident At The Project Site.
P. From Mai’ch 20, 2012 To November 8, 2012, The Naval Facilities Command Issued Contract Modifications 6-12.
Q. On February 21, 2013, The Naval Facility Command Terminated The October 13, 2009 Contract.
R. On July 3, 2013, RDA Construction Corp. Filed A Second Certified Claim.
S. On April 15, 2015, The Naval Facility Command’s Contracting Officer Determined That RDA Construction Corp. Was Liable For Liquidated Damages.
II. PROCEDURAL HISTORY.
III. DISCUSSION,
A Jurisdiction.
1. Whether The Claims Alleged In The May 7, 2015 Second Amended Complaint Arise Under The Contract Disputes Act.
2. Whether The Claims Alleged In The May 7, 2015 Second Amended Complaint Were Submitted To The Contracting Officer For A Final Decision.
a. Regarding Counts I-IV.
b. Regarding Counts V-IX.
c. Regarding Damages.
B. Standing.
C. The Claims Alleged In RDA Construction Corp.’s May 7, 2015 Second Amended Complaint.
1. Count I: Whether The Naval Facilities Command Had A Duty To Disclose The Appledore Report And The Fay, Spofford & Thorn-dike Report.
a. Plaintiffs Argument.
b. The Government’s Response.
c. Plaintiffs Reply.
d. The Court’s Resolution.
2. Count II: Whether RDA Construction Corp. Is Entitled To An Equitable Adjustment Under The October 13, 2009 Contract’s Differing Site Conditions Clause.
a. Plaintiffs Argument.
b. The Government’s Response.
c. The Court’s Resolution.
3. Counts III And IV: Whether The Naval Facilities Command Misrepresented The Condition Of The Wharf And The Purpose Of The October 13,2009 Contract.
a. Plaintiffs Argument.
b. The Government’s Response.
c. The Court’s Resolution.
4. Count V: Whether The Naval Facilities Command’s November 7, 2012 Directive Was A Cardinal Change To The October 13, 2009 Contract.
a. Plaintiffs Argument.
b. The Government’s Response.
c. The Court’s Resolution.
5. Counts VI, VII and VIII: Whether The NAVFAC Violated The Duty Of Good Faith And Fair Dealing.
a. Plaintiffs Argument.
b. The Government’s Response.
c. The Court’s Resolution.
i.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
132 Fed. Cl. 732, 2017 U.S. Claims LEXIS 875, 2017 WL 3188428, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rda-construction-corp-v-united-states-uscfc-2017.