Itek Corporation v. The First National Bank of Boston, Bank Melli Iran

730 F.2d 19, 39 U.C.C. Rep. Serv. (West) 625, 1984 U.S. App. LEXIS 24260
CourtCourt of Appeals for the First Circuit
DecidedMarch 22, 1984
Docket83-1594
StatusPublished
Cited by71 cases

This text of 730 F.2d 19 (Itek Corporation v. The First National Bank of Boston, Bank Melli Iran) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Itek Corporation v. The First National Bank of Boston, Bank Melli Iran, 730 F.2d 19, 39 U.C.C. Rep. Serv. (West) 625, 1984 U.S. App. LEXIS 24260 (1st Cir. 1984).

Opinion

BREYER, Circuit Judge.

The First National Bank of Boston (“FNBB”), at the request of Itek Corp., issued several letters of credit running in favor of Bank Melli Iran (“Melli”). Melli demanded payment from FNBB of the money that the letters promised. Itek obtained a federal district court injunction (see 12 U.S.C. § 632) prohibiting FNBB from paying Melli, 566 F.Supp. 1210. Melli, the true party in interest, appeals. The basic question that Melli’s appeal presents is whether its effort to obtain the money by calling the letters is “fraudulent.” We find the district court’s affirmative answer to this question adequately supported. And we therefore affirm its decision to issue the injunction.

I

The following, somewhat simplified, account provides the necessary factual background:

a. The basic contract. The letters of credit arise out of promises made in a 1977 contract between Itek and Iran’s Imperial Ministry of War. The contract provided that Itek would make and sell high-technology optical equipment to the War Ministry at a price of $22.5 million. Iran was to make a twenty percent down payment ($4.5 million). It would pay Itek sixty percent of the total price ($13.5 million) as work progressed; it would pay the remaining forty percent upon satisfactory completion. The down payment amount would be deducted gradually from the payments due under Itek’s “work-in-progress” invoices. See Contract, Appendix 3, MI 1.1, 1.4.

b. The contract’s bank guarantees. The contract required Itek to provide two types of bank guarantees. The first, the “down payment” guarantee, was for $4.5 million, the amount of the down payment. Its object apparently was to give the Ministry the right to obtain return of the down payment (or portions of the down payment) until Itek produced work of sufficient value to have “earned” the down payment. The second, the “good performance” guarantee was for $2.25 million, ten percent of the contract price. Its object was to protect the Ministry against a breach of contract as might occur, for example, if the goods produced were defective. These guarantees were to be issued in favor of the Ministry by an approved Iranian bank. The Ministry could call for payment under the guarantees simply by submitting a written request for payment to the bank.

Bank Melli, an instrumentality of the Iranian government, issued the guarantees in the form of five “guarantee letters.” One letter was for $2.25 million; it backed “good performance.” The other four letters were each for $1.125 million; they backed the down payment. Melli, as a condition for issuing them, required Itek to provide it with five similar “standby” letters of credit, issued by an American bank *21 in Melli’s favor, and payable on Melli’s certification that the Ministry had required it to pay under its letters to the Ministry. The “standby” letters are the FNBB letters at issue here.

c. The contract’s procedures for cancelling the guarantees. The contract contains specified procedures and conditions governing the termination of the guarantees. It states that the Ministry is to release “down payment” guarantees “within 4 weeks after the clearance of down-payments amount.” Contract 11 9.5. It states that the Ministry is to release the “good performance” guarantee four weeks after its final acceptance of the goods.

The contract provided for another circumstance, directly relevant here, under which the Ministry was to release the “good performance” guarantee. If the contract “is cancelled due to Force Majeure ..., all Bank Guarantees of good performance of work will be immediately released.” Contract U 9.4. The contract defines “Force Majeure” to include cancellation by the United States of necessary export licenses. If force majeure occurs — if, for example, there is a war or a natural disaster, or if the United States cancels the export license — either party can cancel the contract. A party can cancel the contract on this basis, however, only if it has notified the other party of the occurrence of force majeure, the parties have been unable to agree to some resolution of the force majeure difficulty, and three months have passed since notification. The contract also stipulates that, if force majeure leads to cancellation of the contract, Itek will be paid for equipment shipped, for equipment then being manufactured, and for all services rendered to date.

The guarantee letters and the letters of credit backing them had various expiration dates. But both provided for extension upon the request of their respective beneficiaries. And some of them were apparently extended as their expiration dates approached, so that they would remain valid until the completion of the work they guaranteed. The standby letters of credit stated that they were extendable on request and that, if the issuer was “unwilling to extend” a letter, it became immediately payable. See, e.g., Record App. at 31.

d. The circumstances of cancellation. Itek’s work proceeded uneventfully until Iran’s government collapsed in early 1979. At that time Itek’s performance was ahead of schedule, but it had not yet delivered any equipment to Iran. By February 1979, Itek had billed Iran for more than $20 million. It had received the original down payment of $4.5 million and additional payments of $6.6 million — a total of $11.1 million. Iran had consequently released the down payment guarantees to the point where there remained outstanding but one full down payment letter in the amount of $1,125 million and one partial down payment letter in the amount of $70,753.

The change of government in Iran, however, brought with it a deterioration in Iranian/American relations. In April 1979 the United States suspended Itek’s export license. In May Itek notified Iran’s new Ministry of National Defense about this “force majeure” problem, and, in accordance with the contract’s terms, it called for consultations. These took place in Iran in August. Subsequently Itek applied for renewal of the suspended export license.

In November 1979 Iranians seized the United States Embassy in Teheran and took the Americans within it hostage. Given this fact, it is not surprising that, later that month, the United States refused to renew or to reissue the necessary export license. On December 6, 1979, Itek reported this fact to the Iranian Ministry and again invoked the contract’s force majeure clause and requested consultations. No consultations took place. On February 18 and March 4, 1980, Melli cabled FNBB requesting extensions of the two remaining down-payment letters of credit, which, by their terms, expired in mid-April. On March 7, 1980 (three months after Itek had told the Ministry about the new United States refusal to grant export licenses), Itek cancelled the contract in accordance with the force majeure provisions. About *22 one week later (on March 13) FNBB told Melli that it would not extend the down-payment letters of credit, for the contract, along with the guarantees that the letters backed, had been terminated.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Williams v. Fisher
S.D. California, 2023
(HC) Rodriguez v. Madden
E.D. California, 2023
Serna v. Lizarraga
N.D. California, 2022
(HC) Huston v. Campbell
E.D. California, 2022
Rda Construction Corp. v. United States
132 Fed. Cl. 732 (Federal Claims, 2017)
NH Hospital Assoc. v. US Department HHS
2016 DNH 053 (D. New Hampshire, 2016)
Hook Point, LLC v. Branch Banking & Trust Co.
725 S.E.2d 681 (Supreme Court of South Carolina, 2012)
Export-Import Bank v. United California Discount Corp.
738 F. Supp. 2d 1047 (C.D. California, 2010)
Lennar Homes, LLC v. v. VENTURES, LLC
988 So. 2d 660 (District Court of Appeal of Florida, 2008)
New Orleans Brass v. Whitney Nat. Bank
818 So. 2d 1057 (Louisiana Court of Appeal, 2002)
Intrinsic Values Corp. v. Superintendencia
806 So. 2d 616 (District Court of Appeal of Florida, 2002)
Hyosung America, Inc. v. Sumagh Textile Co., Ltd.
25 F. Supp. 2d 376 (S.D. New York, 1998)
3Com Corp. v. Banco De Brasil, S.A.
2 F. Supp. 2d 452 (S.D. New York, 1998)
Resolution Trust Corporation, as Receiver for Pioneer Federal Savings Bank v. United Trust Fund, Inc., a Corporation Organized and Existing Under the Laws of the State of Florida, Financial Federal Savings and Loan Association of Dade County, a Savings and Loan Association Conducting Business in Dade County, Liberty Bell Realty Associates Limited Partnership, Intervenor-Defendant. Resolution Trust Corporation, as Receiver for Pioneer Federal Savings Bank, Cross-Appellee v. United Trust Fund, Inc., a Corporation Organized and Existing Under the Laws of the State of Florida, Federal Home Loan Bank of Atlanta, Financial Federal Savings and Loan Association of Dade County, a Savings and Loan Association Conducting Business in Dade County, Liberty Bell Realty Associates Limited Partnership, Intervenor-Defendant. In Re Financial Federal Savings and Loan Association of Dade County, Resolution Trust Corporation, as Receiver for Pioneer Federal Savings Bank, Plaintiff-Counter-Defendant-Appellant, Cross-Appellee v. United Trust Fund, Inc., a Corporation Organized and Existing Under the Laws of the State of Florida, Federal Home Loan Bank of Atlanta, Financial Federal Savings and Loan Association of Dade County, a Savings and Loan Association Conducting Business in Dade County, Florida, Defendant-Cross-Claimant- Liberty Bell Realty Associates Limited Partnership, a New Jersey Limited Partnership, Intervenor-Defendant-Counter-Claimant, Cross-Defendant-Appellee-Cross- Resolution Trust Corporation, as Receiver for Pioneer Federal Savings Bank, Plaintiff-Counter-Defendant-Appellant v. United Trust Fund, Inc., a Corporation Organized and Existing Under the Laws of the State of Florida, Federal Home Loan Bank of Atlanta, Financial Federal Savings and Loan Association of Dade County, a Savings and Loan Association Conducting Business in Dade County, Florida, Defendant-Cross-Claimant-Appellee, Liberty Bell Realty Associates Limited Partnership, a New Jersey Limited Partnership, Intervenor-Counter-Claimant, Cross-Defendant-Appellee
57 F.3d 1025 (Eleventh Circuit, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
730 F.2d 19, 39 U.C.C. Rep. Serv. (West) 625, 1984 U.S. App. LEXIS 24260, Counsel Stack Legal Research, https://law.counselstack.com/opinion/itek-corporation-v-the-first-national-bank-of-boston-bank-melli-iran-ca1-1984.