United States v. Acme Process Equipment Co.

385 U.S. 138, 87 S. Ct. 350, 17 L. Ed. 2d 249, 1966 U.S. LEXIS 2752
CourtSupreme Court of the United States
DecidedJanuary 16, 1967
Docket86
StatusPublished
Cited by130 cases

This text of 385 U.S. 138 (United States v. Acme Process Equipment Co.) is published on Counsel Stack Legal Research, covering Supreme Court of the United States primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Acme Process Equipment Co., 385 U.S. 138, 87 S. Ct. 350, 17 L. Ed. 2d 249, 1966 U.S. LEXIS 2752 (1967).

Opinion

Mr. Justice Black

delivered the opinion of the Court.

The respondent, Acme Process Equipment Company, brought this action against the United States in the Court of Claims to recover damages for breach of a contract under which Acme undertook through itself and subcontractors to manufacture 2,751 75-mm. recoilless rifles for about $337 per rifle. Among other defenses, the United States alleged that it had rightfully canceled its contract with Acme because three of Acme's principal employees had accepted compensation for awarding subcontracts in violation of the Anti-Kickback Act set out *139 in part below. 1 The Court of Claims found, as facts, that the kickbacks had been paid as alleged and that this was the ground on which the United States had canceled the prime contract with Acme, but construed the Act as not authorizing the cancellation. 171 Ct. Cl. 324, 347 F. 2d 509. We hold that it does.

I.

In October 1952, Acme hired Harry Tucker, Jr., and his associate, James Norris, for the purpose of establishing and managing a new division of the company to handle government contracts. Norris was made general manager of production with authority to submit bids, sign government contracts, and award subcontracts. Tucker was placed in charge of sales, government con *140 tracts, and expediting subcontract operations. Prior to this time Tucker had entered into a contract with All Metals Industries, Inc., under which he was to receive a commission for all sales to customers, including Acme, procured by him. Tucker’s employment contract with Acme specifically stated that he represented and would continue to represent firms in other lines of business, but Acme did not consult with any of his other clients at the time Tucker was hired.

Late in October, Tucker advised his superiors at Acme of the proposed Army contract for rifles, and at Tucker’s suggestion, Acme submitted a bid of $337 per rifle. Since Acme’s bid was the lowest, the Army began negotiations with Acme culminating in the award of the contract in January 1953. The negotiations were handled by Tucker and Norris for Acme. Since it was contemplated that the project would be largely subcontracted, leaving to Acme only the final finishing and assembly of components, the Army expressed a keen interest in Acme’s proposed subcontractors. Not only did it review Acme’s subcontracting plans and require Acme to notify it of changes in those plans during the final stages of negotiation, but the contract eventually awarded required government approval of all subcontracts in excess of $25,000. All Metals, because its proposed subcontract amounted to one-third of the amount of the prime contract, actually participated in the negotiations between Acme and the Army.

During this period of negotiation two other developments took place. Tucker obtained agreements from two other potential subcontractors to pay him commissions on any orders he could procure from Acme. Army contracting officers warned Acme’s president, Joshua Epstein, that Tucker was suspected of having engaged in contingent-fee arrangements with other government contractors.

*141 Finally, Acme was awarded the prime contract. Although the price was fixed at $337 per rifle, the contract contained a price redetermination clause under which, after 30% of the rifles were delivered, the parties could negotiate the price on past and future shipments upward or downward, with an upper limit of $385 per rifle. Within a few weeks after the prime contract was awarded, All Metals and the other two companies with which Tucker had prior kickback arrangements obtained subcontracts from Acme. 2 Tucker was paid his kickbacks, but, apparently unsatisfied with the amount of his payoff, he got Jack Epstein, the superintendent of the chief Acme plant and the son of Acme’s president and principal stockholder, to join the kickback conspiracy. Together Epstein and Tucker threatened to cancel All Metals’ subcontract unless it paid $25,000 to a dummy corporation owned by Tucker, Norris, and Epstein for fictitious consulting services. All Metals reluctantly acceded to the shakedown. The amount paid to Tucker, Norris, and Epstein was charged to Acme through an increase in the subcontract price.

Although they knew that Tucker was representing other companies and had been notified of the Army’s suspicions of Tucker’s involvement in contingent-fee arrangements, other officials of Acme were not aware of the kickback activities of Tucker, Norris, and Epstein until late in 1953. At that time, Acme’s president caused the resignation of the three suspected officials.

In 1956 Tucker, Norris, and Epstein were indicted for violation of the then Anti-Kickback Act, 60 Stat. 37. 3 *142 After presentation of the Government’s case, the District Court granted the defendants’ motion for acquittal on the ground that the Act — which at that time embraced only “cost-plus-a-fixed-fee or other cost reimbursable” government contracts — did not apply to Acme’s contract, a fixed-price contract with a provision for limited price redetermination. The court found the defendants’ actions “despicable and morally reprehensible, but unfortunately within the narrow letter of the law.” The court recommended that Congress amend the Anti-Kickback Act “to include as a crime the vicious and immoral type of conduct that has been exhibited in this case.” United States v. Norris, Crim. No. 18535 (D. C. E. D. Pa.), April 14, 1956.

The District Court’s opinion did indeed spur the Comptroller General to recommend amendatory legislation and in 1960 the Anti-Kickback Act was amended to apply to all “negotiated contracts.” 4 The civil provision of the amended Act was made retroactive to allow government recovery of kickbacks “whether heretofore or hereafter paid or incurred by the subcontractor.”

II.

The Anti-Kickback Act, as originally passed in 1946 and as amended in 1960, provides two express sanctions for its violation: (1) fine or imprisonment for one who makes or receives a kickback, and (2) recovery of the kickback by the United States. The Court of Claims held, and it is argued here, that had Congress wanted “to provide the additional remedy of contract annulment, it could have done so” by express language, 171 Ct. Cl., at 343, 347 F. 2d, at 521, and of course it could *143 have. But the fact that it did not see fit to provide for such a remedy by express language does not end the matter. The Anti-Kickback Act not only “prohibited” such payments, but clearly expressed a policy decidedly hostile to them. They were recognized as devices hurtful to the Government’s procurement practices. Extra expenditures to get subcontracts necessarily add to government costs in cost-plus-a-fixed-fee and other cost reimbursable contracts. And this is also true where the prime contract is a negotiated fixed-price contract with a price redetermination clause, such as this prime contract is here.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sanders v. United States
Federal Claims, 2025
Supreme Foodservice GmbH
Armed Services Board of Contract Appeals, 2020
MedPricer.com, Inc. v. Becton, Dixon & Co.
240 F. Supp. 3d 263 (D. Connecticut, 2017)
Laguna Construction Company v. Defense
828 F.3d 1364 (Federal Circuit, 2016)
Steele v. United States
159 F. Supp. 3d 73 (District of Columbia, 2016)
Laguna Construction Company, Inc.
Armed Services Board of Contract Appeals, 2014
Jack's Canoes & Kayaks, LLC v. National Park Service
933 F. Supp. 2d 58 (District of Columbia, 2013)
United States v. BNP Paribas SA
884 F. Supp. 2d 589 (S.D. Texas, 2012)
Kellogg Brown & Root Services, Inc. v. United States
99 Fed. Cl. 488 (Federal Claims, 2011)
Chenega Management, LLC v. United States
96 Fed. Cl. 556 (Federal Claims, 2010)
Amber Resources Co. v. United States
538 F.3d 1358 (Federal Circuit, 2008)
Cumberland Casualty & Surety Co. v. United States
82 Fed. Cl. 500 (Federal Claims, 2008)
Daewoo Engineering & Construction Co. v. United States
73 Fed. Cl. 547 (Federal Claims, 2006)
George Sollitt Construction Co. v. United States
64 Fed. Cl. 229 (Federal Claims, 2005)
R.P. Wallace, Inc. v. United States
63 Fed. Cl. 402 (Federal Claims, 2004)
Old Stone Corp. v. United States
63 Fed. Cl. 65 (Federal Claims, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
385 U.S. 138, 87 S. Ct. 350, 17 L. Ed. 2d 249, 1966 U.S. LEXIS 2752, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-acme-process-equipment-co-scotus-1967.