Laguna Construction Company v. Defense

828 F.3d 1364, 2016 U.S. App. LEXIS 12981, 2016 WL 3854063
CourtCourt of Appeals for the Federal Circuit
DecidedJuly 15, 2016
Docket2015-1291
StatusPublished
Cited by35 cases

This text of 828 F.3d 1364 (Laguna Construction Company v. Defense) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Laguna Construction Company v. Defense, 828 F.3d 1364, 2016 U.S. App. LEXIS 12981, 2016 WL 3854063 (Fed. Cir. 2016).

Opinion

HUGHES, Circuit Judge.

Laguna Construction Company was awarded a government contract in 2003 to perform work in Iraq. After the work was completed, Laguna sought reimbursement of past costs, a portion of which the government refused to pay. Laguna sued the government for these costs at the Armed Services Board of Contract Appeals. The government alleged that it was not liable because Laguna had committed a prior material breach by accepting subcontractor kickbacks, thereby excusing the government’s nonperformance. The Board granted the government’s motion for summary judgment on this ground, and declined to consider the merits of Laguna’s motion. Because we agree that Laguna committed the first material breach by violating the contract’s Allowable Cost and Payment clause, we affirm.

I

In November 2003, the government awarded Contract No. FA8903-04-D-8690, one of twenty-seven contracts for Worldwide Environmental Remediation and Construction (WERC), to Laguna Construction Company, Inc. (Laguna). The contract is governed by the Contract Disputes Act (CDA), and incorporates by reference certain Federal Acquisition Regulation (FAR) contract clauses. Under the contract, La-guna received sixteen cost-reimbursable task orders to perform work in Iraq, and awarded subcontracts to a number of subcontractors. The physical work under the contract was completed by 2010. The issue on appeal concerns the government’s failure to pay fourteen vouchers that Laguna submitted in 2011 for taxes owed to Pueblo of Laguna and other incurred costs, including $24,000 of subcontract charges.

In February 2009, the Defense Contract Audit Agency (DCAA) began an audit of Laguna’s incurred costs for fiscal year 2006. In 2011, the DCAA disapproved approximately $17.8 million of subcontract costs due to insufficient support proving that the government paid a fair and reasonable price for the services subcontracted. In April 2012, the DCAA rejected a portion of these costs, which comprised the fourteen Laguna vouchers at issue, totaling $3,031,925. Laguna submitted a claim on the rejected vouchers for $2,874,081. Laguna properly submitted a notice of appeal to the Armed Services Board of Contract Appeals (Board) after the Administrative Contracting Officer did not issue a decision.

Meanwhile, in January 2008, the government had begun investigating allegations that Laguna’s employees were engaged in kickback schemes with its subcontractors. In October 2010, Laguna’s project manager, Ismael Salinas, pleaded guilty to conspiracy to pay or receive kickbacks in violation of 18 U.S.C. § 371, to conspiracy to defraud the United States, and to violations of 41 U.S.C. § 53, the Anti-Kickback *1367 Act. Mr. Salinas admitted that from April 2005 to March 2008, he worked with subcontractors to submit inflated invoices to Laguna for reimbursement by the government, and profited from the difference. Additionally, in February 2012, a federal grand jury in the District of New Mexico issued a criminal indictment against three principal officers of Laguna — Neal D. Kas-per, Bradley G. Christiansen, and Tiffany White — alleging that they received kickbacks for awarding subcontracts. The United States Attorney for the District of New Mexico filed a separate criminal information against Mr. Christiansen, the Executive Vice President and Chief Operating Officer of Laguna, for conspiring to defraud the United States by participating in a kickback scheme from December 2004 to February 2009. On July 2, 2013, Mr. Christiansen pleaded guilty to the indictment.

After Mr. Christiansen’s guilty plea, the government moved to amend its answer in the Board appeal to include the affirmative defense of fraud. The Board granted the government’s motion to amend over Lagu-na’s objection. Appeal of Laguna Constr. Co., Inc., ASBCA No. 58324, 13 BCA ¶ 35,-464. In the government’s amended answer, the government alleged that it “is not liable for LCC’s claim ... because of LCC’s breach of Contract No. FA8903-04-D8690 when its principal officers and employees solicited and accepted kickbacks for awarding subcontracts under task orders issued under that contract, which constituted fraud against the United States.” Id.

Laguna filed a motion for summary judgment, arguing that the government is not authorized to withhold funds where it has accepted the subcontractor prices as reasonable during contract performance and that any claims are barred by the statute of limitations. Laguna also alleged that the government had improperly imposed a monetary penalty for alleged deficiencies in Laguna’s files. The government filed a cross-motion for summary judgment, arguing that Laguna’s claim should be denied because Laguna committed the first material breach of contract by the fraud of its employees.

The Board agreed with the government and declined to consider the merits of La-guna’s motion. The Board held that the “well settled principle of antecedent breach” is articulated in Christopher Village, L.P. v. United States, 360 F.3d 1319, 1334 (Fed.Cir.2004), and that Laguna “committed the first material breach under this contract, which provided the government with a legal excuse for not paying [Laguna’s] invoices.” J.A. 13. The Board concluded that Laguna breached the duty of good faith and fair dealing because its employees’ criminal acts in engaging in a kickback scheme were imputed to Laguna. The Board also found that Laguna breached the Allowable Cost and Payment clause in the contract because its vouchers were improperly inflated to include the payment of kickbacks. Id. The Allowable Cost and Payment clause, incorporated as FAR 52.216-7, states that a cost is allowable only when it is reasonable and complies with the terms of the contract.

The Board found that the breaches were material because kickbacks are fraudulent. Id. at 14. Further, “[t]hat the government has not proven that kickbacks were paid under every TO [task order] or under every voucher does not render the fraud any less material.” Id. (citing Joseph Morton Co., Inc. v. United States, 757 F.2d 1273, 1278 (Fed.Cir.1985)).

Laguna appeals the Board’s decision, arguing that the Board did not have jurisdic *1368 tion over the government’s affirmative defense of fraud, and in the alternative, that the Board erred in granting the government’s summary judgment motion. We have jurisdiction under 28 U.S.C. § 1295(a).

II

We review the Board’s legal conclusions without deference, and must accept findings of fact unless they are fraudulent, arbitrary or capricious, so grossly erroneous as to necessarily imply bad faith, or not supported by substantial evidence. Ryste & Ricas, Inc. v. Harvey,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kellogg Brown & Root Services, Inc.
Armed Services Board of Contract Appeals, 2023
Frazier Investments, Inc. d/b/a Optimum Construction
Armed Services Board of Contract Appeals, 2023
Nauset Construction Corporation
Armed Services Board of Contract Appeals, 2021
Mountain Movers/Ainsworth-Benning, LLC
Armed Services Board of Contract Appeals, 2020
Sand Point Services, LLC
Armed Services Board of Contract Appeals, 2019
ECC CENTCOM Constructors, LLC
Armed Services Board of Contract Appeals, 2018
Raytheon Company
Armed Services Board of Contract Appeals, 2018
Securiforce International America, LLC v. United States
879 F.3d 1354 (Federal Circuit, 2018)
SST (Supply & Service Team) GmbH
Armed Services Board of Contract Appeals, 2017
Rashed Elham Trading Company
Armed Services Board of Contract Appeals, 2017

Cite This Page — Counsel Stack

Bluebook (online)
828 F.3d 1364, 2016 U.S. App. LEXIS 12981, 2016 WL 3854063, Counsel Stack Legal Research, https://law.counselstack.com/opinion/laguna-construction-company-v-defense-cafc-2016.