Ryste & Ricas, Inc. v. Francis J. Harvey, Secretary of the Army

477 F.3d 1337, 2007 U.S. App. LEXIS 3481, 2007 WL 489472
CourtCourt of Appeals for the Federal Circuit
DecidedFebruary 16, 2007
Docket06-1196
StatusPublished
Cited by9 cases

This text of 477 F.3d 1337 (Ryste & Ricas, Inc. v. Francis J. Harvey, Secretary of the Army) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ryste & Ricas, Inc. v. Francis J. Harvey, Secretary of the Army, 477 F.3d 1337, 2007 U.S. App. LEXIS 3481, 2007 WL 489472 (Fed. Cir. 2007).

Opinion

SCHALL, Circuit Judge.

Ryste & Ricas, Inc. (“RRI”) appeals the final decision of the Armed Services Board of Contract Appeals (“Board”) in Ryste & Ricas, Inc., 06-1 B.C.A. (CCH) ¶ 33,124 (A.S.B.C.A. Nov. 10, 2005). In its decision, the Board granted summary judgment in favor of the Department of the Army (“Army”), ruling that RRI’s termination settlement proposal was not timely filed under 48 C.F.R. § 52.259-2(e). Ryste & Ricas, Inc., 06-1 B.C.A. (CCH) ¶ 33,124. We affirm.

BACKGROUND

I.

On September 29, 1997, the Army awarded RRI a contract for the repair and renovation of a building located at Fort Belvoir, Virginia. The Contract Disputes Act (“CDA”), 41 U.S.C. § 602(a), governed the contract. 1

Effective August 14,1998, the Army terminated RRI’s contract for default. RRI timely appealed the default termination to the Board. On May 29, 2002, the Board issued a decision converting the termination for default to a termination for the convenience of the government. Ryste & Ricas, Inc., 02-2 B.C.A. (CCH) ¶ 31,883 (A.S.B.C.A. May 29, 2002). Counsel for RRI received the Board’s decision on June 8, 2002.

When a contract is terminated for the convenience of the government, the contractor may submit a termination settlement proposal within one year from the effective date of termination. Federal Acquisition Regulation (“FAR”) § 52.249-2(e), 48 C.F.R. § 52.249-2(e). A settlement proposal is “a proposal for effecting settlement of a contract terminated in whole or in part, submitted by a contractor or subcontractor in the form, and supported by the data, required by this part.” FAR § 49.001, 48 C.F.R. § 49.001. RRI asserted that, following the Board’s decision, it submitted a termination settlement proposal to the contracting officer on July 23, 2003. The Army, however, maintained that it did not receive the proposal. Having received no response from the Army regarding its termination settlement proposal, RRI resubmitted the proposal on October 23, 2003. RRI never received a response from the Army concerning the proposal. It therefore appealed the contracting officer’s deemed denial to the Board under 41 U.S.C. § 605(c)(5). 2

II.

On August 13, 2004, the Army moved for summary judgment before the Board. In *1339 its motion, the Army contended that RRI’s termination settlement proposal was untimely filed under FAR § 52.249-2(e). 3 The Army argued that RRI’s termination settlement proposal, regardless of whether it was submitted on July 23, 2003, or October 23, 2003, was time-barred because RRI had failed to submit the proposal within one year of when its previous counsel received the Board’s decision on June 8, 2002.

In opposing the Army’s motion, RRI contended that summary judgment should be denied because the date when RRI submitted its termination settlement proposal was disputed. In addition, RRI argued that that the “effective date of termination” under FAR § 49.001 (now FAR § 2.101) 4 was September 29, 2002, the date following the expiration of the period for seeking an appeal, rather than June 8, 2002, the date RRI’s previous counsel received the Board’s decision. RRI relied on Melkonyan v. Sullivan, 501 U.S. 89, 111 S.Ct. 2157, 115 L.Ed.2d 78 (1991), and Melka Marine, Inc. v. United States, 29 Fed.Appx. 594 (Fed.Cir.2002) (unpublished decision), two cases decided under the Equal Access to Justice Act (“EAJA”), as well as Houser v. United States, 12 Cl.Ct. 454 (1987), a case decided under the Uniform Relocation Act (“URA”), to argue that the effective date of termination was the date when the period for appealing the Board’s decision converting the termination for default to a termination for the convenience of the government expired.

On November 14, 2005, the Board issued its final decision, granting the Army’s motion for summary judgment. Ryste & Ri-cas, Inc., 06-1 B.C.A. (CCH) ¶ 33,124, at 164,148. The Board determined that the effective date of termination under FAR § 49.001 (now FAR § 2.101) was June 8, 2003, when RRI’s previous counsel received the Board’s decision converting the termination for default to a termination for the convenience of the government. Id. at 164,147. The Board, in rejecting RRI’s argument that the effective date of termination was when the appeal period expired, stated that “[w]e see no reason to engraft the requirements of [the EAJA and URA] onto the straightforward procedure for submission of termination for convenience settlement proposals,” adding that “it would be odd to import a tolling provision from EAJA or the [URA] when the court of appeals has already recognized that the time limits for submission of termination settlement proposals are ‘[a]part from the requirements of the CDA.’” Id. (citing England v. Swanson Group, Inc., 353 F.3d 1375, 1377 (Fed.Cir. 2004)). Additionally, the Board noted that it did not have to resolve whether the *1340 proposal was submitted on July 23, 2003, or on October 23, 2003, because the undisputed material facts were that RRI “neither submitted its proposal by June 9, 2003 [ (one year from the effective date of termination) ], nor requested an extension by that date.” Id. at 164,648. Accordingly, the Board dismissed RRI’s appeal as untimely. Id.

RRI timely appealed the Board’s decision to this court on January 25, 2006. We have jurisdiction pursuant to 28 U.S.C. § 1295(a)(10).

DISCUSSION

Under the CDA, we review legal conclusions of the ASBCA without deference. 41 U.S.C. § 609(b); England v. Contel Advanced Sys., Inc., 384 F.3d 1372, 1377 (Fed.Cir.2004). We must accept the ASBCA’s findings of fact unless they are: (1) fraudulent; (2) arbitrary or capricious; (3) so grossly erroneous as to necessarily imply bad faith; or (4) not supported by substantial evidence. 41 U.S.C. § 609(b); Contel Advanced Sys., Inc., 384 F.3d at 1377.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lessors of Abchakan Village v. Defense
137 F.4th 1301 (Federal Circuit, 2025)
Transportation v. Eagle Peak Rock & Paving, Inc.
69 F.4th 1367 (Federal Circuit, 2023)
South Carolina Public Service Authority
Armed Services Board of Contract Appeals, 2020
Abdul Khabir Construction Co.
Armed Services Board of Contract Appeals, 2018
American Boys Construction Company
Armed Services Board of Contract Appeals, 2018
Black Bear Construction Company
Armed Services Board of Contract Appeals, 2017
Laguna Construction Company v. Defense
828 F.3d 1364 (Federal Circuit, 2016)
Metric Construction Co. v. United States
83 Fed. Cl. 446 (Federal Claims, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
477 F.3d 1337, 2007 U.S. App. LEXIS 3481, 2007 WL 489472, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ryste-ricas-inc-v-francis-j-harvey-secretary-of-the-army-cafc-2007.