Rex Systems, Inc.,appellant v. William S. Cohen, Secretary of Defense

224 F.3d 1367, 2000 U.S. App. LEXIS 23216, 2000 WL 1292620
CourtCourt of Appeals for the Federal Circuit
DecidedSeptember 14, 2000
Docket99-1527
StatusPublished
Cited by34 cases

This text of 224 F.3d 1367 (Rex Systems, Inc.,appellant v. William S. Cohen, Secretary of Defense) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rex Systems, Inc.,appellant v. William S. Cohen, Secretary of Defense, 224 F.3d 1367, 2000 U.S. App. LEXIS 23216, 2000 WL 1292620 (Fed. Cir. 2000).

Opinion

MICHEL, Circuit Judge.

Rex Systems, Inc. (“RSI”) appeals from a decision of the Armed Services Board of Contract Appeals (“Board”) granting summary judgment for the government and denying RSI’s appeal from a Contracting Officer’s denial of its claim for interest on amounts paid under a termination for convenience settlement. The Board issued its initial decision on December 21, 1998, Appeal of Rex Systems, Inc., ABSCA No. 49502 (Dec. 21, 1998), and affirmed its original ruling on April 20, 1999. Appeal of Rex Systems, Inc., ABSCA No. 49502 (Apr. 20, 1999) (reconsideration). After the government terminated a contract with RSI for convenience, the government and RSI agreed upon a settlement amount related to the termination. RSI then filed a claim seeking interest on the settlement amount. RSI argued that that interest was due because its termination settlement proposal had ripened into a claim under the Contract Disputes Act (“CDA”) when the parties allegedly reached an impasse in the settlement negotiations. The Board held, however, that RSI failed to establish that it had a claim upon which interest was due, as the evidence demonstrated that there was no impasse in the negotiations. Because we hold that there cannot have been an impasse when the parties actually signed a settlement agreement, the government was indeed entitled to summary judgment. Therefore, we affirm the Board’s decision.

BACKGROUND

On July 29, 1991, the Army awarded a firm-fixed-price contract to RSI for the delivery of 50 computer and memory assemblies at a total contract price of $68,-950. The contract included the April 1984 version of the Federal Acquisition Regulation (“FAR”) “Termination for Convenience of the Government (Fixed Price)” clause. 48 C.F.R. § 52.249-2 (Fixed Price). On July 14, 1992, the Contracting Officer notified RSI by letter that the government was terminating the contract for convenience. The letter was accompanied by a contract modification of the same date. The government also sent a letter of instruction to RSI assigning settlement of RSI’s termination costs to the Chicago-Milwaukee contract administration office.

On March 9, 1993, RSI submitted the termination settlement proposal at issue to the Termination Contracting Officer (“TCO”). On April 22, 1993, the Defense Contract Audit Agency (“DCAA”) issued its audit report for the RSI proposal. The audit questioned several elements of RSI’s asserted termination costs. On May 10, 1993, RSI representative Darwin Kulzer submitted a letter to the TCO regarding the status of numerous RSI termination settlement proposals, including the one at issue in this appeal. Although the letter states that RSI would “consider [the TCO’s] correspondence and statements as [the TCO’s] final decision,” the letter does not make such a statement with reference to the instant termination settlement proposal. The only statement in the letter regarding the termination settlement proposal for the contract at issue is:

This termination settlement proposal was audited by DCAA and prenegotiation discussions have occurred with the TCO. Production material and profit/loss calculations are in dispute. A partial payment request is pending. DCAA states that the audit was complete in April.

RSI president Philip Brenizer had a conversation with the TCO on May 4, 1993, in which he allegedly requested that the TCO either “immediately negotiate a settlement or issue a contracting officer’s final decision.” The May 10 letter from Kulzer memorializing this conversation characterizes Brenizer’s request not as relating to the instant RSI termination settlement proposal, but rather as regarding a claim for equitable adjustment. Brenizer also *1370 reported that in the same May 4 conversation the TCO stated her willingness to issue a partial payment of 90% of the termination costs recommended by the DCAA. That payment was issued on June 21,1993.

On July 6, 1993, RSI notified the TCO that it needed to revise its termination settlement proposal because it had not yet resolved the settlement proposal with its subcontractor. On August 10, 1993, RSI sent the TCO a listing of the status of various settlement proposals. The letter references the instant termination proposal indicating:

There has been no change in the settlement status of this termination proposal since RSI’s last status report May 10, 1993.RSI is updating the termination proposal to include the [ ]subcontract termination settlement. This update will be submitted on August 11, 1993. This termination proposal was audited by DCAA and prenegotiation discussions have occurred with the TCO. Production material and profit loss calculations are in dispute. Please schedule a negotiation session by August 20, 1993.

(emphasis added). On September 9, 1993, RSI sent a letter regarding its various open termination proposals. With regard to the instant termination settlement proposal, the letter generally requested a meeting to develop “guidelines and timetables for negotiations of our unresolved claims.” The TCO and the RSI president met on September 29, 1993. Following that meeting, RSI submitted revised inventory and cost information. The letter accompanying this revision stated, “[T]his information is being submitted as prescribed at the meeting ... and should be used by the TCO during negotiations.” Appendix at 110 (emphasis added). A series of seven negotiation meetings were held between December 1993 and March 1994. A letter of September 13, 1994 from RSI notes, with regard to the instant termination settlement proposal, that “plant clearance is not completed at this time.” Between the Fall of 1994 and September 1995, RSI and the Army engaged in several litigations before the Board concerning other contracts; however, no attempt was made to begin formal dispute proceedings with regard to the termination settlement proposal at issue here.

On September 18, 1995, the parties reached a termination settlement with respect to the instant contract in the amount of $52,275.13. The parties disagreed about whether interest was owed to RSI but agreed to set the issue aside for a subsequent claim. RSI submitted its interest claim on December 1, 1995, and the Contracting Officer issued a final decision denying the claim on December 12, 1995.

RSI appealed the Contracting Officer’s final decision to the Board. The Board held that it was “unable to conclude that the parties had reached an impasse,” finding that RSI “made no request for a contracting officer’s decision or took any other action which we can regard as implicitly manifesting a desire for such a decision.” The Board specifically rejected RSI’s assertion that the May 10, 1993 letter was a request for a decision, finding that the language quoted by RSI “pertained to another of the parties’ contracts.”

On petition for reconsideration by the Board, RSI again asserted that the May 10 letter established a clear nexus between its request for a final decision regarding the equitable adjustment claim under the contract at issue and the instant termination settlement proposal. The Board reaffirmed its initial decision, holding that RSI failed to present evidence establishing that “despite the desire to settle, an impasse has been reached and the contractor is ready to begin the dispute process.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

AeroKool Aviation Corp.
Armed Services Board of Contract Appeals, 2023
JAAAT Technical Services, LLC
Armed Services Board of Contract Appeals, 2021
The Boeing Company v. Secretary of the Air Force
983 F.3d 1321 (Federal Circuit, 2020)
cooper/ports America, LLC v. Secretary of Defense
959 F.3d 1373 (Federal Circuit, 2020)
Air Services, Inc.
Armed Services Board of Contract Appeals, 2015
JRS Management v. Lynch
621 F. App'x 978 (Federal Circuit, 2015)
Ensign-Bickford Aerospace & Defense Company
Armed Services Board of Contract Appeals, 2014
Rollock Company v. United States
115 Fed. Cl. 317 (Federal Claims, 2014)
Systems Development Corp. v. McHugh
658 F.3d 1341 (Federal Circuit, 2011)
Oregon Woods, Inc. v. Secretary of the Interior
355 F. App'x 403 (Federal Circuit, 2009)
Grumman Aerospace Corporation v. Wynne
497 F.3d 1350 (Federal Circuit, 2007)
Sarang Corp. v. United States
76 Fed. Cl. 560 (Federal Claims, 2007)
Ryste & Ricas v. Harvey
Federal Circuit, 2007
Bannum, Inc. v. United States
121 F. App'x 849 (Federal Circuit, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
224 F.3d 1367, 2000 U.S. App. LEXIS 23216, 2000 WL 1292620, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rex-systems-incappellant-v-william-s-cohen-secretary-of-defense-cafc-2000.