Ryste & Ricas v. Harvey

CourtCourt of Appeals for the Federal Circuit
DecidedFebruary 16, 2007
Docket2006-1196
StatusPublished

This text of Ryste & Ricas v. Harvey (Ryste & Ricas v. Harvey) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ryste & Ricas v. Harvey, (Fed. Cir. 2007).

Opinion

United States Court of Appeals for the Federal Circuit

06-1196

RYSTE & RICAS, INC.,

Appellant,

v.

Francis J. Harvey, SECRETARY OF THE ARMY,

Appellee.

James S. DelSordo, Cohen Mohr, LLP, of Washington, DC, argued for appellant.

Michael S. Dufault, Trial Attorney, Commercial Litigation Branch, Civil Division, United States Department of Justice, of Washington, DC, argued for appellee. With him on the brief were Peter D. Keisler, Assistant Attorney General; David M. Cohen, Director; and Bryant G. Snee, Assistant Director.

Appealed from: United States Armed Services Board of Contract Appeals

Administrative Judge Alexander Younger United States Court of Appeals for the Federal Circuit

__________________________

DECIDED: February 16, 2007 __________________________

Before NEWMAN, SCHALL, and BRYSON, Circuit Judges.

SCHALL, Circuit Judge.

Ryste & Ricas, Inc. (“RRI”) appeals the final decision of the Armed Services

Board of Contract Appeals (“Board”) in Ryste & Ricas, Inc., 06-1 B.C.A. (CCH) ¶ 33,124

(A.S.B.C.A. Nov. 14, 2005). In its decision, the Board granted summary judgment in

favor of the Department of the Army (“Army”), ruling that RRI’s termination settlement

proposal was not timely filed under 48 C.F.R. § 52.259-2(e). Ryste & Ricas, Inc., 06-1

B.C.A. (CCH) ¶ 33,124. We affirm. BACKGROUND

I.

On September 29, 1997, the Army awarded RRI a contract for the repair and

renovation of a building located at Fort Belvoir, Virginia. The Contract Disputes Act

(“CDA”), 41 U.S.C. § 602(a), governed the contract.1

Effective August 14, 1998, the Army terminated RRI’s contract for default. RRI

timely appealed the default termination to the Board. On May 29, 2002, the Board

issued a decision converting the termination for default to a termination for the

convenience of the government. Ryste & Ricas, Inc., 02-2 B.C.A. (CCH) ¶ 31,883

(A.S.B.C.A. May 29, 2002). Counsel for RRI received the Board’s decision on June 8,

2002.

When a contract is terminated for the convenience of the government, the

contractor may submit a termination settlement proposal within one year from the

effective date of termination. Federal Acquisition Regulation (“FAR”) § 52.249-2(e), 48

C.F.R. § 52.249-2(e). A settlement proposal is “a proposal for effecting settlement of a

contract terminated in whole or in part, submitted by a contractor or subcontractor in the

form, and supported by the data, required by this part.” FAR § 49.001, 48 C.F.R.

§ 49.001. RRI asserted that, following the Board’s decision, it submitted a termination

settlement proposal to the contracting officer on July 23, 2003. The Army, however,

maintained that it did not receive the proposal. Having received no response from the

Army regarding its termination settlement proposal, RRI resubmitted the proposal on

1 The CDA applies to contracts for (1) the procurement of property, other than real property in being; (2) the procurement of services; (3) the procurement of construction, alteration, repair or maintenance of real property; and (4) the disposal of personal property. 41 U.S.C. § 602(a).

06-1196 2 October 23, 2003. RRI never received a response from the Army concerning the

proposal. It therefore appealed the contracting officer’s deemed denial to the Board

under 41 U.S.C. § 605(c)(5).2

II.

On August 13, 2004, the Army moved for summary judgment before the Board.

In its motion, the Army contended that RRI’s termination settlement proposal was

untimely filed under FAR § 52.249-2(e).3 The Army argued that RRI’s termination

settlement proposal, regardless of whether it was submitted on July 23, 2003, or

October 23, 2003, was time-barred because RRI had failed to submit the proposal

within one year of when its previous counsel received the Board’s decision on June 8,

In opposing the Army’s motion, RRI contended that summary judgment should

be denied because the date when RRI submitted its termination settlement proposal

was disputed. In addition, RRI argued that that the “effective date of termination” under

FAR § 49.001 (now FAR § 2.101)4 was September 29, 2002, the date following the

expiration of the period for seeking an appeal, rather than June 8, 2002, the date RRI’s

previous counsel received the Board’s decision. RRI relied on Melkonyan v. Sullivan,

501 U.S. 89 (1991), and Melka Marine, Inc. v. United States, 29 Fed. Appx. 594 (Fed.

Cir. 2002) (unpublished decision), two cases decided under the Equal Access to Justice

2 41 U.S.C. § 605(c)(5) provides, in relevant part:

Any failure by the contracting officer to issue a decision on a contract claim within the period required will be deemed to be a decision by the contracting officer denying the claim and will authorize the commencement of the appeal or suit on the claim as otherwise provided in this Act.

06-1196 3 Act (“EAJA”), as well as House v. United States, 12 Cl. Ct. 454 (1987), a case decided

under the Uniform Relocation Act (“URA”), to argue that the effective date of termination

was the date when the period for appealing the Board’s decision converting the

termination for default to a termination for the convenience of the government expired.

On November 14, 2005, the Board issued its final decision, granting the Army’s

motion for summary judgment. Ryste & Ricas, Inc., 06-1 B.C.A. (CCH) ¶ 33,124, at

164,148. The Board determined that the effective date of termination under FAR

§ 49.001 (now FAR § 2.101) was June 8, 2003, when RRI’s previous counsel received

the Board’s decision converting the termination for default to a termination for the

convenience of the government. Id. at 164,147. The Board, in rejecting RRI’s

argument that the effective date of termination was when the appeal period expired,

stated that “[w]e see no reason to engraft the requirements of [the EAJA and URA] onto

the straightforward procedure for submission of termination for convenience settlement

proposals,” adding that “it would be odd to import a tolling provision from EAJA or the

[URA] when the court of appeals has already recognized that the time limits for

(Cont’d. . . .) 3 The pertinent language of FAR § 52.249-2(e), 48 C.F.R. § 52.249-2(e), is as follows:

After termination, the Contractor shall submit a final termination settlement proposal to the Contracting Officer in the form and with the certification prescribed by the Contracting Officer. The Contractor shall submit the proposal promptly, but no later than 1 year from the effective date of termination, unless extended in writing by the Contracting Officer upon written request of the Contractor within this 1-year period. 4 FAR § 2.101 states that the “effective date of termination means the date on which the notice of termination requires the contractor to stop performance under the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Flexfab, L.L.C. v. United States
424 F.3d 1254 (Federal Circuit, 2005)
Mingus Constructors, Inc. v. The United States
812 F.2d 1387 (Federal Circuit, 1987)
Melkonyan v. Sullivan
501 U.S. 89 (Supreme Court, 1991)
Melka Marine, Inc. v. United States
29 F. App'x 594 (Federal Circuit, 2002)
Houser v. United States
12 Cl. Ct. 454 (Court of Claims, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
Ryste & Ricas v. Harvey, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ryste-ricas-v-harvey-cafc-2007.