Gordon R. England, Secretary of the Navy v. The Swanson Group, Inc.

353 F.3d 1375, 2004 U.S. App. LEXIS 259, 2004 WL 42115
CourtCourt of Appeals for the Federal Circuit
DecidedJanuary 9, 2004
Docket03-1051
StatusPublished
Cited by101 cases

This text of 353 F.3d 1375 (Gordon R. England, Secretary of the Navy v. The Swanson Group, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gordon R. England, Secretary of the Navy v. The Swanson Group, Inc., 353 F.3d 1375, 2004 U.S. App. LEXIS 259, 2004 WL 42115 (Fed. Cir. 2004).

Opinion

SCHALL, Circuit Judge.

Gordon R. England, Secretary of the Navy (“Navy” or “government”), appeals the decision of the Armed Services Board of Contract Appeals (“Board”) that awarded $278,076.25 in termination settlement costs to The Swanson Group, Inc. (“Swanson”). Swanson Group, Inc., 02-2 B.C.A. (CCH) ¶ 31,906 (A.S.B.C.A. July 1, 2002). The government asserts that the Board lacked jurisdiction over Swanson’s appeal because Swanson failed to present to the contracting officer a “claim” within the meaning of the Contract Disputes Act (“CDA”), 41 U.S.C. §§ 601-613 (2000). We agree. We therefore vacate the Board’s decision and remand the case to the Board with the instruction that it dismiss Swanson’s appeal for lack of jurisdiction.

BACKGROUND

I.

On December 20, 1991, Swanson was awarded a contract by the Western Division of the Naval Facilities Engineering Command. Under the contract, Swanson was required to provide guard services at the Long Beach Naval Shipyard in California. Swanson Group, Inc., 98-2 B.C.A. (CCH) ¶ 29,896, at 147,988 (A.S.B.C.A. Nov.7, 1997). • The contract had a monthly price of $203,457.73 (prorated from a yearly price of $2,441,492.70) and was scheduled to end on September 30, 1992. Swanson Group, Inc., 02-1 B.C.A. (CCH) ¶ 31,836, at 157,288 (A.S.B.C.A. Mar.28, 2002).

*1377 On April 24, 1992, the contracting officer directed Swanson to cure what the Navy perceived to be Swanson’s failure to comply with the terms of the contract. Swanson Group, 98-2 B.C.A. (CCH) ¶ 29,896, at 147,992-93. In his cure notice, the contracting officer stated that Swanson had failed to properly guard certain posts and had failed to provide a sufficient number of qualified guards at the facility. Id. at 147,991-92. On April 27, 1992, the contracting officer issued a final decision'terminating the contract for default, stating that Swanson had “failed to comply with the terms of the contract and [had] failed to meet the conditions identified in the [cure notice] letter.” Id. at 147,993. Swanson timely appealed the default termination to the Board. Id. On November 7, 1997, the Board issued a decision converting the termination for default to a termination for convenience. Id. at 147,-988-95. Swanson received the Board’s decision on November 17,1997.

II.

Swanson’s contract with the Navy incorporated various standard provisions of the Federal Acquisition Regulations (“FAR”), codified at 48 C.F.R. chs. 1-99. 1 When a contract is terminated for the convenience of the government, the contractor may submit a termination settlement proposal. FAR § 52.249-2(e), 48 C.F.R. § 52.249-2(e). The contractor has one year to submit its proposal. Id. If the contractor fails to submit a proposal within that period, the contracting officer “may determine, on the basis of information available, the amount, if any, due the Contractor because of the termination and shall pay the amount determined.” Id. Apart from the requirements of the CDA, the contractor may appeal from any termination settlement determination by the contracting officer provided it (1) submits a termination settlement proposal within one year from the “effective date of termination” or (2) requests an extension of time for doing so. FAR § 52.249-2(e), (j), 48 C.F.R. § 52.249-2(e), ©. FAR § 2.101 defines the “[effective date of termination” as “the date the contractor receives the notice [of termination]” if the notice is received after the date fixed for termination. 48 C.F.R. § 2.101. Swanson received the Board’s decision converting the termination for default to a termination for convenience on November 17, 1997. Any termination settlement proposal it wished to submit was therefore due to the contracting officer by November 16,1998. 2

Swanson did not submit a termination settlement proposal within the required one-year period. Instead, on November 10, 1998, prior to the expiration of the period, counsel for Swanson sent a letter to the Navy requesting a one-year extension of time to “initiate the claim.” 3 Counsel for the Navy responded on November 23,1998, stating that “the one year period in which [a termination settlement proposal] could have been filed has expired,” but adding that he would consult with the contracting officer regarding *1378 Swanson’s request. Counsel for the Navy informed Swanson on December 9, 1998 that the contracting officer had denied its request for an extension of time. Counsel explained that while the contracting officer planned to move forward and issue a settlement determination on the contract, “[a]ny information which Mr. Swanson wishes to submit for consideration in the determination may be provided the Contracting Officer through me.”

In a unilateral settlement determination issued on March 4, 1999, the contracting officer awarded Swanson $12,294.21 in termination settlement costs. Swanson appealed that decision to the Board on March 22, 1999. Swanson Group, Inc., 01-1 B.C.A. (CCH) ¶ 31,164 (A.S.B.C.A. Nov.2, 2000). Before the Board, the Navy moved to dismiss based on the affirmative defense that Swanson had forfeited its right to appeal by failing to submit a termination settlement proposal within the one-year period established by FAR section 52.249-2. Id. at 153,928, 153,929-30. The Navy argued that the deadline for the submission of Swanson’s proposal was one year from the Board’s decision, or November 6, 1998. Id. at 153,930. Denying the Navy’s motion, the Board concluded that FAR section 52.249-2© did not operate to bar Swanson’s appeal. Id. The Board pointed out that the one-year period for submitting a termination settlement proposal runs from the “effective date of termination,” which is defined by FAR section 2.201 as the date on which the contractor receives notice of termination if notice is received subsequent to the actual date of termination. Id. Swanson received notice of the Board’s decision on November 17, 1997, establishing that as the effective date of termination. The Board ruled that because Swanson filed its request for an extension of time on November 10, 1998, within one year of the effective date, it had preserved its right to appeal the contracting officer’s settlement determination. Id.

On March 28, 2002, the Board issued its quantum decision on the merits of Swanson’s appeal. Swanson Group, Inc., 02-1 B.C.A. (CCH) ¶ 31,836, at 157,297. In its decision, the Board added $249,840.38 to the contractor’s award of $12,294.21, resulting in a total award of $262,134.59. Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jones v. United States
Federal Claims, 2025
Nussbaum v. United States
Federal Circuit, 2021
Kiewit Infrastructure West Co. v. United States
972 F.3d 1322 (Federal Circuit, 2020)
Nussbaum v. United States
Federal Claims, 2019
Black Bear Construction Company
Armed Services Board of Contract Appeals, 2017
Mw Builders, Inc. v. United States
134 Fed. Cl. 469 (Federal Claims, 2017)
Magnus Pacific Corporation v. United States
133 Fed. Cl. 640 (Federal Claims, 2017)
Michael Roth & Associates v. United States
133 Fed. Cl. 279 (Federal Claims, 2017)
Asi Constructors, Inc. v. United States
129 Fed. Cl. 707 (Federal Claims, 2016)
Bruhn Newtech, Inc. v. United States
129 Fed. Cl. 656 (Federal Claims, 2016)
Claude Mayo Construction Company, Inc. v. United States
128 Fed. Cl. 616 (Federal Claims, 2016)
Securiforce International America, LLC v. United States
125 Fed. Cl. 749 (Federal Claims, 2016)
Horn & Associates, Inc. v. United States
123 Fed. Cl. 728 (Federal Claims, 2015)
Meridian Engineering Company v. United States
122 Fed. Cl. 381 (Federal Claims, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
353 F.3d 1375, 2004 U.S. App. LEXIS 259, 2004 WL 42115, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gordon-r-england-secretary-of-the-navy-v-the-swanson-group-inc-cafc-2004.