The Sharman Company, Inc. v. United States

2 F.3d 1564, 39 Cont. Cas. Fed. 76,567, 1993 U.S. App. LEXIS 20853, 1993 WL 309171
CourtCourt of Appeals for the Federal Circuit
DecidedAugust 17, 1993
Docket92-5150
StatusPublished
Cited by150 cases

This text of 2 F.3d 1564 (The Sharman Company, Inc. v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The Sharman Company, Inc. v. United States, 2 F.3d 1564, 39 Cont. Cas. Fed. 76,567, 1993 U.S. App. LEXIS 20853, 1993 WL 309171 (Fed. Cir. 1993).

Opinions

MICHEL, Circuit Judge.

The Sharman Company (“Sharman” or “the contractor”) appeals from the judgment of the United States Claims Court,1 awarding the government $1,391,240 under the Contract Disputes Act of 1978 (CDA), 41 U.S.C. § 601 et seq., following the contractor’s repudiation of this contract to make steel water tanks for the Marine Corps. The Sharman Company v. United States, No. 90-108C (Cl. Ct. June 12, 1992). The Claims Court held that the government was entitled to return of $1,391,240 in unliquidated progress payments because prior steel price increases, not the government’s delays, caused the contractor’s decision not to perform.

Sharman filed suit on February 2, 1990, placing the progress payments claim in litigation. Per CDA section 605, a final decision of a contracting officer on a claim is a jurisdictional prerequisite to litigation. Because the contracting officer had not issued a final decision as to either the government counterclaim, or the contractor’s mirror image claim regarding the progress payments, both derivative of the original contractor costs claim, before Sharman filed suit, the Claims Court lacked jurisdiction over both claims and should have dismissed them.

The Claims Court, however, dismissed the contractor’s claim for its costs asserted in the original complaint of February 2, 1990 as arising from a termination for the convenience of the government, because that claim had not been presented to the contracting officer. Therefore, the jurisdictional prerequisite was held not met as to this claim.2

Additionally, the Claims Court dismissed Sharman’s challenge in its original complaint to the default termination as a declaratory judgment complaint beyond its jurisdiction. Since the 1992 amendments to the CDA grant the Claims Court jurisdiction over contractor challenges to default terminations in all non-final cases, the Claims Court now has subject matter jurisdiction over this matter.

Accordingly, we: (1) reverse the money judgment in favor of the government, for lack of jurisdiction; and (2) remand with instructions to address the contractor’s independent challenge to the default termination, which is no longer beyond the Claims Court’s jurisdiction and in light of our holding requires decision.

I. BACKGROUND

Sharman contracted with the United States Marine Corps (“the government”) for the manufacture of steel water tanks. Due to escalation in steel prices during the term of contract performance, Sharman repudiated the contract. Because Sharman did not complete production of the tanks as required, the government terminated the entire contract 3 for default through a notice and final decision of termination issued by the contracting officer on August 7, 1989.

On September 12, 1989, the government sent a letter to the contractor seeking repay[1567]*1567ment of progress payments in the' amount of $2,066,696.36. The letter was characterized as a “notice of demand for payment of contract debt,” and also notified Sharman that if it disputed the amount sought, it could submit a proposal for deferment of collection.

Sharman, however, did not dispute the amount to the contracting officer but instead filed suit in the Claims Court on February 2, 1990. In its complaint, “Sharman sought invalidation of the default termination, conversion of the termination to one for Government convenience and recovery of all uncompensated costs incurred in the contract’s performance.” Sharman Co. v. United States, 24 Cl.Ct. 763, 765 (1991) (as characterized by Claims Court in its ruling on the government’s motion to dismiss). The complaint also included a count in quantum meruit asserting entitlement to all the government’s progress payments, which Sharman characterized as “payment for the work performed” on the contract, plus additional monies.4

The government filed its answer to Shar-man’s complaint on May 3, 1990, denying Sharman’s entitlement to relief as well as its characterization of the government’s progress payments as earned.

On June 12, 1990, the government moved to dismiss the complaint for lack of subject matter jurisdiction on the grounds that the complaint did not present a “claim,” i. e., an assertion of entitlement to a sum certain presently due and owing, but rather, was essentially a request for declaratory relief concerning the lawfulness of the default termination. Alternatively, the government argued that even if Sharman’s complaint were read as including a demand for relief from the debt first noticed in the contracting officer’s letter of September 12, 1989, the court lacked jurisdiction because on its face that letter plainly was not a final decision, which did not issue until after suit was initiated.

On October 18, 1990, before the Claims Court ruled on the government’s motion to dismiss, the contracting officer sent the contractor another letter regarding return of the progress payments. This letter stated that it was a “notice of the Contracting Officer’s final decision,” and identified the amount owed in unliquidated progress payments as $1,391,240.29. It was the first statement by the government of a “claim,” i.e., the assertion as a matter of right to a sum certain as presently due and owing, on which there was a final decision by the contracting officer.

On December 20, 1991, the Claims Court granted in part and denied in part the government’s motion to dismiss. The court dismissed Sharman’s claim for convenience termination costs on the grounds that the claim had not been quantified and had never been submitted to the contracting officer. Sharman, 24 Cl.Ct. at 766. The court also stated that, in view of Overall Roofing & Construction, Inc. v. United States, 929 F.2d 687, 689 (Fed.Cir.1991), the contracting officer’s decision on the default termination was, of itself, insufficient to confer jurisdiction with respect to Sharman’s challenge. However, the court held that it nevertheless had jurisdiction to entertain Sharman’s challenge to the default termination decision as an issue relating to the money claim but not as an independent claim, i.e., a separate cause of action. It viewed the contracting officer’s letter of September 12, 1989, concerning return of excess progress payments as a “timely assertion of a repayment demand,” 24 Cl.Ct. at 767, which had the effect of quantifying the government’s claim inherent in the earlier default termination decision. Accordingly, the Claims Court viewed Sharman’s challenge to the termination for default as being properly before it “as a contractor’s suit on a quantified Government claim.” Id. at 768. The court did not explain how this September 1989 notice and demand constituted a “claim” under the CDA and its implementing regulation. Nor did it explain how the September letter met the requirement for a final decision.

In response to the court’s partial dismissal, Sharman amended its complaint on January 6, 1992 to include a specific challenge to the [1568]*1568government’s right to payment of the amount representing unliquidated progress payments. The government counterclaimed for the unliquidated progress payments in the amount of $1,391,240.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

PAE Applied Technologies LLC
Armed Services Board of Contract Appeals, 2023
American Technical Services, Inc
Armed Services Board of Contract Appeals, 2023
Tidewater Contractors, Inc. v. United States
131 Fed. Cl. 372 (Federal Claims, 2017)
Kansas City Power & Light Co. v. United States
131 Fed. Cl. 161 (Federal Claims, 2017)
Securiforce International America, LLC v. United States
125 Fed. Cl. 749 (Federal Claims, 2016)
Nexagen Networks, Inc. v. United States
124 Fed. Cl. 645 (Federal Claims, 2016)
Estes Express Lines v. United States
123 Fed. Cl. 538 (Federal Claims, 2015)
Baha v. United States
123 Fed. Cl. 1 (Federal Claims, 2015)
Rudolph and Sletten, Inc. v. United States
120 Fed. Cl. 137 (Federal Claims, 2015)
K-Con Building Systems, Inc. v. United States
778 F.3d 1000 (Federal Circuit, 2015)
Dobyns v. United States
118 Fed. Cl. 289 (Federal Claims, 2014)
Macro-Z Technology
Armed Services Board of Contract Appeals, 2014
Hanover Insurance Company (The) v. United States
116 Fed. Cl. 303 (Federal Claims, 2014)
Raytheon Company v. United States
747 F.3d 1341 (Federal Circuit, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
2 F.3d 1564, 39 Cont. Cas. Fed. 76,567, 1993 U.S. App. LEXIS 20853, 1993 WL 309171, Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-sharman-company-inc-v-united-states-cafc-1993.