Macro-Z Technology

CourtArmed Services Board of Contract Appeals
DecidedAugust 18, 2014
DocketASBCA No. 56711
StatusPublished

This text of Macro-Z Technology (Macro-Z Technology) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Macro-Z Technology, (asbca 2014).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) Macro-Z Technology ) ASBCA No. 56711 ) Under Contract No. N44255-04-D-9122 )

APPEARANCES FOR THE APPELLANT: James F. Nagle, Esq. Adam K. Lasky, Esq. Oles Morrison Rinker & Baker LLP Seattle, WA

APPEARANCES FOR THE GOVERNMENT: Ronald J. Borro, Esq. Navy Chief Trial Attorney Anthony K. Hicks, Esq. Robyn L. Hamady, Esq. Trial Attorneys

OPINION BY ADMINISTRATIVE JUDGE JAMES

This appeal arises from the contracting officer's (CO) deemed denial of the $5,434,297 claim ofMacro-Z Technology (MZT) which it certified on 2 September 2008. The Board has jurisdiction of the appeal under the Contract Disputes Act of 1978 (CDA), 41 U.S.C. §§ 7101-7109. The parties have agreed to decide this appeal on entitlement only by documentary submission under Board Rule 11. The record contains 958 Rule 4 and supplemental Rule 4 documents submitted by the parties. MZT submitted its Rule 11 brief on 15 January 2014. Respondent submitted its Rule 11 brief on 4 March 2014. MZT submitted a reply brief on 11 April 2014.

FINDINGS OF FACT

1. On 15 July 2004 the Naval Facilities Engineering Command (NAVF AC) Engineering Field Activity Northwest (EF ANW) issued a Request for Proposals for an SBA§ 8(a) Multiple Award Construction Contract (MACC). Under the MACC, the "seed project P-041 Fire Station Addition and Renovation, NAS [Naval Air Station] Whidbey Island" would be used as a sub-criterion for selecting MACC awardees. (R4, tab 2 at 14 1) EFANW advised offerors that under the solicitation it would award three to five indefinite-delivery, indefinite-quantity (IDIQ) contracts, under which task

1 Citations to all Rule 4 pages are to their Bates numbers and ignore sub-tab numbers. orders would be issued for design-construction projects (R4, tab 2 at 14-23, tab 5 at 992).

2. On 29 September 2004 EFANW awarded Contract No. N44255-04-D-9122 to MZT, and on the same day issued to MZT Task Order No. 0001 (T0-1) in the amount of $3,999,872.00 for the design and construction of"Fire Station Addition & Renovation" at NASWI, to be completed by 6 March 2006 (R4, tab 28 at 4778-4801).

3. T0-1 's price was increased to a final price of $4,313 ,443 .57 and its completion date was extended cumulatively to 27 June 2006. EF ANW accepted the work as complete on 26 April 2007. The CO stated that liquidated damages (LDs) "can be assessed" for 303 days of delay (303 x $1,850/day = $560,550), which exceeded the $524,726.12 remaining on T0-1 by $35,823.88. 2 (R4, tab 13 at 1299, tab 28 at 4735-36, tab 31at4881)

4. MZT's 10 March 2008 Request for Equitable Adjustment (REA) demanded $5,434,297 under T0-1. Under the heading "IMPACT ISSUE DESCRIPTION," that $5,434,297 was composed of $3,442,579 for "impact damages," $628,657 for "delay damages" and $752,560 for "proposal preparation costs" (aka REA development costs), subtotaling "4,823,797" (sic, $4,823,796). MZT also demanded $610,500 for "LIQUIDA TED DAMAGES WITHHELD" and "a time extension of 303 [or 305] calendar days." (R4, tab 27 at 1873, 1968, 1992, 2451-53)

5. The REA's $3,442,579 impact damages were based upon 85 "B" and "V" (variance) items. Item B.1.20 listed 42 "V" items for which MZT stated, "Total Costs: $ TBD," except for items VOOl ($1,000), V038 ($5,600) and V040 ($1,500). (R4, tab 27 at 1967, 2452-533, 2459-61, 3465-66, 3468, 3473, 3628, 4160, 4261)

6. The REA requested $628,657 for 303 (or 305) calendar delay days, which MZT attributed to the 85 "B" and "V" impact items (R4, tab 27 at 1968, 1992).

7. The REA alleged $752,560 for proposal preparation, with the note: "Proposal preparation costs are ongoing and will be adjusted as additional costs are incurred" (R4, tab 27 at 1969, 2451).

8. The REA's item for $610,500 LDs retained and withheld, also described as "financing costs to complete the project," includes a $170, 170 "retention" for 13

2 The CO apparently assessed LDs by retaining/withholding $524,726.12 from payments otherwise due under T0-1. Record evidence does not show whether the CO demanded the $35,823.88 balance ofLDs from MZT. 2 months and $488,400 assessed LDs for 6 months ($170, 170 + $488,400 = $658,570) 3 (R4, tab 27 at 1965-67, 1970, 2451 ).

9. The REA alleged general operative facts with respect to the Navy's pre-award failure to disclose superior knowledge, violation of duty of good faith and fair dealing, bid mistakes, but did not attribute any specific costs to those legal theories (R4, tab 27 at 1882-89, 1970, 1998).

10. The CO's 21August2008 letter to MZT found no merit in the REA except for impact items B.1.13 and B.1.40, for which the parties agreed to a $130,000 adjustment in contract Modification No. 6 (R4, tab 13 at 1299, tab 28).

11. On 2 September 2008 MZT submitted to the CO a certified claim constituted of its 10 March 2008 REA (R4, tab 29). MZT's 16 January 2009 letter appealed to the ASBCA from the CO's deemed denial of its claim.

12. On 6 March 2010, MZT moved for partial summary judgment on its eight alleged unilateral, pre-award mistakes and stated:

The Board should rescind the subject contract and grant MZT restitution on a quantum meruit basis.. . . MZT should be entitled to recover its total reasonable costs incurred in the performance of the ... contract (not to exceed the Navy's $8.150 million estimate for new construction), less the amounts already paid by the Navy to MZT. In addition, the liquidated damages withheld ... should be released.

(App. mot. at ii-iii, 2, 49-83, 94) The Navy's last new construction cost estimate was $8,027,000 (supp. R4, tab 480) and MZT was paid $3,658,717.45 (R4, tab 25 at 1861).

13. Our February 2012 decision on that motion stated the operative facts with respect to how the Navy developed its requirement and cost estimates for the addition to and renovation of the Whidbey Island Fire Station, prepared the competitive solicitation, received and evaluated 12 proposals, discussed MZT' s proposal with MZT, explained the source selection rationale and awarded the contract and T0-1 to MZT. We described the legal theories of unilateral mistakes, unconscionability and superior knowledge/misrepresentation on which MZT based its motion as follows:

MZT' s motion for partial summary judgment advances three entitlement theories: unilateral mistakes

3 MZT does not explain the $48,070 discrepancy between $610,500 and $658,570. 3 prior to award about which the Navy knew or should have known; unconscionability associated with the alleged unilateral mistakes and acceptance of MZT' s proposal for new construction at an "unrealistically low price;" and superior knowledge/misrepresentation associated with alleged misrepresentations and nondisclosures which induced MZT to bid at an "unrealistically low price" a:nd alleged failure to disclose superior knowledge that the price was "unrealistically low."

Macro-Z Technology, ASBCA No. 56711, 12-1BCAif35,000 at 171,999. We denied MZT' s motion due to genuine issues of material facts, mistakes in judgment, insufficient supporting evidence, and inadequacies in MZT' s foregoing legal theories on the eight pre-award mistakes. 12-1 BCA if 35,000 at 172,010.

14. On 28 February 2013, MZT notified the Board it would only pursue the bases for entitlement raised in its partial motion for summary judgment (supp. R4, tab 627).

15. At MZT's request, the Board's 29 November 2012 order dismissed with prejudice 19 "B" claim items (supp. R4, tabs 625, 626).

16. At MZT's request, the Board's 9 July 2013 order dismissed with prejudice MZT's 30 remaining "B" claim items and 51 of its "V" claim items (supp.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bender v. Williamsport Area School District
475 U.S. 534 (Supreme Court, 1986)
The Sharman Company, Inc. v. United States
2 F.3d 1564 (Federal Circuit, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
Macro-Z Technology, Counsel Stack Legal Research, https://law.counselstack.com/opinion/macro-z-technology-asbca-2014.