Crippen & Graen Corp. v. United States

35 Cont. Cas. Fed. 75,726, 18 Cl. Ct. 237, 1989 U.S. Claims LEXIS 187, 1989 WL 111560
CourtUnited States Court of Claims
DecidedSeptember 26, 1989
DocketNo. 322-88C
StatusPublished
Cited by15 cases

This text of 35 Cont. Cas. Fed. 75,726 (Crippen & Graen Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Crippen & Graen Corp. v. United States, 35 Cont. Cas. Fed. 75,726, 18 Cl. Ct. 237, 1989 U.S. Claims LEXIS 187, 1989 WL 111560 (cc 1989).

Opinion

OPINION

MARGOLIS, Judge.

This contract case against the United States Department of the Army Armament, Munitions and Chemical Command, is before the court on the defendant’s motion to dismiss for lack of subject matter jurisdiction. After a careful review of the entire record, and after hearing oral argument, the court has determined that it has jurisdiction to consider the plaintiff’s default termination claim, but does not have jurisdiction over plaintiff’s claim based on the contracting officer’s demand for the return of unliquidated progress payments. The contracting officer has not issued an appealable final decision relating to that demand. Accordingly, the defendant’s motion to dismiss is denied in part and granted in part.

FACTS

Plaintiff, Crippen & Graen Corporation, was awarded Contract No. DAAA09-86-C-0013 on October 23,1985, by the U.S. Army Armament, Munitions and Chemical Command, Rock Island, Illinois, to supply “control modules.” According to the terms of the contract, the control modules were to be fabricated and tested in accordance with detailed designs and specifications submitted by the Army. The control modules fabricated by the plaintiff did not meet the Army’s performance expectations and were rejected.

On June 12, 1987, the contracting officer terminated the plaintiff’s contract for failure to meet a first article test delivery date. By letter dated March 22, 1988, the Army requested the refund of unliquidated progress payments made under the contract in the amount of $37,665. The March 22, 1988 letter stated:

If it is your intention to dispute the assessment of this sum, you are invited to submit whatever facts are deemed relevant to the Contracting Officer within 30 days of the receipt of this letter. If no response is received, it will be assumed that you dispute this amount, and a final decision will be issued in pursuit of an affirmative government claim.

(Emphasis added).

The plaintiff maintains that it procured and assembled the necessary parts in accordance with the contract and design specifications and that the default is excusable because the Army’s design specifications were defective. The plaintiff seeks relief under the Contract Disputes Act of 1978 (CDA), 41 U.S.C. §§ 601-613, and the Tucker Act, 28 U.S.C. § 1491. The plaintiff requests the court to convert the termi[239]*239nation for default into a termination for the convenience of the government and to rule that it is entitled to retain the unliquidated progress payments.

Defendant filed a motion to dismiss contending that the request to convert the default termination into a termination for convenience is in the nature of a declaratory judgment with no claim for money damages tied to it, and as such is beyond the subject matter jurisdiction of the court. The defendant also argues that the court lacks jurisdiction over the plaintiff’s claim based on the government’s request for the return of unliquidated progress payments because there was no final decision by the contracting officer as required by section 605(a) of the CDA.

DISCUSSION

I. Jurisdiction

A. The Default Termination Claim

Until recently, the United States Claims Court held that it did not have jurisdiction to entertain a default termination claim not accompanied by a monetary claim because the court lacks authority to grant post-award declaratory relief. Industrial Coatings, Inc. v. United States, 11 Cl.Ct. 161, 164 (1986); Gunn-Williams v. United States, 6 Cl.Ct. 820, 824 (1984). In Malone v. United States, 849 F.2d 1441, 1445 (Fed.Cir.), modified, 857 F.2d 787 (Fed.Cir.1988), however, the United States Court of Appeals for the Federal Circuit ruled that a default termination is a government claim, and that agency boards of contract appeals (BCAs) have jurisdiction under the CDA over default termination claims that are not accompanied by a claim for monetary relief. The Federal Circuit cautioned, however, that “[t]his court has not yet considered, nor does it now consider, the validity of the Claims Court precedent [holding that the court lacks jurisdiction over default terminations].” 849 F.2d at 1444.

In the Malone case, the government contended that the contractor’s default termination appeal was in the nature of a request for declaratory relief, which the BCA had no power to grant. The Federal Circuit disagreed and ruled that BCAs have jurisdiction to entertain default termination actions. The Malone court articulated several reasons for its decision. Most notably, the court concluded that:

... Congress in the CDA actually expanded the BCAs’ jurisdiction. Formerly, the BCAs only had jurisdiction to hear disputes concerning contract interpretation, and could not decide breach of contract issues. The CDA, however, broadened the BCAs’ jurisdiction to permit those tribunals to hear all disputes relating to a contract, including breach of contract issues.

Id. (citing S.Rep. No. 1118, 95th Cong., 2d Sess. 5, 19, reprinted in 1978 U.S.Code Cong. & Admin.News 5235, 5239, 5253).

The court also reasoned that challenges to default terminations are “money oriented” because such claims have monetary consequences. Id. at 1445. As the court pointed out: “If the default was proper, the contractor is liable for the government’s excess reprocurement costs. If the default was improper, the government is liable for the contractor’s termination for convenience costs.” Id. (citing Z.A.N. Company v. United States, 6 Cl.Ct. 298, 305 (1984)). Thus, the Malone court concluded that default terminations are not purely declaratory in nature but are “inextricably linked to the financial liability of both the government and the contractor.” Id.

Shortly after the Federal Circuit’s Malone decision was issued, a series of cases decided by this court held that the Claims Court also has jurisdiction to entertain an action challenging a default termination not accompanied by a monetary claim. Moser Industrienmontage GmbH v. United States, slip op. No. 254-88C at 4 (April 24, 1989) (Harkins, S.J.); R.J. Crowley, Inc. v. United States, slip op. Nos. 330-87C, 577-87C, 35-88C at 5 (April 14, 1989) (Napier, J.); Russell Corp. v. United States, 15 Cl.Ct. 760, 761-62 (1988) (Merow, J.); Claude E. Atkins Enterprises, Inc. v. United States, 15 Cl.Ct. 644, 647 (1988) (Turner, J.).

[240]*240In ruling that the Claims Court has jurisdiction, the court in Claude E. Atkins emphasized that the “^jurisdiction of the agency boards and the Claims Court is coextensive with respect to review of decisions of a contracting officer.” Id. The court found no basis for distinguishing agency board jurisdiction from Claims Court jurisdiction under the reasoning employed in Malone because the CDA provides, “in lieu of appealing the decision of the contracting officer ...

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Universal Shelters of America, Inc. v. United States
87 Fed. Cl. 127 (Federal Claims, 2009)
Todd Construction, L.P. v. United States
85 Fed. Cl. 34 (Federal Claims, 2008)
The Sharman Company, Inc. v. United States
2 F.3d 1564 (Federal Circuit, 1993)
Boeing Co. v. United States
37 Cont. Cas. Fed. 76,276 (Court of Claims, 1992)
McDonnell Douglas Corp. v. United States
37 Cont. Cas. Fed. 76,273 (Court of Claims, 1992)
Sharman Co. v. United States
37 Cont. Cas. Fed. 76,246 (Court of Claims, 1991)
AAI Corp. v. United States
37 Cont. Cas. Fed. 76,038 (Court of Claims, 1991)
Summit Contractors v. United States
36 Cont. Cas. Fed. 75,964 (Court of Claims, 1990)
Aviation v. United States
36 Cont. Cas. Fed. 75,963 (Court of Claims, 1990)
Continental Heller Construction v. United States
36 Cont. Cas. Fed. 75,944 (Court of Claims, 1990)
Scott Aviation v. United States
36 Cont. Cas. Fed. 75,901 (Court of Claims, 1990)
Overall Roofing & Construction Inc. v. United States
36 Cont. Cas. Fed. 75,849 (Court of Claims, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
35 Cont. Cas. Fed. 75,726, 18 Cl. Ct. 237, 1989 U.S. Claims LEXIS 187, 1989 WL 111560, Counsel Stack Legal Research, https://law.counselstack.com/opinion/crippen-graen-corp-v-united-states-cc-1989.