Russell Corp. v. United States

35 Cont. Cas. Fed. 75,589, 15 Cl. Ct. 760, 1988 U.S. Claims LEXIS 179, 1988 WL 120218
CourtUnited States Court of Claims
DecidedNovember 10, 1988
DocketNo. 556-84C
StatusPublished
Cited by12 cases

This text of 35 Cont. Cas. Fed. 75,589 (Russell Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Russell Corp. v. United States, 35 Cont. Cas. Fed. 75,589, 15 Cl. Ct. 760, 1988 U.S. Claims LEXIS 179, 1988 WL 120218 (cc 1988).

Opinion

OPINION

MEROW, Judge:

This litigation involves a contract (No. DLA600-83-D-4167) for certain gasolines, distillates and residuals, awarded to plaintiff on March 16, 1983 by the Defense Fuel Supply Center (DFSC).

Background

Following a controversy over the pricing formula of the contract involved, on July 26, 1983 plaintiff submitted a claim to recover some $77,195.82 in losses asserted to have been incurred during performance and a modification of the pricing formula. By a decision dated August 26, 1983, the [761]*761contracting officer denied plaintiff’s claim. No appeal was taken by plaintiff from this decision denying the claim asserted.

By letter of September 21, 1983, plaintiff’s counsel notified DFSC that the failure to provide the requested relief to plaintiff constituted a “default” and that “there is no need for the government to engage in its own useless gesture of termination.”

In the absence of further performance of the contract by plaintiff, by letters dated October 31 and November 23, 1983, the contracting officer issued a final decision(s) terminating plaintiff’s right to perform the contract for default. The decision(s) noted that the terminated supplies covered by the contract would be repurchased and any excess costs assessed against plaintiff.

On October 31, 1984, plaintiff filed its complaint (petition) in this matter, count I of which appealed the contracting officer’s default decisions of October 31 and November 23, 1983. Count II of the complaint (petition) asserted that the DFSC wrongfully and willfully refused to modify the contract. Count III of the complaint (petition) asserts a claim for relief on the basis of an asserted mistake-in-bid theory. Count IV of the complaint (petition) premised a claim on the provisions of “Section 4(b)(1)(D) of the Emergency Petroleum Allocation Act of 1973, 15 U.S.C. § 753(b)(1)(D).” For requested relief, plaintiff's complaint (petition) sought: a modification of the pricing formula to reflect changes in market conditions; that any funds wrongfully withheld as a result of wrongful termination be paid to plaintiff; that plaintiff’s discontinuation of performance be found to be excusable; that the default termination be changed to a termination for convenience of the government; that the government pay $600,000 as damages and lost profit due to wrongful termination; that interest on the claim be paid under the Contract Disputes Act (CDA).

DFSC has asserted three claims against plaintiff under contract No. DLA600-83-D-4167 for its asserted failure to perform under the contract. The contracting officer issued a final decision on the first claim for $58,081.22 on January 9, 1985. The contracting officer issued a final decision on the second claim for $135,214.63 on March 8, 1985. The contracting officer issued a final decision on the third claim for $6,818.15 on June 3, 1985. This third claim amount was revised to $5,248.96 by a letter dated August 8, 1985.

In March of 1985, DFSC withheld $60,-731.37, otherwise due plaintiff on another contract, to apply against its claim against plaintiff for failure to deliver under the instant contract, No. DLA600-83-D-4167.

On July 17, 1985, plaintiff filed an amended complaint which retained the original language with the exception that the requested relief of $600,000 in damages and lost profit was deleted.

Defendant’s answer was filed on September 16, 1985 and a pretrial order was then issued. Certain pretrial submissions have been exchanged as contemplated by this order.

By motion to dismiss, defendant asserts that the Claims Court lacks jurisdiction to grant the relief sought by plaintiff, which relief is claimed to be declaratory in nature. Alternatively, defendant seeks a ruling, in limine, barring plaintiff from challenging the default termination on the basis of contentions which were the subject of the un-appealed contracting officer’s decision of August 26, 1983. If the motion in limine is granted, defendant seeks summary judgment on the basis that plaintiff could not then overcome the default determination.

Plaintiff opposes defendant’s motion(s) for dismissal, in limine, and summary judgment, asserting that jurisdiction is present to grant the relief requested by plaintiff and defendant has not established valid grounds to support the in limine ruling sought.

Discussion

The basic question raised by defendant’s motion is whether the Claims Court has jurisdiction over plaintiff’s appeal of the default termination decision rendered by the contracting officer. While there are Claims Court decisions on this question which support defendant’s position, a re[762]*762cent decision, Claude E. Atkins Enterprises, Inc. v. United States, 15 Cl.Ct. 644 (1988), concludes that the Claims Court has jurisdiction in this circumstance pursuant to the express language in 28 U.S.C. § 1491(a)(2) added by section 14(i) of the CDA, 92 Stat. 2391. This decision is considered to be correct.1

A contracting officer’s CDA decision that a contractor is in default constitutes a “money oriented” government claim against the contractor. Malone v. United States, 849 F.2d 1441, 1443, 1445 (Fed.Cir.1988). The Claims Court has been afforded jurisdiction to grant declaratory relief on a contractor’s appeal under the CDA to overturn a government claim, as asserted by a contracting officer’s decision. Ralcon, Inc. v. United States, 13 Cl.Ct. 294, 300-01 (1987).

In the instant case, plaintiff has appealed only the government default decisions. Plaintiff did not appeal the August 26, 1983 decision by the contracting officer denying the claim to recover listed losses and to obtain a contract modification. Plaintiff has also not appealed the contracting officer’s decisions asserting excess cost claims. Plaintiff has not filed a claim with the contracting officer seeking the $60,-731.37 withheld by DFSC. A claim submitted to the contracting officer and a timely appeal from a resulting decision are prerequisites to Claims Court jurisdiction under the CDA. Paragon Energy Corp. v. United States, 227 Ct.Cl. 176, 645 F.2d 966 (1981).

Accordingly, while the validity of the excess cost assessments and the withholding of $60,731.37 are undoubtedly inextricably linked to the validity of the government default determinations, Malone v. United States, 849 F.2d 1441, 1445 (Fed.Cir.1988), these separate claim matters have not appropriately been brought before the court in this litigation. On the record to date, this case encompasses only the validity of the default determinations.

Defendant seeks a ruling, in limine, that plaintiff’s case against the validity of the default determinations may not be premised on any of the contentions which were the subject of the claim denied by the contracting officer on August 26, 1983.

Section 6(b) of the CDA, 41 U.S.C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Oscar Renda
709 F.3d 472 (Fifth Circuit, 2013)
Todd Construction, L.P. v. United States
85 Fed. Cl. 34 (Federal Claims, 2008)
Roxco, Ltd. v. United States
60 Fed. Cl. 39 (Federal Claims, 2004)
Marshall Associated Contractors, Inc. v. United States
39 Cont. Cas. Fed. 76,702 (Federal Claims, 1994)
Boeing Co. v. United States
38 Cont. Cas. Fed. 76,332 (Court of Claims, 1992)
AAI Corp. v. United States
37 Cont. Cas. Fed. 76,038 (Court of Claims, 1991)
Summit Contractors v. United States
36 Cont. Cas. Fed. 75,964 (Court of Claims, 1990)
Aviation v. United States
36 Cont. Cas. Fed. 75,963 (Court of Claims, 1990)
Continental Heller Construction v. United States
36 Cont. Cas. Fed. 75,944 (Court of Claims, 1990)
Overall Roofing & Construction Inc. v. United States
36 Cont. Cas. Fed. 75,849 (Court of Claims, 1990)
Crippen & Graen Corp. v. United States
35 Cont. Cas. Fed. 75,726 (Court of Claims, 1989)
OSHCO-PAE-SOMC v. United States
35 Cont. Cas. Fed. 75,642 (Court of Claims, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
35 Cont. Cas. Fed. 75,589, 15 Cl. Ct. 760, 1988 U.S. Claims LEXIS 179, 1988 WL 120218, Counsel Stack Legal Research, https://law.counselstack.com/opinion/russell-corp-v-united-states-cc-1988.