Overall Roofing & Construction Inc. v. United States

36 Cont. Cas. Fed. 75,849, 20 Cl. Ct. 181, 1990 U.S. Claims LEXIS 138, 1990 WL 47672
CourtUnited States Court of Claims
DecidedApril 20, 1990
DocketNo. 500-89C
StatusPublished
Cited by12 cases

This text of 36 Cont. Cas. Fed. 75,849 (Overall Roofing & Construction Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Overall Roofing & Construction Inc. v. United States, 36 Cont. Cas. Fed. 75,849, 20 Cl. Ct. 181, 1990 U.S. Claims LEXIS 138, 1990 WL 47672 (cc 1990).

Opinion

ORDER

MOODY R. TIDWELL, III, Judge:

This contract case is before the court on defendant’s motion to dismiss. Such a motion requires the court to consider whether, upon the facts as alleged by plaintiff, the complaint states a claim for which this court may provide relief. Scheuer v. Rhodes, 416 U.S. 232, 236, 94 S.Ct. 1683, 1686, 40 L.Ed.2d 90 (1974); Pope v. United States, 15 Cl.Ct. 218, 222 (1988). At issue is whether this court has jurisdiction over a default termination dispute in the absence of a specific claim for monetary damages.

FACTS

In September of 1987, plaintiff was awarded a contract by defendant for the repair of miscellaneous roofs at the Naval Air Station in Key West, Florida. A dispute arose as to the structural integrity of several of the roofs plaintiff constructed. Defendant demanded that plaintiff remove and reconstruct a certain number of the roofs in accordance with defendant’s directions. Plaintiff refused to comply with defendant’s demand and, instead, charged defendant with a breach of contract. As a result, the contract was terminated for default by final decision of the contracting officer on October 25, 1988. The contracting officer’s final decision reserved for the government all rights and remedies provided by law or called for under the contract, including the right to assess any increased costs occasioned by completion of the defaulted contract. The final decision also contained the requisite language that it was final unless appealed within 90 days to the General Services Administration Board of Contract Appeals, or within one year to this court.

DISCUSSION

In its Complaint, plaintiff argued that the termination for default was improper both because defendant had agreed to a workmanship standard during plaintiff’s initial performance and because, due to subsequent unilateral changes in inspection standards and policies, defendant violated its duty to cooperate with the contractor in performance of the contract. Furthermore, plaintiff continued, defendant violated its duty to cooperate by 1) allowing plaintiff to continue work on other buildings while knowing that defendant would ultimately not accept plaintiff’s effort, 2) directing plaintiff to do acts constituting economic waste, and 3) failing to pay legitimately due and owing progress payments to plaintiff. Defendant, in its motion to dismiss, asserted that the Claims Court lacked jurisdiction to hear plaintiff’s claims because, in the absence of a specific claim for monetary relief, plaintiff's claims amounted to a request for declaratory judgment which the Claims Court has no authority to render under the Contract Disputes Act of 1978, 41 U.S.C. §§ 601-613 (1982).

This court agrees with defendant that the court has no jurisdiction at this time to hear plaintiff’s claims. Plaintiff has not brought a specific claim for monetary relief in response to the contracting officer’s termination for default and the established parameters of this courts jurisdiction ex[183]*183tend only to claims for money damages against the United States. 28 U.S.C. § 1491 (1982); see, e.g., United States v. King, 395 U.S. 1, 3-5, 89 S.Ct. 1501, 1502-03, 23 L.Ed.2d 52 (1969); Glidden Co. v. Zdanok, 370 U.S. 530, 557, 82 S.Ct. 1459, 1476-77, 8 L.Ed.2d 671, reh’g denied, 371 U.S. 854, 83 S.Ct. 14, 9 L.Ed.2d 93 (1962); Austin v. United States, 206 Ct.Cl. 719, 723, cert. denied, 423 U.S. 911, 96 S.Ct. 215, 46 L.Ed.2d 140 (1975); Eastport S.S. Corp. v. United States, 372 F.2d 1002, 1007, 178 Ct.Cl. 599 (Fed.Cir.1967); Ralcon, Inc. v. United States, 13 Cl.Ct. 294, 299-300 (1987); Citizens Assocs., Ltd. v. United States, 12 Cl.Ct. 599, 600-01 (1987); Industrial Coatings, Inc. v. United States, 11 Cl.Ct. 161, 162-64 (1986); Alan J. Haynes Constr. Sys., Inc. v. United States, 10 Cl.Ct. 526, 528 (1986); Gunn-Williams v. United States, 8 Cl.Ct. 531, 534-35 (1985). Moreover, it has long been established that a contractor may appeal to this court only those claims which constitute a “dispute” as defined by the Contract Disputes Act, 41 U.S.C. §§ 601-613 (1982). Keystone Coat & Apron Mfg. Corp. v. United States, 150 Ct.Cl. 277, 281-82 (1960). In this case, where the contracting officer has only given a termination for default, there is no contract “dispute” for purposes of the Act. E.g., Gunn-Williams, 8 Cl.Ct. at 534 (citations omitted).

The Government in terminating a contract for default has merely administratively exercised one of its contractual rights. At this point, there is no dispute between the parties — the contractor can accept the default termination, and the Government can decide not to pursue its contractual remedies for default (e.g., [such as] assessment of excess costs of reprocurement, assessment of liquidated damages, and recovery of earlier paid progress payments). A “claim,” under the Contract Disputes Act, does not exist until there is a dispute between the parties. See Keystone Coat & Apron Mfg. Corp. v. United States, 150 Ct.Cl. 277 (1960). [It is only when] the Government contracting officer issues a final decision representing the Government’s intention to pursue its contractual remedies for default [that] a [dispute] exists that is ripe for appeal to this Court.

Gunn-Williams, 8 Cl.Ct. at 535. Therefore, plaintiff may not invoke this court’s direct access jurisdiction to challenge the validity of defendant’s termination for default until plaintiff has filed its own monetary claim(s) with the contracting officer challenging the default or until the contracting officer has asserted its intention to pursue specific monetary contractual remedies against plaintiff. See White Plains Iron Works, Inc. v. United States, 229 Ct.Cl. 626, 629-30 (1981); Austin, 206 Ct.Cl. at 723; Frawley v. United States, 14 Cl.Ct. 766, 768 (1988); Citizens Assocs., 12 Cl.Ct. at 601. Until the procedural prerequisites have been accomplished, plaintiff’s claim would not be ripe for appeal to this court. 41 U.S.C. § 605; see Austin, 206 Ct.Cl. at 723; Frawley, 14 Cl.Ct. at 768; Citizens Assocs., 12 Cl.Ct. at 601. Plaintiff’s “appeal” to this court is therefore premature and must be dismissed. E.g., Borough of Alpine v. United States, 19 Cl.Ct. 802, 805 (Cl.Ct.1990).

The court is not persuaded by the recent Claims Court decisions cited by plaintiff which run contrary to our holding today. Crippen & Graen Corp. v. United States, 18 Cl.Ct. 237 (1989); Moser Industrien-montage GmbH v. United States, No. 254-88C, slip op. at 4 (Cl.Ct. April 24, 1989); R.J. Crowley, Inc. v. United States, Nos. 330-87C, 577-87C, 35-88C, slip op. at 5 (Cl.Ct. April 14,1989); City of El Centro v. United States, 17 Cl.Ct. 794 (1989); Russell Corp. v. United States, 15 Cl.Ct. 760 (1988); Claude E. Atkins Enters., Inc.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Page Construction Co. v. United States
38 Cont. Cas. Fed. 76,319 (Court of Claims, 1992)
Cox v. United States
38 Cont. Cas. Fed. 76,321 (Court of Claims, 1992)
CPT Corp. v. United States
37 Cont. Cas. Fed. 76,282 (Court of Claims, 1992)
AAI Corp. v. United States
37 Cont. Cas. Fed. 76,038 (Court of Claims, 1991)
Summit Contractors v. United States
36 Cont. Cas. Fed. 75,964 (Court of Claims, 1990)
Aviation v. United States
36 Cont. Cas. Fed. 75,963 (Court of Claims, 1990)
Continental Heller Construction v. United States
36 Cont. Cas. Fed. 75,944 (Court of Claims, 1990)
Scott Aviation v. United States
36 Cont. Cas. Fed. 75,901 (Court of Claims, 1990)
Arkansas Best Freight System, Inc. v. United States
36 Cont. Cas. Fed. 75,905 (Court of Claims, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
36 Cont. Cas. Fed. 75,849, 20 Cl. Ct. 181, 1990 U.S. Claims LEXIS 138, 1990 WL 47672, Counsel Stack Legal Research, https://law.counselstack.com/opinion/overall-roofing-construction-inc-v-united-states-cc-1990.