CPT Corp. v. United States

37 Cont. Cas. Fed. 76,282, 25 Cl. Ct. 451, 1992 U.S. Claims LEXIS 89, 1992 WL 46471
CourtUnited States Court of Claims
DecidedMarch 13, 1992
DocketNo. 91-1005C
StatusPublished
Cited by6 cases

This text of 37 Cont. Cas. Fed. 76,282 (CPT Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CPT Corp. v. United States, 37 Cont. Cas. Fed. 76,282, 25 Cl. Ct. 451, 1992 U.S. Claims LEXIS 89, 1992 WL 46471 (cc 1992).

Opinion

ORDER

MOODY R. TIDWELL, III, Judge:

This case is before the court on defendant’s motions for summary judgment and to dismiss part of the complaint for lack of subject matter jurisdiction. For the reasons set forth below, the court sua sponte dismisses the complaint, without prejudice, for lack of jurisdiction over the subject matter.

FACTS

In 1983, the General Services Administration (GSA) entered into schedule contracts with CPT Corporation which allowed various government agencies to rent Automatic Data Processing Equipment (ADPE) from CPT. Included in the schedule contracts were provisions for equipment purchases under a federal lease to ownership plan (FLTOP), through which the government could acquire title to the equipment after making the necessary monthly lease payments. All payments, if properly invoiced, were due on the thirtieth day of the month and the Prompt Payment Act (PPA), 31 U.S.C. §§ 3901-3907 (1988), applied to all contracts.

Pursuant to the GSA schedule contracts, the Army entered into a series of ADPE leases with CPT. The leases covered the time from September 30, 1985 to September 1987, except for the months of October 1986, January 1987, and February 1987. On September 29, 1987, defendant issued a modification to the lease covering November and December 1986 to exercise its purchase option under that lease. After the purchase orders were issued, CPT assigned its interests in the equipment and the leases to PacifiCorp, a financing institution. PacifiCorp, however, did not perfect its assignment, see, e.g., 41 U.S.C. § 15 (1988), but, as the real party in interest, is a party-plaintiff in accordance with RUSCC 17.

On June 13, 1989, plaintiffs sent a letter to the Army Contracting Officer in Stuttgart, asserting that payment for the buyout had been received late, that certain lease payments had either been paid late or not at all, and requesting payment of the unpaid amounts and interest pursuant to the Contracts Disputes Act (CDA), 41 U.S.C. §§ 601-613 (1988), and the PPA. The letter requested $43,669.81 and asked for a written decision within sixty days. [453]*453The contracting officer responded by noting that the buyout had not been properly invoiced by plaintiffs, and requested that plaintiffs submit a proper invoice and additional documentation to confirm the late or missing payments. In a letter on August 30, 1989, plaintiffs’ attorney admitted that the buyout modification had not been properly invoiced and that “arrears rentals for months prior to the buyout date were received late and mistakenly applied as partial payment of the buyout.” The letter stated that “the proper resolution of the matter [would be] to have the claim withdrawn and the buyout invoiced.” An invoice was enclosed with the letter, and a separate copy of the invoice was sent to the Army payment office. Plaintiffs advised that if payment were received under the new invoice, their “claims” would be withdrawn.

By December 7, 1989, plaintiffs had not received payment and another letter to the contracting officer was dispatched, this time seeking $49,021.39 plus PPA interest.1 Although the letter was characterized as “a claim in accordance with the [CDA]” and requested a written decision within sixty days, it also said to contact plaintiffs’ attorney if settlement was desired. The Contracting Office, through its Regional Counsel, responded in a letter dated January 4, 1990 which indicated that $11,389.64 of the buyout had been paid “for almost two years” and that only $37,631.75 was owed. Accordingly, defendant agreed to send a check for the balance “before the week [was] out,” but since plaintiffs’ invoice was incorrect, no interest would be given. The letter stated that it “was not a final decision of a contracting officer under the [CDA].”

In a letter dated February 9, 1990, plaintiffs’ attorney acknowledged receipt of defendant’s check for $37,631.15, but then asked for an additional $33,276.46, plus interest, for missing ADPE rental payments for June, July, and September 1986, January and February 1987, part of May 1987, and July, August, and September 1987. As in previous letters, plaintiffs asked for “a written decision within 60 days, as required by CDA.” In reply, defendant wrote that it had researched the matter and agreed that the rental payments for June, July, and September 1986, and May 1987 were covered by contract and were owed. However, no contract had existed for October 1986 and January, February, July, August, and September 1987. Plaintiffs were informed that their ratification of January and February 1987 had been improperly completed, and that the proper paperwork would need to be resubmitted. The rental of equipment for October 1986 would also have to be ratified and defendant suggested that since it had already been paid, plaintiff should apply that payment to September 1986. The letter stated that no action by plaintiffs would be necessary to start the ratification of July, August, and September 1987, and that the payments for June and July 1986, and May 1987, would be processed promptly.

Plaintiffs, in a letter on May 21, 1990, agreed to apply the October 1986 payment to September 1986, and to resubmit the ratification for January and February 1987. At the suggestion of the contracting office, they also reserved their claims for October 1986, and for July, August, and September 1987, and renewed their demand for CDA and PPA interest. In response, defendant wrote that plaintiffs’ requests for interest were inappropriate since the government had just received proper invoices for the missing payments covered by contract. Defendant’s letter also pointed out that plaintiffs had improperly completed the original ratification of January and February 1987, and that, upon further research, the rentals for July, August, and September 1987 had apparently already been paid [454]*454to an affiliate of CPT.2 In light of these facts, defendant suggested that plaintiffs “seriously consider dropping [the interest] claims, in a spirit of compromise.” The letter closed by stating that it was not a “final decision of a Contracting Officer under the CDA.”

On July 23, 1990, plaintiffs’ attorney wrote that he “would be willing ... to press [his] client to waive any interest claim” if prompt payment was received. Approximately a month later, plaintiffs’ attorney wrote that the process was “dragging” and that his clients “should have interest.” Defendant wrote back and outlined the progress made and again stated that plaintiffs were not entitled to interest. Plaintiffs’ attorney, on September 27, 1990, again wrote that if payment was received within thirty days, plaintiffs would “not seek further interest on these funds.” Subsequent letters established that all missing payments, except October 1986, were received. On February 21, 1991, plaintiffs’ attorney inquired as to when that final payment would be received, but made no demand for interest. At no time did the contracting officer issue a final decision on any of plaintiffs’ submissions.

On March 11, 1991, plaintiffs filed an action in this court seeking payment of the ADPE rental for October 1986 and, pursuant to the CDA and the PPA, interest on the buyout and all late rental payments.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bay County, Florida v. United States
117 Fed. Cl. 131 (Federal Claims, 2014)
Sarang Corp. v. United States
76 Fed. Cl. 560 (Federal Claims, 2007)
Gutz v. United States
45 Fed. Cl. 291 (Federal Claims, 1999)
Medina Construction, Ltd. v. United States
43 Cont. Cas. Fed. 77,458 (Federal Claims, 1999)
Kraft, Inc. v. United States
30 Fed. Cl. 739 (Federal Claims, 1994)
Sterling Millwrights, Inc. v. United States
38 Cont. Cas. Fed. 76,316 (Court of Claims, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
37 Cont. Cas. Fed. 76,282, 25 Cl. Ct. 451, 1992 U.S. Claims LEXIS 89, 1992 WL 46471, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cpt-corp-v-united-states-cc-1992.