Mayfair Construction Company v. The United States

841 F.2d 1576, 34 Cont. Cas. Fed. 75,450, 1988 U.S. App. LEXIS 2879, 1988 WL 18892
CourtCourt of Appeals for the Federal Circuit
DecidedMarch 9, 1988
Docket87-1251
StatusPublished
Cited by31 cases

This text of 841 F.2d 1576 (Mayfair Construction Company v. The United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mayfair Construction Company v. The United States, 841 F.2d 1576, 34 Cont. Cas. Fed. 75,450, 1988 U.S. App. LEXIS 2879, 1988 WL 18892 (Fed. Cir. 1988).

Opinions

BISSELL, Circuit Judge.

Mayfair Construction Company (Mayfair) appeals from a decision of the Armed Services Board of Contract Appeals (ASBCA), [1577]*1577Mayfair Construction Co., ASBCA No. 30800, 87-1 BCA ¶ 19,542, denying Mayfair’s appeal. We affirm.

BACKGROUND

On September 5, 1980, the Department of the Air Force awarded a contract to Mayfair for the “Pacer Down” facilities restoration project at McConnell Air Force Base, Kansas, in the amount of $4,176,296. This contract incorporated by reference the March 1979 version of the Defense Acquisition Regulation Disputes clause.

On January 28, 1982, the contracting officer terminated the contract for the convenience of the government. Mayfair submitted a termination settlement proposal to the contracting officer on June 17, 1982, in the amount of $990,937.29. By letter of August 2, 1982, Mayfair’s counsel denominated the June 17,1982 proposal as a claim under the Contract Disputes Act of 1978 (CDA), 41 U.S.C. § 601 et seq. (1982), and enclosed certification of the proposal as a claim.

On December 11, 1984, Mayfair forwarded an updated termination settlement proposal to the contracting officer in the amount of $610,172, and certified this proposal as a claim under the CDA. The proposal included a request for interest from August 2, 1982, to December 10, 1984, in the amount of $146,612.12.

On February 14, 1985, the parties entered into a termination supplemental agreement under which they agreed that the government would pay Mayfair $438,-346 for its termination costs. This agreement, however, expressly reserved Mayfair’s claim for interest. On the same date, the contracting officer issued a final decision denying Mayfair’s claim for interest. Thereafter, Mayfair appealed to the ASBCA, which held that the Disputes clause of the contract defined “claim” to require the existence of a dispute; no dispute existed between the parties, therefore no claim existed; and consequently, no interest would be allowable under the CDA where there was no claim.

ISSUES

1. Whether Mayfair’s termination settlement proposal constitutes a claim.

2. Whether Mayfair may recover interest on its termination settlement proposal.

OPINION

I.

The contract at issue specifically incorporated by reference the March 1979 version of the Disputes clause. That clause defined claim as follows:

(b) “Claim” means:
(1) a written request submitted to the Contracting Officer;
(2) for payment of money, adjustment of contract terms, or other relief;
(3) which is in dispute....

44 Fed.Reg. 12,524 (1979) (emphasis added). It is beyond cavil that under this clause, no claim exists unless it involves a dispute.

As a matter of fact, the ASBCA found here that no dispute existed between the parties. It looked to Mayfair’s substantial concurrence with an August 1982 government audit report, and the large reductions Mayfair made thereafter in its proposed settlement. It noted that excluding the $146,612.12 interest element of Mayfair’s December 1984 settlement proposal, the final settlement agreement for $438,346 gave Mayfair only $25,213.88 less than the $463,559.88 it had requested in December 1984. As a result, the ASBCA characterized Mayfair and the government during this period as being in “a pre-dispute, negotiation posture.” Mayfair, 87-1 BCA at 98,744.

We must treat the ASBCA’s factual findings as final unless “fraudulent, or arbitrary, or capricious, or so grossly erroneous as to necessarily imply bad faith,” or unless those findings are “not supported by substantial evidence.” 41 U.S.C. § 609(b) (1982). There is nothing here to suggest these findings are fraudulent, arbitrary, capricious, or grossly erroneous. With respect to the substantial evidence standard, this “means such relevant evidence as a reasonable mind might accept as [1578]*1578adequate to support a conclusion.” Universal Camera Corp. v. National Labor Relations Bd., 340 U.S. 474, 477, 71 S.Ct. 456, 459, 95 L.Ed. 456 (1951) (quoting Consolidated Edison Co. v. National Labor Relations Bd., 305 U.S. 197, 229, 59 S.Ct. 206, 216-17, 83 L.Ed. 126 (1938)). In our view, a reasonable fact-finder could have found as the ASBCA did. Therefore, we hold that the ASBCA’s conclusion that no dispute existed between Mayfair and the government is supported by substantial evidence. Under the terms of the controlling contractual provision, consequently, Mayfair’s termination settlement proposal did not constitute a claim.

Mayfair attempts to resist this result with two arguments. First, Mayfair states that a revised Disputes clause that did not require a claim to be disputed superseded the March 1979 Disputes clause in Mayfair’s contract. Mayfair notes that the new clause was issued on April 30, 1980, well before the award of the subject contract, on September 5, 1980. This argument, however, does not wash. The new clause applied only to contracts resulting from solicitations issued on or after June 1,1980. 45 Fed.Reg. 31,035, 31,037 (1980). Because the solicitation for the subject contract was dated February 17, 1980, Mayfair, 87-1 BCA at 98,741, the new clause is inapplicable.

Mayfair also contends that the CDA does not require a claim to be disputed, and as such, the terms of the Disputes clause requiring a dispute are in violation of the statute. In order to dispose of this case, we need not, and do not, decide whether the CDA requires a claim to be disputed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Estes Express Lines v. United States
123 Fed. Cl. 538 (Federal Claims, 2015)
Executive Court Reporters, Inc. v. United States
29 Fed. Cl. 769 (Federal Claims, 1998)
Hardwick Bros. v. United States
41 Cont. Cas. Fed. 76,972 (Federal Claims, 1996)
Alvarado Construction, Inc. v. United States
39 Cont. Cas. Fed. 76,708 (Federal Claims, 1994)
Blake Construction Co. v. United States
38 Cont. Cas. Fed. 76,537 (Federal Claims, 1993)
Isles Engineering & Construction, Inc. v. United States
38 Cont. Cas. Fed. 76,326 (Court of Claims, 1992)
Facilities Systems Engineering Corp. v. United States
38 Cont. Cas. Fed. 76,315 (Court of Claims, 1992)
CPT Corp. v. United States
37 Cont. Cas. Fed. 76,282 (Court of Claims, 1992)
B.E.S. Environmental Specialists, Inc. v. United States
37 Cont. Cas. Fed. 76,163 (Court of Claims, 1991)
Sun Eagle Corp. v. United States
37 Cont. Cas. Fed. 76,119 (Court of Claims, 1991)
Elden-Rider, Inc. v. The United States
935 F.2d 281 (Federal Circuit, 1991)
Essex Electro Engineers, Inc. v. United States
37 Cont. Cas. Fed. 76,042 (Court of Claims, 1991)
Dawco Construction, Inc. v. The United States
930 F.2d 872 (Federal Circuit, 1991)
Robin Industries, Inc. v. United States
36 Cont. Cas. Fed. 76,006 (Court of Claims, 1991)
Rowe Industries, Inc. v. The United States
918 F.2d 186 (Federal Circuit, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
841 F.2d 1576, 34 Cont. Cas. Fed. 75,450, 1988 U.S. App. LEXIS 2879, 1988 WL 18892, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mayfair-construction-company-v-the-united-states-cafc-1988.