Rowe Industries, Inc. v. The United States

918 F.2d 186, 1990 WL 145564
CourtCourt of Appeals for the Federal Circuit
DecidedDecember 7, 1990
Docket90-1113
StatusUnpublished

This text of 918 F.2d 186 (Rowe Industries, Inc. v. The United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rowe Industries, Inc. v. The United States, 918 F.2d 186, 1990 WL 145564 (Fed. Cir. 1990).

Opinion

918 F.2d 186

37 Cont.Cas.Fed. (CCH) 76,060

Unpublished Disposition
NOTICE: Federal Circuit Local Rule 47.8(b) states that opinions and orders which are designated as not citable as precedent shall not be employed or cited as precedent. This does not preclude assertion of issues of claim preclusion, issue preclusion, judicial estoppel, law of the case or the like based on a decision of the Court rendered in a nonprecedential opinion or order.
ROWE INDUSTRIES, INC., Plaintiff-Appellant,
v.
The UNITED STATES, Defendant-Appellee.

No. 90-1113.

United States Court of Appeals, Federal Circuit.

Oct. 5, 1990.
Suggestion for Rehearing In Banc Declined Dec. 7, 1990.

Before NIES, Chief Judge,1 COWEN, Senior Circuit Judge, and BROWN, District Judge.2

BROWN, District Judge.

Appellant Rowe Industries, Inc. ("Rowe") appeals from a decision of the Armed Services Board of Contract Appeals ("the Board") that the Air Force properly terminated for default its contracts with Rowe for the sale of electrical bundles for use in the B-52 bomber. For the following reasons, we will affirm the Board's decision below.

Background

On November 16, 1983, the Air Force, acting through its Oklahoma City Air Force Logistics Center ("OCAMA"), awarded to Rowe contract No. F34601-84-C-0053, The contract required Rowe to supply 80 electrical bundles for use in the B-52 bomb navigation radar system. Forty bundles were to be delivered on or before December, 1984, and the remaining bundles by January, 1985.

On May 7, 1984, OCAMA awarded to Rowe a second contract, No. F34601-84-C-1576, for seventy-one more electrical bundles. The contract provided for delivery of the seventy-one bundles by June, 1985 at the same price per bundle as the first contract.

The procurements under these two contracts constituted "restrictive acquisitions" under the Department of Defense's High Dollar Spare Parts Breakout Program. Each contract contained identical clauses providing that only the Boeing Airplane Co. and Groman Corp., Rowe's parent corporation, were approved to provide the electrical bundles.3

The contracts' requirements concerning cable insulation were incorporated by reference. The contracts expressly required that Rowe provide the wire assemblies described in Rowe's drawing of part number 4R1044. Rowe's drawing designated Part Number R1035-1 as the cable to be used in the assemblies. Rowe's drawing for Part Number R1035-1 specified the use of "Okoflex Insulation or Equivalent." These cable assemblies, including the Okoflex insulation, were produced by Okonite Company ("Okonite"). Rowe had used Okoflex insulation in the bundles delivered under all prior contracts since 1975. Okonite was the sole supplier of Okoflex insulation.

On May 16, 1984, Okonite notified Rowe that it would no longer produce Okoflex and would replace it with insulation composed of Ethylene/Propylene Rubber ("EPR"). Okonite also forwarded to Rowe documentation in which Okonite asserted that the EPR insulation met or exceeded the applicable requirements for Okoflex.

Rowe subsequently contacted Mr. Richard Barry, a quality assurance representative at the Defense Contract Administration Management Area ("DCASMA") in Detroit, Michigan, to inform him of the change in insulation material. Rowe offered sample cables containing the EPR insulation to Mr. Barry for inspection. Mr. Barry declined to inspect them, however, until Rowe had submitted documentation that the new materials met or exceeded requirements.

Rowe then submitted a formal value engineering change proposal ("VECP"), seeking approval of the modification. Mr. Barry approved the VECP and forwarded it to the Defense Contract Administration Office in Cleveland, Ohio. There is no evidence of record that Mr. Barry conducted independent tests before giving his approval to the VECP. The Board below found that Mr. Barry had rubber stamped the approval based on Rowe's representations. The VECP thereafter received approval through the next two tiers of review, and was submitted for final approval to OCAMA in Oklahoma City.

OCAMA rejected Rowe's VECP, and advised Rowe accordingly. At the hearing before the Board, Mr. Billy Albritton, the aircraft systems electrical engineer responsible for evaluating Rowe's engineering change proposal, testified that the VECP was not approved because the engineering data supplied by Rowe was insufficient. Mr. Albritton expressed concern that the testing of the insulation had been done on a coax cable, not an assembly cable. He concluded that the only way the Air Force could find out whether the cable would work with the EPR insulation would be to subject the cable to extensive testing.

Mr. Albritton also testified that during his investigation, he discovered that the cable would be eliminated from the aircraft. The record before the Board demonstrated that the Modification deleting the electrical bundles from the B-52 bomb navigation radar had been released in June, 1980, and was fully approved and implemented by the Air Force by 1982. App. at p. 23. At no time prior to the disapproval of the VECP did the Air Force inform Rowe that the electrical bundles contracted for in the November 16 and May 7 contracts would be obsolete. App. at 24.

The next day, Rowe wrote the Air Force and asked that it reconsider its decision. On April 3, 1985, OCAMA responded that it was evaluating its assets and determining whether the requirement for the items still existed. On July 1, 1985, Rowe informed OCAMA that the cables had been completed, and that they were currently delinquent in delivery on the first contract by seven months because they were waiting on approval of the VECP. The VECP, however, was never approved, and Rowe never tendered delivery of the cables with the EPR insulation. In July, 1985, OCAMA terminated the Rowe contracts for default.

Rowe timely appealed the terminations. The Board sustained the default terminations in its decision issued on July 31, 1989. The Board found that the Air Force had ordered the electrical bundles in 1983 and 1984 with the "expectation that it would receive bundles which were the same as those which had been qualified and had been procured from Rowe for almost a decade." The Board denied Rowe's motion for reconsideration on November 16, 1989. Rowe filed this timely appeal pursuant to 41 U.S.C. Sec. 607(g).

Discussion

I.

Pursuant to 41 U.S.C. Sec. 609(b), factual findings of the Board "shall be final and conclusive, and shall not be set aside unless the decision is fraudulent, or arbitrary, or capricious, or so grossly erroneous as to necessarily imply bad faith, or if such decision is not supported by substantial evidence." Substantial evidence is "more than a mere scintilla. It means such relevant evidence as a reasonable mind might accept as adequate to support a conclusion." Richardson v. Perales, 402 U.S. 389, 401 (1971); Mayfair Constr. Co. v. United States, 841 F.2d 1576, 1577-78 (Fed.Cir.), cert.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Richardson v. Perales
402 U.S. 389 (Supreme Court, 1971)
Blinderman Construction Co., Inc. v. The United States
695 F.2d 552 (Federal Circuit, 1982)
Julius Goldman's Egg City v. The United States
697 F.2d 1051 (Federal Circuit, 1983)
Darwin Construction Co., Inc. v. United States
811 F.2d 593 (Federal Circuit, 1987)
Alvin, Ltd. v. United States Postal Service
816 F.2d 1562 (Federal Circuit, 1987)
Afro-Lecon, Inc. v. The United States
820 F.2d 1198 (Federal Circuit, 1987)
Mayfair Construction Company v. The United States
841 F.2d 1576 (Federal Circuit, 1988)
WRB Corp. v. United States
183 Ct. Cl. 409 (Court of Claims, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
918 F.2d 186, 1990 WL 145564, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rowe-industries-inc-v-the-united-states-cafc-1990.