Darwin Construction Co., Inc. v. United States

811 F.2d 593, 33 Cont. Cas. Fed. 75,063, 1987 U.S. App. LEXIS 105
CourtCourt of Appeals for the Federal Circuit
DecidedFebruary 12, 1987
DocketAppeal 86-1370
StatusPublished
Cited by55 cases

This text of 811 F.2d 593 (Darwin Construction Co., Inc. v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Darwin Construction Co., Inc. v. United States, 811 F.2d 593, 33 Cont. Cas. Fed. 75,063, 1987 U.S. App. LEXIS 105 (Fed. Cir. 1987).

Opinion

COWEN, Senior Circuit Judge.

Appellant (Darwin) appeals from a reconsidered decision of the Armed Services Board of Contract Appeals (ASBCA or Board) which had reversed its earlier holding. The Board initially converted a termination for default into a termination for the convenience of the Government. Upon Government’s motion for reconsideration, the Board reversed its earlier decision and upheld the termination for default. We reverse the Board’s amended decision and remand with instructions for the Board to convert the termination for default into a termination for the convenience of the Government in accordance with the Board’s initial decision.

BACKGROUND

Darwin was awarded a fixed price construction contract on June 3, 1983, for certain improvements to the Propellant Machinery Facility (PMF) at the Naval Ordnance Station (NOS) in Maryland. Contract work was to be completed within 150 calendar days, by November 15, 1983.

The contract provided that the contractor would be allowed access to the construction site only during two 14 calendar day periods which were to be separated by another period of at least 14 calendar days during which time normal Naval production operations at the facility would take place. Based upon the schedule agreed upon between the parties, the last day for construction was to have been November 7, 1983. At the conclusion of this second 14-day work period, Darwin had completed approximately 65 percent of the required contract work.

In response to a “show cause” letter Darwin noted that the late delivery of necessary equipment made it impossible for the contract to be completed by November 7. Darwin, nevertheless, asserted that it was physically and financially ready to complete the remaining contract work within a two week period beginning on December 17, 1983. Nevertheless, on February 13, 1984, the Navy terminated the contract for default, claiming that Darwin had not diligently performed during the two 14-day periods when it had access to the site. The Navy alleged that a 2-week shutdown of the facility during December was not possible in order to permit Darwin to complete the contract.

On appeal to the ASBCA, the Board found that “on the record * * * no excusable cause for delay has been proven by the appellant. Therefore, as of 15 November, the date of completion for the performance of the captioned contract, Darwin was in default.” Darwin Constr. Co., ASBCA No. 29340, 84-3 BCA ¶ 17,673 at 88,149 (1984).

Despite its finding of default, the Board held that the termination for default “must be converted to one for convenience of the *595 Government.” The decision stated that “the Board finds that this termination for default was arbitrary and capricious because it is evident to the Board that the default action was taken solely to rid the Navy of having to further deal with Darwin.” (Emphasis supplied).

The Board’s conclusion regarding the arbitrary action of the contracting officer was based, among others, on the following findings of fact made by the Board:

The only reason Darwin was unable to complete the work in time was that the material needed for the unfinished portion was not delivered in the second 2-week period for performing the contract. On November 15, 1983, the Navy knew that Darwin had performed 65 percent of the work in an acceptable manner, and there was no evidence to suggest that the contractor was financially unable to complete the remainder of the work.

The Navy knew that renewed performance could not begin at the very earliest until August 1984, and therefore, the Navy had no basis for concluding that Darwin’s late performance in November 1983 would still be a viable cause for delay in August 1984 — 9 months later.

The failure of Darwin to complete the work on time did not interfere with the Navy’s use of the building, which was still used for the production of explosives since Darwin had restored the building into usable condition. Darwin contemplated working from December 27 through December 81, 1983, having estimated that the remaining work could be completed in 4 days. There was no urgency associated with the contract.

When the contract was terminated on February 3, 1984, the Navy estimated the next available date when the remaining work could be completed as August 1984, but by the date of the hearing, this hoped-for completion date had regressed to January 1985.

At the time Darwin was performing work on the contract, many other construction contracts were being performed at the same ordnance station, and the Navy was content to collect liquidated damages for those contracts in which performance had been delayed.

Although needed material was delivered by October 4, 1983, Darwin did not receive Navy approval of the material until October 19, 1983. At that time, Darwin submitted a written request for a time extension on account of that delay. The Board found that there was no evidence in the record that the contracting officer had acted on that request as required by General Provision 5 of the contract, entitled “Termination for Default — Damages for Delay— Time Extension.” With respect to the default termination, the Board observed that “this termination for default exudes an odor piscatorial,” citing Alinco Life Insurance Co. v. United States, 373 F.2d 336, 341, 178 Ct.Cl. 813 (1967).

Accordingly, the Board converted the default termination into one for the convenience of the Government.

On the basis of the Government’s motion for reconsideration, the Board reversed its initial decision and upheld the termination for default. Darwin Constr. Co., ASBCA No. 29340, 86-2 BCA ¶ 18,959 (1986).

In reversing its decision on reconsideration, the Board, at the Government’s urging, noted that the Board should recognize and follow the decision in Kalvar Corp. v. United States, 543 F.2d 1298, 211 Ct.Cl. 192 (1976), cert. denied, 434 U.S. 830, 98 S.Ct. 112, 54 L.Ed.2d 89 (1977), in which the court held that “well-nigh irrefragable proof” is required to induce the court to abandon the presumption of good faith dealing by public officials.

However, the Board again stressed its determination that the action of the contracting officer in terminating the contract was “arbitrary and capricious, given the unique circumstances present at the time of default.”

Furthermore, the Board stated that its initial decision was at variance with a decision by a Senior Deciding Group which held that once the right of termination is acquired by the Government and if that right *596 is not lost by the Government because of its conduct, the Board will uphold the termination for default without any inquiry into the “motives” or judgment of the contracting officer leading to the decision to terminate, citing Nuclear Research Associates, Inc., ASBCA No. 13563, 70-1 BCA ¶ 8,237 (1970). Since this holding was binding on the Board’s panel in this case, the Board declared that the holding should have been followed in the initial decision. Therefore, it upheld the termination for default.

DISCUSSION

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Transportation v. Eagle Peak Rock & Paving, Inc.
69 F.4th 1367 (Federal Circuit, 2023)
Safaa Al-Rawaby Company
Armed Services Board of Contract Appeals, 2023
Central Company
Armed Services Board of Contract Appeals, 2022
Goodloe Marine, Inc.
Armed Services Board of Contract Appeals, 2022
GSC Construction, Inc.
Armed Services Board of Contract Appeals, 2020
ECC CENTCOM Constructors, LLC
Armed Services Board of Contract Appeals, 2018
Highland Al Hujaz Co., Ltd.
Armed Services Board of Contract Appeals, 2016
U.S. Coating Specialties & Supplies, LLC
Armed Services Board of Contract Appeals, 2015
Tigerswan, Inc. v. United States
118 Fed. Cl. 447 (Federal Claims, 2014)
Trust Title Company v. United States
118 Fed. Cl. 99 (Federal Claims, 2014)
Emiabata v. United States
102 Fed. Cl. 787 (Federal Claims, 2012)
Celsis in Vitro, Inc. v. CellzDirect, Inc.
664 F.3d 922 (Federal Circuit, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
811 F.2d 593, 33 Cont. Cas. Fed. 75,063, 1987 U.S. App. LEXIS 105, Counsel Stack Legal Research, https://law.counselstack.com/opinion/darwin-construction-co-inc-v-united-states-cafc-1987.