McDonnell Douglas Corp. v. United States

40 Cont. Cas. Fed. 76,912, 35 Fed. Cl. 358, 1996 U.S. Claims LEXIS 57, 1996 WL 163038
CourtUnited States Court of Federal Claims
DecidedApril 8, 1996
DocketNo. 91-1204C
StatusPublished
Cited by19 cases

This text of 40 Cont. Cas. Fed. 76,912 (McDonnell Douglas Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McDonnell Douglas Corp. v. United States, 40 Cont. Cas. Fed. 76,912, 35 Fed. Cl. 358, 1996 U.S. Claims LEXIS 57, 1996 WL 163038 (uscfc 1996).

Opinion

OPINION

HODGES, Judge.

This case comes before the court after almost five years of litigation regarding the termination for default of the A-12. This opinion sets forth our reasons for vacating the termination for default and converting the termination for default decision to a termination for the convenience of the Government.1

Plaintiffs McDonnell Douglas Corporation and General Dynamics Corporation contracted with the Navy to develop a carrier-based, low observable (Stealth) attack aircraft known as the A-12.2 Defendant terminated the contract for default on January 7, 1991. Plaintiffs argued that the Navy terminated their contract improperly, and that the contract should be converted to a termination for the convenience of the Government. We tried this part of the case, Count XVII, and later vacated the termination for default:

Testimony and other evidence at trial showed that the A-12 contract was not terminated because of contractor default. The contract was terminated because the Office of the Secretary of Defense withdrew support and funding from the A-12. Prior to that, the Navy did not believe that the contractors performance justified termination for default.

McDonnell Douglas Corp. and General Dynamics Corp. v. United States, No. 91-1204C, Order, 1994 WL 715992 (Dec. 9, 1994).

Plaintiffs argued that this ruling meant we must convert the termination to one for convenience of the Government immediately; defendant countered that conversion would create a windfall for the contractors if they were in default without excuses as of January 7,1991. According to defendant, a “technical violation” in terminating the contract could not justify conversion in light of plaintiffs’ alleged “egregious” performance failures. The Navy’s failure to exercise discretion in terminating plaintiffs for default was not a technical violation, but we agreed to hear evidence of plaintiffs’ egregious conduct. We converted the termination to default to one for the convenience of the Government in December 1995, upon finding that the Navy was aware of all critical information that could have affected a termination decision.

BACKGROUND

The Navy awarded a full-scale engineering and development (FSED) contract to the McDonnell Douglas/General Dynamics team in 1988 after competition in concept development. The incrementally funded, fixed-price incentive FSED contract had a ceiling price of $4,777,330,294 and a target price of $4,379,219,436.3 Installment payments were [362]*362scheduled to be obligated over the five-year contract. The Navy obligated a $185,000,000 installment to the contract on November 1, 1990, and a $553,200,000 installment was scheduled for January 7,1991.

The contractors were to produce eight FSED aircraft. The contract also provided the Navy an option to purchase four production lots of aircraft. Each FSED aircraft would test different characteristics of the A-12; stealth capabilities would be verified in the “fully capable, fully equipped” eighth aircraft that would serve as the basis for the production lots. Under the original agreement, the first FSED aircraft would be delivered in June 1990; the rest would be delivered monthly through January 1991. The Navy exercised its option on the first production lot on May 31,1990.

Three design reviews were held during the contract. An initial design review was completed in May 1988 and the Preliminary Design Review was completed in January 1989. The Critical Design Review process, to begin after the design is essentially complete, began in June 1990.

A. Problems with Performance

The parties were aware of problems in the performance of this contract, namely controlling the growth of the aircraft weight and meeting the contract schedule. Contracting Officer Michael Mutty knew during early 1990 that the contractors would not meet the June delivery date for the first FSED aircraft, yet he took no action to terminate the contract then. When the contractors did not meet the first flight date in June, Mutty noted serious concern regarding performance and asked plaintiffs for an estimate of when the first aircraft would be delivered.

The contractors proposed a new schedule. They asserted claims for changes to the contract, partly due to impossibility of performance and nondisclosure of superior knowledge. The contractors’ estimates showed that the projected costs would exceed the contract ceiling price by $324 million. Negotiations on a new schedule were not successful. On August 17, the Navy unilaterally issued contract modification P00046 setting the date for first flight as December 31,1991. It did not terminate the contract then.

The projected weight was a concern throughout contract performance.4 The contractors’ Best and Final Offer (BAFO) design proposal for the aircraft had indicated a weight empty for the aircraft. At that weight, the aircraft was predicted to meet needed performance characteristics.

Problems in meeting the BAFO weight surfaced around September 1988. The Contracting Officer believed that the contractors would overcome the problems. In late 1989, the CO was concerned that the BAFO weight would not be possible, but he did not issue a cure notice. The Navy believed that the aircraft’s other performance characteristics would meet its needs even if the aircraft were not at the originally predicted weight.

In January 1990, the Navy estimated that the aircraft in the first production lot would weigh 7930 pounds over BAFO.5 The contractors’ estimate was less. The Navy obligated the scheduled payment of $1.05 billion that month. The CO did not issue a cure notice.

B. Major Aircraft Review

The Department of Defense initiated a Major Aircraft Review at the beginning of 1990 to consider its major aircraft programs in light of a diminishing threat and a changing world situation. Its purpose was to decide whether to continue certain programs or to cancel them. The A-12 was included in that review. Secretary of Defense Richard B. Cheney visited the McDonnell Douglas plant in March 1990 as part of the review. There he heard some concerns with production of [363]*363the aircraft, but he felt fairly confident that the Navy and the contractors could deliver. The conclusions drawn from the review were that the need for the A-12 remained and the Navy should pursue the program. The Secretary reported these results to Congress in April 1990.

Within weeks after his testimony before Congress, the Secretary learned of problems with the A-12. He was informed that the contractors were having schedule and cost problems that would not allow them to perform under the terms of the contract. The Secretary was disturbed by this information because of his recent testimony before Congress. He discussed his concerns with the contractors that summer.

C. Acceptability of the A-12

In July 1990, the Navy sought to revali-date the requirements for the A-12 and to reassess its acceptability at the predicted weight of 7930 over BAFO. The question was whether the increased weight of the aircraft would affect the performance characteristics so that the Navy could not accept the aircraft. The answer was No. The aircraft would be acceptable at the increased weight.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Aerospace Facilities Group, Inc.
Armed Services Board of Contract Appeals, 2020
State v. U.S. Dep't of Commerce
333 F. Supp. 3d 282 (S.D. Illinois, 2018)
5860 Chicago Ridge, LLC v. United States
104 Fed. Cl. 740 (Federal Claims, 2012)
General Dynamics Corp. v. United States
131 S. Ct. 1900 (Supreme Court, 2011)
McDonnell Douglas Corp. v. United States
567 F.3d 1340 (Federal Circuit, 2009)
Glazer Construction Co. v. United States
52 Fed. Cl. 513 (Federal Claims, 2002)
McDonnell Douglas Corp. v. United States
50 Fed. Cl. 311 (Federal Claims, 2001)
Florida Engineered Construction Products Corp v. United States
42 Cont. Cas. Fed. 77,355 (Federal Claims, 1998)
SIPCO Services & Marine Inc. v. United States
42 Cont. Cas. Fed. 77,277 (Federal Claims, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
40 Cont. Cas. Fed. 76,912, 35 Fed. Cl. 358, 1996 U.S. Claims LEXIS 57, 1996 WL 163038, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcdonnell-douglas-corp-v-united-states-uscfc-1996.