McDonnell Douglas Corp. v. United States

567 F.3d 1340, 2009 U.S. App. LEXIS 11716, 2009 WL 1515777
CourtCourt of Appeals for the Federal Circuit
DecidedJune 2, 2009
Docket2007-5111, 2007-5131
StatusPublished
Cited by22 cases

This text of 567 F.3d 1340 (McDonnell Douglas Corp. v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McDonnell Douglas Corp. v. United States, 567 F.3d 1340, 2009 U.S. App. LEXIS 11716, 2009 WL 1515777 (Fed. Cir. 2009).

Opinion

MICHEL, Chief Judge.

This case arises from the government’s default termination in 1991 of a contract between the United States Navy (“the government”) and two contractors, McDonnell Douglas Corporation (“MDC”) and General Dynamics Corporation (“GD”) (collectively “contractors”) to develop a carrier-based stealth aircraft, the A-12 Avenger. The contractors challenge the judgment of the Court of Federal Claims in favor of the government. McDonnell Douglas Corp. v. United States, 76 Fed.Cl. 385 (2007) (“McDonnell Douglas XIII ”). We heard oral argument on December 3, 2008. Because the overall evidence of record supports a conclusion that the government was justified in terminating the contract for default, we affirm.

I. BACKGROUND

This American version of Jarndyce and Jarndyce has entered its eighteenth year of litigation. The detailed facts have been repeated many times previously. See, e.g., McDonnell Douglas XIII; McDonnell Douglas Corp. v. United States, 323 F.3d 1006 (Fed.Cir.2003) (“McDonnell Douglas XII ”); McDonnell Douglas Corp. v. United States, 50 Fed.Cl. 311 (2001) (“McDonnell Douglas XI ”); and McDonnell Douglas Corp. v. United States, 182 F.3d 1319 (Fed.Cir.1999) (“McDonnell Douglas X”). As we are writing what necessarily will become “McDonnell Douglas XIV,” we will only provide a summary of relevant facts here.

A. The A-12 contract

In January 1988, the Navy awarded the contractors a fixed-price research and development contract for the A-12 stealth aircraft. The full-scale engineering and development (“FSD”) contract was structured as an incrementally funded, fixed-price incentive contract with a ceiling price of $4,777,330,294. The contract incorporated by reference Federal Acquisition Regulation (FAR) 52.249-9 Default provision (Fixed-Price Research and Development), which provides in relevant part:

(a)(1) The Government may ... by written Notice of Default to the Contractor, terminate this contract in whole or in part if the Contractor fails to—
*1343 (ii) Prosecute the work so as to endanger performance of this contract (but see paragraph (a)(2) of this clause);
(2) The Government’s right to terminate this contract under subdivisions (a)(1)(h) and (iii) of this clause may be exercised if the Contractor does not cure such failure within 10 days (or more, if authorized in writing by the Contracting Officer) after receipt of the notice from the Contracting Officer specifying the failure.

48 C.F.R. § 52.249-9 (1984).

Under the contract, the contractors were to design, manufacture, and test eight A-12 prototypes according to a specified schedule, with the first aircraft to be delivered in June 1990 (the “first flight” date) and the remaining seven to be delivered monthly through January 1991. The contractors were to conclude their testing of the aircraft by April 1993, the completion time of the Navy’s technical evaluation program (“TCHEVAL”). The contractors would also support the Navy’s evaluation of the aircraft and further provide training support for three years after delivering training equipment to the Navy in June 1993. In addition, the contract gave the Navy the option to purchase four production lots of aircraft. In May 1990, the Navy exercised its option on Lot I for six aircraft to be delivered between June 1991 and May 1992.

B. Modification of the A-12 contract

From the start, the contractors encountered difficulties in performing the contract, including meeting the contract schedule and keeping the aircraft weight within specifications. McDonnell Douglas XI I, 323 F.3d at 1011. Two weeks before the first flight date, the contractors reported to the Navy that the projected first flight date would be July-September 1991, instead of June 1990 as originally agreed, and the remainder of the contract work would be delayed a corresponding twelve to fourteen months. They also predicted that the cost of completing the contract would exceed the ceiling price so substantially that it would be “unacceptable” to the contractors. The contractors asserted that a fundamental problem with the FSD contract was its fixed-price structure and proposed that the contract be modified.

At the end of June 1990, the contractors missed the first flight date. The Navy did not terminate the contract. Instead, the contracting officer sent a letter to the contractors in July, expressing “sei’ious concern” regarding the deficient performance under the contract. He warned that the contractors’ failure to meet the first flight date “could jeopardize performance of the entire [contract] effort.” He also asked for the contractors’ plan to meet the rest of the original schedule as well as then-proposal for contract revision.

As the parties failed to reach an agreement, on August 17, 1990, the Navy unilaterally issued a contract modification, P00046, which revised the prototype aircraft delivery dates but left Lot I and later milestones intact. The delivery schedules are:

*1344 [[Image here]]

C. Performanee after contract modification

After the contract modification, more problems arose concerning the performance of the contract. During the months leading to termination, the contractors’ internal schedules showed that they would not meet the P00046 modified first flight date in December 1991. McDonnell Douglas XIII, 76 Fed.Cl. at 401. Instead, they projected three more months’ delay with the first flight date in March 1992. By December 1990, the contractors’ “confidence in the March 1992 flight date [was further] reduced.” They believed that such a date was achievable “only after significant changes.”

At the same time, the contractors continued operations, spending $120-150 million of their own money every month. McDonnell Douglas XIII, 76 Fed.Cl. at 427. In November 1990, the contractors submitted a formal request to the Navy to restructure the contract as a cost-reimbursement type contract. McDonnell Douglas X, 182 F.3d at 1322.

D. The termination

The contractors’ continued difficulties in performing the contract led the Department of Defense and the Navy to question the viability of the project. On Friday, December 14, 1990, then-Secretary of Defense Dick Cheney directed the Secretary of the Navy to show cause by January 4, 1991, why the A-12 program should not be terminated.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Transportation v. Eagle Peak Rock & Paving, Inc.
69 F.4th 1367 (Federal Circuit, 2023)
Emiabata v. United States
Federal Circuit, 2019
SYMVIONICS, Inc.
Armed Services Board of Contract Appeals, 2017
Sikorsky Aircraft Corporation v. United States
122 Fed. Cl. 711 (Federal Claims, 2015)
Trust Title Company v. United States
118 Fed. Cl. 99 (Federal Claims, 2014)
AEON Group, LLC
Armed Services Board of Contract Appeals, 2014
AEY, Inc. v. United States
99 Fed. Cl. 300 (Federal Claims, 2011)
General Dynamics Corp. v. United States
131 S. Ct. 1900 (Supreme Court, 2011)
Armour of America v. United States
96 Fed. Cl. 726 (Federal Claims, 2011)
Edge Construction Co. v. United States
95 Fed. Cl. 407 (Federal Claims, 2010)
Yankee Atomic Power Co. v. United States
94 Fed. Cl. 678 (Federal Claims, 2010)
LB&B Associates Inc. v. United States
91 Fed. Cl. 142 (Federal Claims, 2010)
United Partition Systems, Inc. v. United States
90 Fed. Cl. 74 (Federal Claims, 2009)
Takota Corp. v. United States
90 Fed. Cl. 11 (Federal Claims, 2009)
United States v. Washington
573 F.3d 701 (Ninth Circuit, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
567 F.3d 1340, 2009 U.S. App. LEXIS 11716, 2009 WL 1515777, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcdonnell-douglas-corp-v-united-states-cafc-2009.