McDonnell Douglas Corp. v. United States

42 Cont. Cas. Fed. 77,274, 40 Fed. Cl. 529, 1998 U.S. Claims LEXIS 61, 1998 WL 142275
CourtUnited States Court of Federal Claims
DecidedMarch 30, 1998
DocketNo. 91-1204C
StatusPublished
Cited by9 cases

This text of 42 Cont. Cas. Fed. 77,274 (McDonnell Douglas Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McDonnell Douglas Corp. v. United States, 42 Cont. Cas. Fed. 77,274, 40 Fed. Cl. 529, 1998 U.S. Claims LEXIS 61, 1998 WL 142275 (uscfc 1998).

Opinion

OPINION AND ORDER

HODGES, Judge.

INTRODUCTION

Plaintiffs McDonnell Douglas and General Dynamics entered into a full-scale engineering and development (FSED) contract with the Navy in 1988 to develop the A-12, a Stealth aircraft. The Navy terminated the contract for default in 1991. We ruled that the termination for default was improper and converted it into a termination for the convenience of the Government. See McDonnell Douglas Corp. v. United States, 35 Fed.Cl. 358 (1996). The purpose of this opinion is to set forth our reasons for awarding plaintiffs most of the costs that they incurred in performing the A-12 contract.

BACKGROUND

“[I]f, after termination, it is determined that the Contractor was not in default, or that the default was excusable, the rights and obligations of the parties shall be the same as if the termination had been issued for the convenience of the Government.” Federal Acquisition Regulation (FAR) 52.249-9(g). We approach this situation as if the Government had terminated this contract for convenience on January 7, 1991 — the date of the default termination.1

[534]*534Plaintiffs argued that the FAR entitles them to incurred costs plus a reasonable profit, while defendant urged us to adjust plaintiffs’ cost reimbursement amount downward to reflect the loss that they would have sustained had the contract been completed. When the Government terminates a contract for its convenience, the contractor “should be compensated fairly for the work done and the preparations made for the terminated portions of the contract, including a reasonable amount for profit.” FAR 49.201. Typically, the contractor is entitled to recover all of its incurred costs and settlement costs, and reasonable profits if warranted. See FAR 52.249-2(f). If it appears that the contractor would have suffered a loss on the entire contract, however, the contractor would not obtain a profit, and its cost recovery is reduced according to the rate of loss. See id; see also McDonnell Douglas Corp. v. United States, 37 Fed.Cl. 270, 272-73 (1996). For reasons stated in a December 1996 ruling, however, we did not allow profit or consider to what extent a loss ratio might apply. See McDonnell Douglas Corp., 37 Fed.Cl. at 272. We could not consider plaintiffs’ Requests for Equitable Adjustment for similar reasons. See Id. at 272. During trial in June and July 1997, we considered only the costs plaintiffs incurred by performing the A-12 FSED contract, Lots I, and II options, and “wind-up” termination costs.

Plaintiffs presented a termination for convenience claim for $3.992 billion, excluding profit and interest and before application of the “funding cap.”2 The $3.992 billion in costs include: $3.750 billion for the FSED portion of the contract, $.212 billion for Lot I, and $.030 billion for Lot II.3 Plaintiffs submitted their certified termination for convenience claim on a total cost basis in June 1991. Later updates covered costs incurred in the interim, such as subcontractor settlements.

The funding cap imposed by the court limits recovery to $3,499,793,515 for the FSED portion of the contract. Additional funds obligated through the Incentive Price Revision and Economic Price Adjustment clauses raise the funding cap to $3,635,767,-376. Adding to this amount the $.212 billion for Lot I and $.030 billion for Lot II, which are undisputed amounts “outside” of the cap, we arrive at. $3,877,767,376, the highest award possible with the funding cap in place. Unless the Government’s valid challenges would bring the amount claimed by plaintiffs below this figure, findings detailed below have little practical effect.

The parties asked us to determine plaintiffs’ total incurred costs, irrespective of the cap. If the funding cap is higher or does not apply, plaintiffs’ reasonable, allowable, and [535]*535allocable costs total $8,978,002,676. Otherwise, plaintiffs may recover no more than $3,877,767,376.

Problems with the Coopers & Lybrand (Miller) Report

The Government hired Coopers & Lybrand to audit plaintiffs’ incurred costs. This effort was managed by Frederic R. Miller, an auditor who was the Government’s only witness at trial.

The Government’s challenges to plaintiffs’ claimed costs are based entirely upon the Miller Report. Plaintiffs supplied proof with respect to all of their claimed costs to some degree, but more in some areas than in others. Some of these costs could not be awarded if strict accounting standards were employed. We believe that the FAR does not limit such costs to a rigid application of cost accounting standards.

Plaintiffs attacked Mr. Miller’s experience and credibility along with the usefulness of his report. General Dynamics contended that Miller had no personal knowledge and experience with the program. He was “denied access to the very government personnel who were familiar with it,” such as the program manager, contracting officer and class desk. Additionally,

Miller had no experience working for an aircraft design company and no prior experience with an RDT & E program that had been terminated. Miller had only a general sense of what the A-12 contract required; he did not have the necessary security clearances to know what it specifically required. Miller lacked familiarity with the requirements, schedule, and terminology of the A-12 research and development contract, including such issues as concept formulation, DEM/VAL, IDR, PDR, CDR, concurrency, how many radars were required, how many test aircraft were required, how many change orders occurred, when first flight was, and when and how the contract schedule changed. Despite this inexperience, [Coopers & Lybrand] consulted with no one in the Navy who had been involved with the A-12 program for technical assistance — not Captain Elberfeld, not Captain Cook, not Mr. Mutty, and not Admiral Morris. Miller conceded that such information could be competent evidence for an auditor to consider, but observed that he did not have access to such people____ Indeed, the government instructed C & L not to consult with such Navy personnel.

Plaintiffs’ problems with Miller’s report do not stop there. General Dynamics questions, inter alia, Miller’s level of experience/familiarity with the “25% rule” that applies to items being returned to vendors for restocking, Inventory Verification Reports, and plant clearance officers. According to General Dynamics, Miller “did not consider relevant FAR and DCAA Contract Audit Manual ... provisions before questioning plaintiffs’ post-termination relocation expenses.”

Miller’s report claims to represent the “independent and objective opinions of [Coopers & Lybrand] regarding plaintiffs’ termination for convenience claim.” Plaintiffs question this assessment.4 General Dynamics observes that “[d]uring the drafting of the May 1995 reports, Miller consulted with, and received comments from the Department of Justice in order, in Miller’s words, ‘to make sure we were all singing from the same sheet of music in terms of the final report.’ ”

Mr. Miller’s analysis was helpful but marginally useful in determining the proper level of incurred costs. He acknowledged that the audit involved making determinations that were “straight up and down accounting type of decisions____ We viewed our role as providing ... only an audit report that was advisory ...

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kellogg Brown & Root Services Inc. v. United States
103 Fed. Cl. 714 (Federal Claims, 2012)
McDonnell Douglas Corp. v. United States
567 F.3d 1340 (Federal Circuit, 2009)
General Dynamics Corp. v. United States
69 Fed. Cl. 180 (Federal Claims, 2005)
Thermalon Industries, Ltd. v. United States
51 Fed. Cl. 464 (Federal Claims, 2002)
Hercules Inc. v. United States
49 Fed. Cl. 80 (Federal Claims, 2001)
Energy Capital Corp. v. United States
47 Fed. Cl. 214 (Federal Claims, 2000)
Morrison Knudsen Corp. v. Fireman's Fund Insurance
175 F.3d 1221 (Tenth Circuit, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
42 Cont. Cas. Fed. 77,274, 40 Fed. Cl. 529, 1998 U.S. Claims LEXIS 61, 1998 WL 142275, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcdonnell-douglas-corp-v-united-states-uscfc-1998.