McDonnell Douglas Corporation, Plaintiff-Cross and General Dynamics Corporation, Plaintiff-Cross v. United States

182 F.3d 1319, 1999 U.S. App. LEXIS 14805, 1999 WL 450934
CourtCourt of Appeals for the Federal Circuit
DecidedJuly 1, 1999
Docket98-5096, 98-5122, 98-5123
StatusPublished
Cited by69 cases

This text of 182 F.3d 1319 (McDonnell Douglas Corporation, Plaintiff-Cross and General Dynamics Corporation, Plaintiff-Cross v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McDonnell Douglas Corporation, Plaintiff-Cross and General Dynamics Corporation, Plaintiff-Cross v. United States, 182 F.3d 1319, 1999 U.S. App. LEXIS 14805, 1999 WL 450934 (Fed. Cir. 1999).

Opinion

CLEVENGER, Circuit Judge.

This dispute arises out of the government’s default termination of a contract between the United States Navy and defense contractors McDonnell Douglas Corporation and General Dynamics Corporation (“Contractors”) to develop a carrier-based, low-observable “stealth” aircraft known as the A-12 Avenger. After several years of litigation, the United States Court of Federal Claims held that the government’s termination of the contract for default could not be sustained because the government did not exercise the requisite discretion before entering a default termination, see McDonnell Douglas Corp. v. United States, 35 Fed. Cl. 358, 368-71 (1996) (hereinafter McDonnell Douglas IV), and converted the termination for default into a termination for convenience, awarding Contractors costs totaling $3,877,767,376. See McDonnell Douglas Corp. v. United States, 40 Fed. Cl. 529, 555-56 (1998) (hereinafter McDonnell Douglas IX). We hold that, because the termination for default was predicated on contract-related issues, it was within the discretion of the government. Accordingly, the Court of Federal Claims’ conversion of the termination for default into a termination for convenience was in error. We reverse the trial court’s judgment and remand the case to the trial court for a determination of whether the government’s default termination was justified, an issue upon which we express or intimate no view.

I

A

In 1984; the Department of the Navy introduced the Advanced Tactical Aircraft *1322 Program, known as the A-12 program, to develop a carrier-based stealth aircraft for the Navy. In January 1988, Contractors entered into a Full Scale Engineering Development contract (the “A-12 FSD Contract”) with the government to produce eight FSD aircraft at a target price of $4,379,219,436. See McDonnell Douglas IV, 35 Fed. Cl. at 361. The contract was structured as an incrementally funded, fixed-price incentive contract with a ceiling price of • $4,777,330,294, and recited a schedule of installment payments, over the five-year term of the contract. The first aircraft was originally scheduled to be delivered in June 1990, and subsequent aircraft were to be delivered each month through January 1991. See id. at 361-62.

From the outset, Contractors encountered difficulties in performing the contract. Particular problems included meeting the contract schedule and keeping the aircraft weight within specifications. At the beginning of 1990, the Department of Defense initiated a Major Aircraft Review to evaluate various major aircraft programs in view of recent changes around the world and the corresponding reduced threat to national security. See id. at 362. The A-12 program was included in this Review, and Defense Secretary Richard Cheney visited the McDonnell Douglas plant as part of the review process. By the early part of 1990, the Navy’s contracting officer knew that Contractors would not meet the delivery date for the first aircraft. See id. However, although Secretary Cheney was apprised of some concerns in the A-12 program, the review concluded that there was a continuing need for the A-12 and that the Navy should pursue the program. See id. at 363. Secretary Cheney reported these results during his testimony before Congress in April 1990.

In June 1990, Contractors informed the Navy that they could not meet the contract schedule, that the cost of completing the contract would substantially exceed the ceiling price, and that Contractors could not absorb the loss that would result from the contract. Contractors asserted that a fundamental problem with the FSD contract was its structure as a fixed-price contract and proposed that the contract be modified. Thereafter, Contractors submitted a proposal to change the contract schedule, but the Navy and Contractors failed to reach an agreement on that issue. Instead, on August 17, 1990, the Navy unilaterally issued a contract modification that changed the delivery schedule for the aircraft. Under this modification, the delivery date of the first aircraft was delayed until December 1991, and the remaining aircraft became due periodically between February 1992 and February 1993. See Contract Modification P00046 ¶ 1(b), Joint Appendix at 15,657.

In November 1990, Contractors submitted a formal request to the Navy to restructure the contract as a cost-reimbursement type contract. At the end of the same month, two reports were published which documented the handling of the A-12 program under the Major Aircraft Review. The Navy’s “Beach Report,” dated November 28, 1990, found that the A-12 program manager had been unreasonable both in reaching a conclusion that the contract could be performed within the ceiling price and in evaluating the risk of failing to meet the contract schedule. See McDonnell Douglas IV, 35 Fed. Cl. at 363. The Beach Report criticized several Navy officials involved in the A-12 program. Separately, a November 29, 1990 Department of Defense Inspector General report concluded that problems in the A-12 program were inaccurately identified during the Review because the Review did not accord with specified procedures and was otherwise handled poorly. See id.

During the Secretary’s briefing to the President of the United States in early December 1990, the Secretary indicated his disappointment with the Navy’s handling of the A-12 program and promised to take appropriate actions. On December 3, the Secretary directed the Deputy Secretary of Defense to review and report on the status of the A-12 program within ten *1323 days. This resulted in several meetings by the Defense Acquisition Board and Defense Procurement Review Boards. In addition, on December 12, the Secretary of the Navy responded to Secretary Cheney’s December 3 request with a memorandum that expressed concern about Contractors’ ability and willingness to perform under the contract, and which noted in particular Contractors’ belief that the government should assume responsibility for failure to meet goals under the contract, and that the government should restructure the contract. The memorandum concluded with a statement that the Navy would examine whether the contract should be terminated for default, and would make a recommendation to the Secretary by January 5,1991. See id.

On Friday, December 14, Secretary Cheney directed the Secretary of Navy to show cause by January 4, 1991 why the A-12 program should not be terminated. The following Monday, December 17, the Navy issued a cure notice to Contractors stating that unless they were able to meet contract specifications by January 2, 1991, the government might choose to terminate the contract for default. In particular, the cure letter stated that, inter alia, Contractors had “failed to fabricate parts sufficient to permit final assembly in time to meet the schedule for delivery,” and had “fail[ed] to meet specification requirements.” Joint Appendix at 16,524. The letter asserted that “[t]hese conditions are endangering performance of [the] contract.” Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Transportation v. Eagle Peak Rock & Paving, Inc.
69 F.4th 1367 (Federal Circuit, 2023)
GSC Construction, Inc.
Armed Services Board of Contract Appeals, 2020
Aerospace Facilities Group, Inc.
Armed Services Board of Contract Appeals, 2020
Watts Constructors, LLC
Armed Services Board of Contract Appeals, 2019
Raytheon Company
Armed Services Board of Contract Appeals, 2017
Pyrotechnic Specialties, Inc.
Armed Services Board of Contract Appeals, 2017
Delfasco LLC
Armed Services Board of Contract Appeals, 2017
Sanchez v. Brennan
679 F. App'x 671 (Tenth Circuit, 2017)
Canpro Investments, Ltd v. United States
130 Fed. Cl. 320 (Federal Claims, 2017)
Third Coast Fresh Distribution, L.L.C.
Armed Services Board of Contract Appeals, 2016
Securiforce International America, LLC v. United States
125 Fed. Cl. 749 (Federal Claims, 2016)
Allen Engineering Contractor Inc. v. United States
611 F. App'x 701 (Federal Circuit, 2015)
Trust Title Company v. United States
118 Fed. Cl. 99 (Federal Claims, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
182 F.3d 1319, 1999 U.S. App. LEXIS 14805, 1999 WL 450934, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcdonnell-douglas-corporation-plaintiff-cross-and-general-dynamics-cafc-1999.