Hardeman-Monier-Hutcherson v. United States

458 F.2d 1364, 198 Ct. Cl. 472, 1972 U.S. Ct. Cl. LEXIS 205
CourtUnited States Court of Claims
DecidedMay 12, 1972
DocketNo. 353-70
StatusPublished
Cited by61 cases

This text of 458 F.2d 1364 (Hardeman-Monier-Hutcherson v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hardeman-Monier-Hutcherson v. United States, 458 F.2d 1364, 198 Ct. Cl. 472, 1972 U.S. Ct. Cl. LEXIS 205 (cc 1972).

Opinion

Per Curiam: :

This opinion was prepared 'by Judge Collins before bis death and has been adopted by the court.

The facts in this Government contract case are not in dispute. They are set forth below as they appear in the decision of the Armed Services Board of Contract Appeals (hereinafter ASBCA or board). The case is before the court on the parties’ cross-motions for summary judgment.

Plaintiff, Hardeman-Monier-Hutcherson, is a joint venture consisting of American and Australian corporations. In mid-July 1963, after competitive bidding, plaintiff was awarded [476]*476a contract at a fixed price of $34,880,000 for the first increment of the construction of a radio communications facility for the United States Navy at North West Cape, Western Australia.

North West Cape is located at the confluence of the western side of Exmouth Gulf with the Indian Ocean. It is an area remote from the population centers of Australia, and prior to the inception of this project the area was uninhabited. The nearest city, Perth, is located 850 miles to the south.

Among the items of work to be constructed was a pier, approximately 1,100 feet in length, extending from the shore into the Exmouth Gulf in an easterly direction. Due to the remoteness of the site, it was contemplated that the pier would be utilized by plaintiff, as well as by other contractors, for the offloading of ships carrying equipment, materials, and supplies. Thus, the construction of the pier was of vital importance to the completion of the entire project and, for this reason, it was given a relatively short construction time of 360 days. Liquidated damages in the amount of $600 were to be assessed for each day of unexcused delay beyond the “usable completion date” fixed at July 13,1964. The pier was actually accepted as usably complete on January 3, 1967. However, the contracting officer extended the completion time 334 days, due to excusable delays.

The beaches around North West Cape and its vicinity are fronted with, coral reefs. There is relatively deep water close inshore at Point Murat, which projects into Exmouth Gulf approximately 2.5 miles southeast of the tip of North West Cape. Prior to the invitation for bids and during the project design period, various studies were made to decide upon the location and design of the pier. Between July 6 and 31,1961, at the request of the United States Navy, soundings were taken in the area southward of Point Murat by the Department of Public Works of Western Australia. This was done by the crew of the department’s vessel “Gunga Din,” under the command of Captain Piggford. Due to bad weather and rough seas, the crew took 25 days to complete the task instead of 2 weeks, as Captain Piggford had originally estimated. Captain Piggford reported, in part:

[477]*4773.1. Considering Area ‘A’, the area at Point Murat in which the proposed jetty or pier is to be sited—
From a general hydrographic and navigational viewpoint, the site has some obvious advantages—
(i) Protection from winds and sea from S.W. to N.W.
(ii) Deep water comparatively close inshore.
(iii) Relatively deep and clear approaches.
3.2. Disadvantages perhaps not so obvious are—
(i) Pt. Murat is a point of convergence for tidal streams of velocities up to Sy2 feet per second, causing overfalls1 on both ebb and flood tides.
(ii) In the southern winter season, winds are mainly N.E. to S.S.E. This area is exposed to all winds from N. to S. through east with a fetch of 25-30 miles or more in practically all of these directions.
This, combined with the overfalls mentioned in (i) above can set up an unpleasantly rough sea on occasions.
(iii) It is an evident fact that the advantages outlined in 3.1. (ii) and (iii) are due to the scouring action of strong tides and to the exposed nature of this corner.
3.3. It follows that the further south, away from the point, that the jetty or pier can be constructed, the better will be the conditions for it.

Notwithstanding this unfavorable report, the United States Navy chose as the pier site a location approximately 800 feet south of Point Murat. Captain Piggford had ceased his soundings without covering the entire pier site because, in his opinion, no one would build a pier at that location due to the severe weather and sea conditions.

The “Gunga Din” returned to Exmouth Gulf on June 13, 1962, this time under the command of Captain Drexel, for the purpose of taking additional soundings and core borings at the site. As before, the survey work was repeatedly delayed and the ship and crew were endangered by bad weather and rough seas. Finally, on August 17, 1962, the second survey was completed. This resulted in a report of the Senior Engi[478]*478neer, Harbours and Rivers Division (hereinafter the Drexel report), which contained the following comments:

It was unfortunate that the timing for this job entailed working on the west side of a very large Gulf during the seasonal period of SE, E & NE winds, with regular intensities of 20 to 30 knots.
íji #
2. The location does not commend itself for floating-
plant operation.
Aspects to be considered are:
(a) The mass of coral outcrop projecting from the seabed, some as high as '6 feet, inside the wharf face, render the moving of mooring wires and chains difficult, and navigation hazardous.
(b) Although we found a reasonably protected area ■for mooring our 40' workboat, draft 4'9 behind the reef line, the water depths are the absolute minimum and further restricted by odd outcrops of coral. Heavy floating plant would require larger tug power, for which there is no safe mooring area. Cyclones would render the whole water area particularly dangerous and impossible for moored craft. Short term use of floating plant at selected times of the year would be practicable, the plant being removed from the area outside these periods.
It would have been quite impracticable to drive piles from floating rigs during the period the “GUNGA DIN” was at Exmouth, except for the odd small number of calm days.

Captain Drexel also measured currents along the face of the pier on several days in mid-July. He found such currents to range from approximately 2.5 to over 4 knots on ebb tide.

The invitation for bids was accompanied by a document entitled “Information for Bidders,” which contained the following:

1. The following is furnished as general information to prospective bidders. This does not relieve bidders from the need for making site inspection, investigation, and analysis. These papers are not considered as being part of the contract documents; publication of this information does not imply any responsibility on the part [479]*479of the TJ.S. Government. In no event may this information be made the basis for contract claim against the Government or used in furtherance of any such claim.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

H&L Contracting LLC
Armed Services Board of Contract Appeals, 2025
Shoreline Foundation, Inc.
Armed Services Board of Contract Appeals, 2024
Agredano v. United States
82 Fed. Cl. 416 (Federal Claims, 2008)
Land Grantors v. United States
74 Fed. Cl. 518 (Federal Claims, 2006)
Daewoo Engineering & Construction Co. v. United States
73 Fed. Cl. 547 (Federal Claims, 2006)
Sweetwater, A Wilderness Lodge LLC v. United States
72 Fed. Cl. 208 (Federal Claims, 2006)
Federal Group, Inc. v. United States
67 Fed. Cl. 87 (Federal Claims, 2005)
Renda Marine, Inc. v. United States
66 Fed. Cl. 639 (Federal Claims, 2005)
Conner Brothers Construction Co. v. United States
65 Fed. Cl. 657 (Federal Claims, 2005)
D.F.K. Enterprises, Inc. v. United States
45 Fed. Cl. 280 (Federal Claims, 1999)
TANO Automation, Inc. v. United States
939 F. Supp. 483 (E.D. Louisiana, 1996)
Hardwick Bros. v. United States
41 Cont. Cas. Fed. 76,972 (Federal Claims, 1996)
Sergent Mechanical Systems, Inc. v. United States
40 Cont. Cas. Fed. 76,860 (Federal Claims, 1995)
Miller Elevator Co. v. United States
39 Cont. Cas. Fed. 76,635 (Federal Claims, 1994)
Reliance Insurance v. United States
38 Cont. Cas. Fed. 76,494 (Federal Claims, 1993)
Wm. T. Thompson Co. v. United States
38 Cont. Cas. Fed. 76,311 (Court of Claims, 1992)
Hercules Inc. v. United States
37 Cont. Cas. Fed. 76,291 (Court of Claims, 1992)
Granite Construction Co. v. United States
37 Cont. Cas. Fed. 76,240 (Court of Claims, 1991)
A.S. McGaughan Co. v. United States
37 Cont. Cas. Fed. 76,239 (Court of Claims, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
458 F.2d 1364, 198 Ct. Cl. 472, 1972 U.S. Ct. Cl. LEXIS 205, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hardeman-monier-hutcherson-v-united-states-cc-1972.