H&L Contracting LLC

CourtArmed Services Board of Contract Appeals
DecidedAugust 18, 2025
Docket63695
StatusPublished

This text of H&L Contracting LLC (H&L Contracting LLC) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
H&L Contracting LLC, (asbca 2025).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of - ) ) H&L Contracting LLC ) ASBCA No. 63695 ) Under Contract No. W912WJ-22-C-0012 )

APPEARANCES FOR THE APPELLANT: Michael H. Payne, Esq. Cohen Seglias Pallas Greenhall & Furman PC Philadelphia, PA

Matthew C. Long, Esq. Cohen Seglias Pallas Greenhall & Furman PC Washington, DC

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Theresa A. Negron, Esq. Sheena M. Wandera, Esq. Engineer Trial Attorneys U.S. Army Engineer District, New England

OPINION BY ADMINISTRATIVE JUDGE MCLISH

Appellant H&L Contracting LLC (H&L) appeals from the final decision of a contracting officer for the United States Army Corps of Engineers (USACE) denying H&L’s claims arising from a contract to dredge channels at Newburyport Harbor, Massachusetts.

The contract required dredging of shoaled sediments from two channels: a nine-foot channel within the harbor adjacent to the Town of Newburyport and a 15-foot channel located at the mouth of the Merrimack River where it meets the Atlantic Ocean. (R4, tab 6 at 180, tab 7 at 221-22) This appeal involves the 15-foot channel, also called the entrance channel.

H&L intended to use its cutterhead dredge the Oyster Bay to dredge the entrance channel. The Oyster Bay, however, completed none of the required dredging due to the size of the sea swell at the channel. H&L eventually abandoned its plan and subcontracted with another company to provide a larger dredge better able to perform in the conditions at the entrance channel at that time of year. That larger dredge quickly completed the work. H&L then submitted a claim to USACE seeking the extra costs it incurred in subcontracting for the larger dredge, alleging that USACE withheld superior knowledge and issued defective specifications. It contends in the alternative that the parties made a mutual mistake of fact.

After we denied cross-motions for summary judgment, the parties agreed to submit the appeal for a decision without a hearing under our Rule 11. Only entitlement is before us. For the reasons below, we sustain the appeal as to entitlement.

FINDINGS OF FACT

I. The Solicitation

The parties’ dispute largely concerns the content of the solicitation issued by USACE on May 20, 2022 for the Newburyport dredging contract that was ultimately awarded to H&L (the Solicitation) (app. supp. R4, tab 20 at 1636). 1

The drawings showed that the entrance channel was located at the mouth of the Merrimack River, near two jetties protecting the harbor, and extending out into the Atlantic Ocean (R4, tab 7 at 222-23). The specifications included the following description of the sea conditions at the entrance channel:

The tidal currents at the entrance to the harbor can be substantial, creating potentially dangerous conditions. Under good weather conditions, the sea swell is typically 1-2 feet in a northerly direction. In normal weather conditions, the sea swell can range from 2 to 4 feet or more.

(R4, tab 6 at 182, tab 4 at 158)

The Solicitation stated that its description of the project conditions “is for the Contractor's information” and that the government “shall not be responsible for any

1 This decision references three solicitations. The solicitation that led to the contract in dispute, Solicitation No. W912WJ-22-B-0011, is referred to as “the Solicitation.” The solicitation USACE issued in 2010 for a contract to dredge the same entrance channel at Newburyport is referred to as “the 2010 Solicitation.” Finally, the USACE solicitation for a contract to dredge at nearby Hampton Harbor, New Hampshire, is referred to as “the Hampton Harbor Solicitation.” 2 interpretation of or conclusion drawn from the data or information by the Contractor” (R4, tab 6 at 182). The specifications further indicated that “[b]efore commencing work at the site, the Contractor shall verify the existing conditions indicated on the drawings and in the specifications,” and included a standard Federal Acquisition Regulation (FAR) clause under which the contractor acknowledges that it has “investigated and satisfied itself as to the general and local conditions which can affect the work or its cost,” including such things as “uncertainties of weather . . . , tides, or similar physical conditions at the site,” as well as “the character of equipment . . . needed during work performance. . . .” (id.; R4, tab 4 at 139 (incorporating FAR 52.236-3, SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK (APR 1984)).

Among the USACE employees assigned to the Newburyport project team and tasked with preparing and approving the contract specifications in the Solicitation were Brendan Sprague and Thomas Marcotte (app. br., ex. 2 at 7). Mr. Sprague prepared the initial draft of Specification 01 11 00, which included the description of sea conditions quoted above. Mr. Marcotte drafted the remaining Specifications (app. br., ex. 7, Marcotte depo tr. at 74:5-22). Mr. Sprague and Mr. Marcotte were knowledgeable of sea conditions at the entrance channel based on prior assignments for USACE, including the preparation of the 2010 Solicitation, discussed in more detail below.

Mr. Sprague based the Solicitation’s description of sea conditions in the Newburyport channels on USACE’s solicitation a few years earlier for dredging Hampton Harbor, New Hampshire (the Hampton Harbor Solicitation) (app. br., ex. 1, Sprague depo tr. at 54:3-11). Hampton Harbor is located roughly five miles from Newburyport and that project also involved dredging an entrance channel leading from the Atlantic Ocean into the harbor (app. supp. R4, tab 3 at 399; app. br. ex. 4, Haney depo tr. at 32:19-25, 44:3-25). H&L had been the contractor for that project and successfully completed the dredging there in November and December 2019 using a 16-inch cutterhead dredge (app. br., ex. 3, Haney aff. ¶ 6; ex. 5, Coward depo tr. at 30:2-8, 39:9-13).

The Hampton Harbor Solicitation had described the conditions there as:

e. Conditions at Entrance Channel to Harbor: The tidal currents at the entrance to the Harbor can be substantial (up to 5 knots during maximum flood and ebb tidal periods), creating a potentially dangerous condition. Under optimum weather conditions, the sea swell is typically 1-2 feet in a southerly direction. In normal weather, the sea swell can range from 2-4 feet.

3 (App. supp. R4, tab 3 at 402) Mr. Marcotte had been involved in preparing the specifications for the Hampton Harbor Solicitation (app. supp. R4, tab 6 at 742-43). He testified that the conditions at the Newburyport Harbor entrance channel presented a “rougher situation” than those at the Hampton Harbor entrance channel (app. br., ex. 7, Marcotte depo tr. at 78:22-79:2).

The Solicitation’s description of conditions at the 15-foot channel at Newburyport was similar, but not identical, to USACE’s description of conditions at Hampton Harbor. Specifically, USACE changed the word “optimum” to “good”, changed the wind direction from “southerly” to “northerly,” and added the words “or more” after “2-4 feet” (compare app. supp. R4, tab 3 at 402 with R4, tab 6 at 182). The words “or more” were added at the suggestion of a USACE employee in the Construction Office who lacked specific knowledge of the sea conditions at the entrance channel and who had previously advocated omitting any description of the sea conditions (app. br., ex. 1, Sprague depo tr. at 102:6-103:23). Mr. Marcotte rejected omitting any mention of the sea conditions, stating “[a] non-local may not be fully aware at bidding. The Merrimack at the mouth can be a challenge and I would like to get this information out.” (App. supp. R4; tab 11 at 992) Mr. Marcotte, however, concurred with adding the phrase “or more” (id. ; app. br. ex. 1, Sprague depo tr. at 130:10-12). Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
H&L Contracting LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hl-contracting-llc-asbca-2025.