TANO Automation, Inc. v. United States

939 F. Supp. 483, 1996 WL 537744
CourtDistrict Court, E.D. Louisiana
DecidedSeptember 20, 1996
DocketCivil Action No. 94-2620
StatusPublished

This text of 939 F. Supp. 483 (TANO Automation, Inc. v. United States) is published on Counsel Stack Legal Research, covering District Court, E.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
TANO Automation, Inc. v. United States, 939 F. Supp. 483, 1996 WL 537744 (E.D. La. 1996).

Opinion

ORDER AND REASONS

BERRIGAN, District Judge.

This matter comes before the Court on motion for summary judgment filed by the defendant, United States of America (“United States”). Having considered the record, the memoranda of counsel and the law, the Court has determined that summary judgment is appropriate for the following reasons.

The undisputed facts show that in 1987, the plaintiff, TANO Automation, Inc. (“TANO”), entered into a contract with the Coast Guard to design, produce, test and install a computer system for two Coast Guard polar icebreakers. After beginning work on the contract, TANO suspected error in the Government-Furnished Information (“GFI”) supplied by the Coast Guard. In April 1989, TANO submitted a Rough Order of Magnitude (“ROM”) setting forth an estimate of the resulting additional costs. Negotiations between TANO and the Coast Guard began at that time. TANO resubmitted the ROM as a Request for Equitable Adjustment (“REA”), which was subsequently revised by letters, the last of which was dated September 19, 1989. On October 1, 1989, the Coast Guard accepted the settlement counter-offer made by TANO. In January 1990, the parties made the “Supplemental Agreement of Settlement and Release of Liability” part of their contract by signing a bilateral modification (“Modification 20”).

[485]*485TANO maintains that the settlement concerned only additional costs and performance delays caused by defective GFI in the design phase of the contract. In this suit, TANO seeks recovery of subsequent additional costs it allegedly incurred because of defective GFI. It also claims that the Coast Guard knew its GFI was defective even before accepting bids for the project, that the Coast Guard had concealed the fact that its GFI were grossly defective from bidders and that the defectiveness of the GFI was also concealed from TANO in negotiations leading to the settlement agreement.

TANO is suing the United States for the additional monies allegedly owed under the contract and argues that the settlement is void because of mutual mistake and fraud. In this motion, the United States argues first that TANO’s claims are barred because of the settlement. It further claims that the TANO cannot prove fraud as a matter of law and that TANO has otherwise ratified the settlement.

SETTLEMENT

The language in the settlement document entitled “Supplemental Agreement of Settlement and Release of Liability” provides in pertinent part:

WHEREAS, the Contractor has submitted, by letters dated 12 April 1989, 25 May 1989, 6 June 1989 and 29 August 1989, a Request for Equitable Adjustment in the amount of $1,712,922.46 which includes allegations of defective Specifications and Government Furnished Information provided as a part of this contract ...
* * 4* * * 4*
WHEREAS, The Government and the Contractor desire now to settle these issues under the Contract;
NOW, THEREFORE, in consideration of the foregoing, the parties do mutually agree as follows:
******
ARTICLE 2 — THE REQUEST FOR EQUITABLE ADJUSTMENT
This Supplemental Agreement constitutes full and final compensation for all costs, including costs of travel and inspection aboard the cutters such as discussed in the Contractor’s letter 4910-1681-165 dated 20 September 1989, associated with the Contractor’s Request for Equitable Adjustment as described in the following letters:
* Serial 4910-1681-07 dated 14 September 1988;
* Unserialized letter dated 12 April 1989;
* Serial 4910-1681-139 dated 25 May 1989;
* Serial 4910-1681-142 dated ' 6 June 1989; and
* Serial 4910-1681-156 dated 29 August 1989.
******
ARTICLE 16 — FULL AND FINAL SETTLEMENT
(a) The Contractor ... hereby remises, releases, and forever discharges the Government ... from (i) any and all actual or potential entitlement of the Contractor to any equitable adjustment in the Contract price or delivery schedule, or both, of this contract for Covered Events or for the impact of Covered Events; and (ii) any and all actual or potential liabilities to the contractor for money damages and/or other relief for Covered Events or for the impact of Covered Events upon this contract.
******
(2) “Covered Events” refers to events occurring before the effective date of this Supplemental Agreement, whether formal or constructive, which were known or rea- ■ sonably should have been known to the Contractor as of the effective date of this Supplemental Agreement.
(d)(1) The Contractor hereby confirms and acknowledges that in agreeing to the terms of this Supplemental Agreement, it has considered, made full allowance for, and is releasing all rights to any entitlement for any and all costs under, and any and all impacts upon, this Contract, whether or not such costs and impacts are known or unknown or foreseeable or unforeseeable as of the effective date of this Supplemental Agreement, whether or not [486]*486such costs and impacts have been discussed with, or for any reason reserved for future discussion with, the Government, or have been made the basis for other assertions of claims or request for equitable adjustment, whether or not such costs and impacts were, or are, incurred and sustained, respectively, before or after the effective date of this Supplemental Agreement, and whether or not such costs and impacts are caused directly by, indirectly by, cumulatively by, or in consequence of the impact of any of the Covered Events. * * * * * *
(d) The Contractor’s release is complete and final, no rights are reserved under this Supplemental Agreement, and in any event, any and all such rights shall be deemed to have been waived without exception.

(Rec.Doc. 23, Exh. C).

TANO does not take issue with any specific word or words in the release. Neither does TANO controvert the “one critical and undisputed fact” asserted by the United States that only one set of GFI exists; that was delivered to TANO prior to 1989 and forms the basis of its settled claims. (Rec. Doe. 23, p. 2) (emphasis original). Rather, TANO argues that it may introduce extrinsic evidence to prove intent without first establishing an ambiguity in the release and that the United States may not rely on the release if the United States is guilty of passive fraud or bad faith.

TANO’s argument for the consideration of extrinsic evidence relies heavily on United States v. Lennox Metal Manufacturing Co., 225 F.2d 302 (2d Cir.1955), which focused on the word “may” in a contract drafted by the government. However, that court clearly did

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Williams v. Phillips Petroleum Co.
23 F.3d 930 (Fifth Circuit, 1994)
Mingus Constructors, Inc. v. The United States
812 F.2d 1387 (Federal Circuit, 1987)
Michael Rose Productions v. Loew's Incorporated
143 F. Supp. 606 (S.D. New York, 1956)
King Fisher Marine Service, Inc. v. United States
35 Cont. Cas. Fed. 75,616 (Court of Claims, 1989)
United States v. Lennox Metal Manufacturing Co.
225 F.2d 302 (Second Circuit, 1955)
Hardeman-Monier-Hutcherson v. United States
458 F.2d 1364 (Court of Claims, 1972)
Ingram Corp. v. J. Ray McDermott & Co.
698 F.2d 1295 (Fifth Circuit, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
939 F. Supp. 483, 1996 WL 537744, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tano-automation-inc-v-united-states-laed-1996.