Renda Marine, Inc. v. United States

65 Fed. Cl. 152, 2005 U.S. Claims LEXIS 105, 2005 WL 950506
CourtUnited States Court of Federal Claims
DecidedApril 19, 2005
DocketNo. 02-306 C
StatusPublished
Cited by6 cases

This text of 65 Fed. Cl. 152 (Renda Marine, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Renda Marine, Inc. v. United States, 65 Fed. Cl. 152, 2005 U.S. Claims LEXIS 105, 2005 WL 950506 (uscfc 2005).

Opinion

OPINION AND ORDER

HEWITT, Judge.

Before the court1 is plaintiffs Motion for Trial Amendment (Pl.’s Mot.), filed eleetroni-[154]*154cally on April 6, 2005, which the court construes as a motion for an amendment of the pleadings pursuant to Rule of the Court of Federal Claims (RCFC) 15(b). In its motion, plaintiff claims that “the issue of what amount is owed by the Corps to Renda as its unpaid earned contract balance has been tried by implied consent of the parties,” PL’s Mot. at 3, and asks “that the [c]ourt permit [pjlaintiff to amend its Complaint to conform to the evidence presented at the trial of this matter so that the Complaint clearly sets forth the issue that has been tried by implied consent of the [djefendant,” id. at 1; see also id. at 2-3 (citing RCFC 15(b) (2004)). In a telephonic oral argument, held on the record on April 13, 2005 pursuant to the court’s Order dated April 12, 2005, the parties addressed the propriety of plaintiffs motion and, in particular, whether a jurisdictional basis exists for the amendment of plaintiffs complaint.

I. Background

A. Plaintiffs Complaint

On April 11, 2002, plaintiff filed suit against the United States, acting through the Army Corps of Engineers, Galveston (TX) District (defendant). Complaint (Compl.) at 1. Plaintiff alleges that it encountered a number of differing site conditions during the course of its performance of the Upper Bayou Project Contract (Upper Bayou Contract or Contract). See id. at 3, 1111. The Contract involved dredging a portion of the Houston-Galveston Navigation Channel and the mechanical and hydraulic construction of levees at the Lost Lake Placement Area. See Renda Marine, Inc. v. United States, 58 Fed.Cl. 57, 58 (2003) (Renda I). In its complaint, plaintiff seeks $14,244,848 in damages resulting from the alleged differing site conditions,2 Compl. at 29, and requests that “[ujnder the circumstances, the Corps should release and/or waive any and all liquidated damages,” id. at 28.

A four-week trial of this matter was held in Houston, Texas. Plaintiff presented its case-in-ehief from February 27, 2005 through March 11, 2005 and defendant presented its case-in-chief from March 28, 2005 through April 7, 2005. Post-trial briefing is now underway.

B. Plaintiffs Motion to Amend its Complaint

On April 6, 2005, plaintiff electronically filed a motion to amend its pleadings to conform to evidence presented at trial on March 10, 2005, during the testimony of Mr. Rudy Renda, one of plaintiffs two designated corporate representatives. See generally, PL’s Mot. at 2-4. The direct examination of Mr. Renda focused on the contents of three joint exhibits (JX): Pay Estimate Nos. 29 and 30, see JX 8.029 & 8.030, which plaintiff submitted to defendant to request payment for work performed under the Contract, and Contract Modification No. 28, which was issued by defendant on September 18, 2001 and deleted all remaining work from the Contract, see JX 6.028. Of the three exhibits, only Pay Estimate 29 was admitted during Mr. Renda’s testimony.

Using Pay Estimate No. 29 as a template, plaintiffs counsel asked Mr. Renda to explain the information recorded in each column of the document and focused on various sums that were billed by plaintiff to defendant. See Transcript of Trial (Trial Tr.) at 2571:4-2577:22. Plaintiffs counsel moved this exhibit into evidence without objection from defendant’s counsel. Id. at 2577:19-22.

Mr. Renda then was questioned about Pay Estimate No. 30. His testimony focused primarily on two items that were billed to the defendant, but allegedly not paid for: $140,000 for hydraulic levee construction, see id. at 2579:5-7, 2584:3-6, and $259,840.85 in [155]*155earned contract retainage, see id. at 2583:14-25. Plaintiffs counsel asked Mr. Renda, “Now, if you add [$]140,000 to the $259,840.85 figure, what do you get, sir?” Id. at 2584:7-8. Mr. Renda replied, “Well, they would still owe us $399,840.85, and if that’s the case they — they still would owe that to us, yes.” Id. at 2584:9-11; see also id. at 2584:13-14 (statement of Mr. Renda that “they would owe us [$]399,840.85”). Plaintiffs counsel then asked Mr. Renda, “As of June 2001, the date of this payment estimate, did the Corps of Engineers give Renda any reason why they weren’t paying that amount [the $399,840.85]?,” id. at 2584:20-22, and Mr. Renda replied, “No,” id. at 2584:23. Defendant did not object to Mr. Renda’s testimony about Pay Estimate No. 30.

Plaintiffs counsel then showed Mr. Renda JX 6.028, the September 18, 2001 contract modification deleting all remaining dredging and levee construction work from the contract. Id. at 2584:25. Mr. Renda testified that his understanding of the modification was that “[Renda] w[as] done” with its work under the contract. Id. at 2586:25. Plaintiffs counsel asked Mr. Renda whether, “at the time that this [modification] was issued, did the Corps of Engineers give Renda any reason why the Corps was not paying the contract balance.” Id. at 2587:1-3. Mr. Renda replied, “No.” Id. at 2587:4. Although this question assumed that plaintiff never was paid the contract balance — a fact not in evidence when Mr. Renda testified — defendant did not object. Nor did defendant cross-examine Mr. Renda concerning any of his testimony.

Approximately four weeks later, plaintiffs counsel filed a Rule 15(b) motion to amend its pleadings to conform to the testimony and evidence presented during the examination of Mr. Renda. In its motion, plaintiff argues that

[c]ounsel for the Government did not object to any of Mr. Renda’s testimony ... nor did he object to either of the exhibits admitted into evidence (Joint Exhibits 8.029 and 8.030) in support of such testimony.3 Further, counsel for the Government did not even cross-examine Mr. Renda on any of his testimony regarding the issue of the earned but unpaid contract balanced claimed by Renda as due an[d] owing from the Corps. In the absence of any objection by the Government to the foregoing evidence, the Court should conclude that the issue of what amount is owed by the Corps to Renda as its unpaid earned contract balance has been tried by implied consent of the parties.

Pl.’s Mot. at 3 (footnote added).

In its motion, plaintiff provides a four-paragraph “amendment, which is to be inserted immediately after paragraph 197 of the Complaint and in substitution of the ‘Liquidated Damages’ section of the Complaint.” Pl.’s Mot. at 1. The proposed amendment to plaintiffs complaint is titled “Release of Liquidated Damages — Payment of Earned Contract Balance,” id., and seeks the following relief:

The Corps should release all withheld earned contract funds, including any amounts withheld for alleged liquidated damages and Renda should be paid an amount not less than $399,840.85 as its earned contract balance, including contractual retainage. The amount due Renda is in addition to the various amounts requested for the claims addressed herein.

Id. at 2, ¶ 201.

C. The November 2002 Contracting Officer’s Final Decision

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Thorington Electrical and Construction Company
Armed Services Board of Contract Appeals, 2017
United States v. Oscar Renda
709 F.3d 472 (Fifth Circuit, 2013)
Bannum, Inc. v. United States
80 Fed. Cl. 239 (Federal Claims, 2008)
Renda Marine, Inc. v. United States
71 Fed. Cl. 378 (Federal Claims, 2006)
Lockheed Martin Corp. v. United States
70 Fed. Cl. 745 (Federal Claims, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
65 Fed. Cl. 152, 2005 U.S. Claims LEXIS 105, 2005 WL 950506, Counsel Stack Legal Research, https://law.counselstack.com/opinion/renda-marine-inc-v-united-states-uscfc-2005.