Renda Marine, Inc. v. United States

66 Fed. Cl. 639, 2005 WL 1793421
United States Court of Federal Claims·Decided July 28, 2005·No. No. 02-306C·Published·Cited by 27 cases

Opinion

OPINION

HEWITT, Judge.

This case is before the court following trial on claims1 by plaintiff Renda Marine, Inc. (Renda, RMI or plaintiff) that it encountered six Type I differing site conditions,2 one Type II differing site condition,3 and one constructive contract modification4 during the course of its performance of Contract No. DACW64-99-C-0001, known as the Upper Bayou Project Contract (Upper Bayou Contract or Contract). See Complaint (Compl.) n 10-11, 20-31, 54-61, 75-79, 84-88, 91-95, 102-15, 122-37, 148-83. The Upper Bayou Contract involved dredging a portion of the Houston-Galveston Navigation Channel (the [643] Channel) and constructing perimeter levees and other structures at a disposal area known as Lost Lake to contain material to be dredged under the Contract and material to be later dredged under other contracts. See generally Joint Exhibit (JX) 2 (Contract Specifications for Dredging Upper Bayou (Specs.)); JX 5 (Contract Plans and Drawings (Drawings)); see also Transcript of Trial (Tr.) at 3098:15-21, 3171:5-8 (C. Michael McClenan, Administrative Contracting Officer) (explaining that the levees were designed to contain material dredged under contracts issued for 50 years following the Upper Bayou Contract); cf. id. at 4150:18-25 (J. Timothy Few, civil engineer) (explaining that the designs of “all of the placement areas” in the 45-Foot Project were predicated on a “50-year dredge material management plan”). Plaintiff seeks $10,842,811 in damages. Post-Trial Brief by Plaintiff, Ren-da Marine, Inc. (Pl.’s Br.) at 2, 98; cf Tr. at 2456:10-11 (plaintiffs damages expert, Robert McCullough); Plaintiffs Exhibit (PX) 1863A (Summary of Plaintiffs Claims by Mr. McCullough) (Revised McCullough Rep.) at 1.

I. Introduction

Between February 28 and April 7, 2005, the court conducted nineteen days of trial, during which it heard the testimony of twenty-two live witnesses5 and admitted more than five hundred exhibits into evidence. In [645] addition to the record amassed during trial, the court has reviewed deposition testimony from twelve witnesses,6 see generally JX 94A-JX 106B, and has had the opportunity to consider extensive post-trial briefing filed by the parties, see generally PL’s Br.; Defendant’s Posh-Trial Brief (Def.’s Br.); Reply Brief by Plaintiff, Renda Marine, Inc. (PL’s Reply); and Defendant’s Reply to Plaintiffs Post-Tidal Brief (Def.’s Reply).

The court found the testimony of all of the witnesses before it to be given earnestly and in good faith. However, plaintiffs witness Mr. Bowman at times appeared so committed to establishing plaintiffs trial positions that his testimony was more than once at odds with deposition testimony that proved unhelpful to plaintiff’s case at trial. For example, in an effort to establish that plaintiffs pre-bid site investigation was both reasonable and through, Mr. Bowman testified at trial that plaintiffs pre-bid investigation of the Channel and the Lost Lake Placement Area lasted “two days and one night,” Tr. at 552:6-7 (Bowman). During cross-examination, defendant’s counsel reminded Mr. Bowman of his deposition testimony that the investigation lasted only “one afternoon and one evening.” Tr. at 1501:10-12 (Def.’s Counsel) (quoting JX 99A (Bowman Dep.) at 37:14-15). When confronted with his deposition, Mr. Bowman did not contradict his earner testimony and conceded that a significant portion of this brief investigation took place “after dark.” See generally id. at 1500:13— 1501:20 (colloquy between Mr. Bowman and def.’s counsel). Similarly, in an effort to discredit the representations in plaintiff’s Inspection Reports of Dredging concerning the character of materials encountered by plaintiffs dredge, Mr. Bowman testified that “it [646] would not be obvious,” whether the material flowing through the dredge pipe consisted of sands, clay or other material. See Tr. at 1533:18-1534:12 (colloquy between Bowman and def.’s counsel). When confronted with his deposition testimony that “it was real obvious [to the person monitoring the discharge pipe] when we were in the good clays, and it was obvious when we were in the sands, and it was obvious when were in what you call the maintenance material, which was the silt and clay,” id. at 1535:2-5 (Def.’s counsel) (quoting JX 99A (Bowman Dep.) at 145:10-14), Mr. Bowman did not attempt to correct or explain his earlier statements.

Two of the major participants in the relevant events were not called as witnesses at trial. Plaintiffs did not call as a witness Eddie Fisher, its former Vice President. Defendant had taken the precaution of designating Mr. Fisher’s deposition as a trial exhibit. The court has found the deposition to be a useful resource with respect to plaintiffs preparation of its bid, an important aspect of a differing site condition claim. Defendant did not call as a witness Erik Russek, Project Engineer with the Corps. Plaintiff had not taken the precaution of designating Mr. Rus-sek’s deposition as a trial exhibit. Plaintiff argues that defendant’s failure to call Mr. Russek “warrants a negative inference.” PL’s Reply at 14. The proof of a differing site conditions claim, however, is focused on the actions of the plaintiff. The court does not see how the absence of a government witness could be deployed to assist plaintiff in carrying its burden of proof.

II. Applicable Legal Standards

A. Standard of Review

The “Disputes” clause in the Upper Bayou Contract, see generally JX 1 (Solicitation) at 91 (incorporating FAR § 52-233-1 (“Disputes”) (Oct.1995) as a standard clause), provides that disputes arising under the Contract are to be governed by the Contract Disputes Act of 1978(CDA), as amended, see generally 41 U.S.C. §§ 601-613 (2000). The CDA imposes two “jurisdictional prerequisites,” which must be met before a contractor may pursue a claim in this court. E.g., England v. The Swanson Group, Inc., 353 F.3d 1375, 1379 (Fed.Cir.2004); Bath Iron Works Corp. v. United States, 20 F.3d 1567, 1578-79 (Fed.Cir.1994); Sharman Co. v. United States, 2 F.3d 1564, 1568-69 (Fed.Cir.1993), overruled in part on other grounds by Reflectone, Inc. v. Dalton, 60 F.3d 1572 (Fed.Cir.1995). First, “[a]ll claims by a contractor against the government relating to a contract ... [must] be in writing and ... be submitted to the contracting officer for a decision.” 41 U.S.C. § 605(a). Second, “[t]he contracting officer [must] issue [a final] decision[ ] in writing, and ... furnish a copy of the decision to the contractor.”7 Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Renda Marine, Inc. v. United States, 66 Fed. Cl. 639, 2005 WL 1793421 (uscfc 2005).

66 Fed. Cl. 639 (Renda Marine, Inc. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Meltech Corporation, Inc.
Armed Services Board of Contract Appeals, 2024
Corinthian-WBCM, a Joint Venture
Armed Services Board of Contract Appeals, 2021
Zebel LLC v. United States
Federal Claims, 2017
King County v. Vinci Construction Grands Projets/Parsons RCI/Frontier-Kemper, JV
191 Wash. App. 142 (Court of Appeals of Washington, 2015)
Meridian Engineering Company v. United States
122 Fed. Cl. 381 (Federal Claims, 2015)
Zafer Taahhut Insaat Ve Ticaret, A.S. v. United States
120 Fed. Cl. 604 (Federal Claims, 2015)
Optimum Services, Inc.
Armed Services Board of Contract Appeals, 2015
Lee's Ford Dock, Inc.
Armed Services Board of Contract Appeals, 2014
United States v. Oscar Renda
709 F.3d 472 (Fifth Circuit, 2013)
United States v. Renda Marine, Inc.
667 F.3d 651 (Fifth Circuit, 2012)
United States v. Renda
821 F. Supp. 2d 853 (E.D. Texas, 2011)
United States v. Renda Marine, Inc.
750 F. Supp. 2d 755 (E.D. Texas, 2010)
Banks v. United States
84 Fed. Cl. 288 (Federal Claims, 2008)
Bell BCI Co. v. United States
81 Fed. Cl. 617 (Federal Claims, 2008)