Thorington Electrical and Construction Company

CourtArmed Services Board of Contract Appeals
DecidedFebruary 16, 2017
DocketASBCA No. 60476
StatusPublished

This text of Thorington Electrical and Construction Company (Thorington Electrical and Construction Company) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Thorington Electrical and Construction Company, (asbca 2017).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) Thorington Electrical and Construction Company ) ASBCA No. 604 76 ) Under Contract No. FA3300-05-C-0015 )

APPEARANCES FOR THE APPELLANT: Deitra Crawley, Esq. Natalie Mark, Esq. Taylor English Duma LLP Atlanta, GA

APPEARANCES FOR THE GOVERNMENT: Jeffrey P. Hildebrant, Esq. Air Force Deputy Chief Trial Attorney Lawrence M. Anderson, Esq. Trial Attorney

OPINION BY ADMINSTRATIVE JUDGE PROUTY ON THE GOVERNMENT'S MOTION FOR SUMMARY JUDGMENT

Before us is the government's motion for summary judgment, which argues that the claim appealed here by appellant, Thorington Electrical and Construction Company 1 (Thorington), is time-barred under the Contract Disputes Act of 1978 (CDA), 41 U.S.C. §§ 7101-7109. Thorington opposes the government's motion, arguing that its claim was timely because it is an amendment of an earlier claim of which the government was on notice. For the reasons stated herein, we conclude that the claim is time-barred under the CDA and enter judgment in favor of the government.

STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION

1. On 30 September 2005, the United States Air Force (government) awarded Contract No. FA3300-05-C-0015 (the contract) to Thorington for the construction of a new entry control facility at the Bell Street Gate at Maxwell Air Force Base, Alabama (R4, tab 1).

2. The construction of the facility was substantially completed by 11 August 2008, when the government determined that it was "fully operational" (compl. ~~ 32, 34).

1 Contract was awarded to "Thorington Electrical/Construction Company" but the claim and correspondence herein replaces the backslash (/) with "and." 3. On 28 April 2009, Thorington submitted a letter to the contracting officer (CO) seeking $764,813 in compensation from the government (R4, tab 48). The letter was labeled as a "claim" and was certified by Thorington's general manager and owner, Mr. Kelvin R. Thorington (id.). The letter provided that, "[t]he items that [Thorington] is making a claim [upon] are associated with work that was performed but was never paid and material cost for items increased since submitting the original cost estimate in 2005" (id. at 1). Thorington also stated, in relevant part:

In Addition, the claim does not include cost that TECC [Thorington] has acquired or projects that TECC could have obtained over the last six months. The delay in paying the modifications has caused TECC to lose several projects over the past year. As stated in several letters to the CO, the impact of nonpayment towards these modifications has caused delays in TECC paying our sub-contractors in a timely manner. This delay in payment has also caused the sub- contractors and venders [sic] to file claims against the surety company. If all modifications had been paid in a timely manner, TECC could have paid the sub-contractors and venders [sic] which would have eliminated any intervention by the surety company. Once the surety company pays any claims it is detrimental to your company's future ability to bond. The extended performance time occupied our bonding because the government delayed the project for approximately 1 Yi years and continues to occupy our bonding capabilities until the modifications are settled. These additional claims will be submitted through the legal system at a later date but with-in the next few months.

(Id. at 6)

4. By letter dated 14 August 2009, the CO issued a final decision partially granting and partially denying Thorington's claim dated 28 April 2009 (R4, tab 49).

5. Thorington appealed the CO's decision to this Board, and the appeal was docketed on 17 November 2009 as ASBCA Nos. 56987, 56988, 56989, 56990, 56991, 56992, 56993, 56994, 56995, 56996, 56998, 56999 and 57000. These appeals were all resolved when Thorington signed an agreement, dated 18 August 2015, which resolved all of its claims dated 28 April 2009 (gov't mot., attach. 1). The agreement

2 stated that "[t]he only claim that is not discharged is Contractor's 17 July 2015£21 claim for $20 million" (id. at 2). At the parties' request, the Board subsequently dismissed with prejudice ASBCA Nos. 56987, 56988, 56989, 56990, 56991, 56992, 56993, 56994, 56995, 56996, 56998, 56999 and 57000 on 26 August 2015.

6. The July 2015 "claim" excluded by the August 2015 settlement agreement, originated in a letter dated 16 July 2015, that Thorington submitted to the CO (R4, tab 52). This letter is titled "Amended Claim to the Claim Submitted on 28 April 2009," and seeks $20 million for the value of the loss of business, profit, and income; opportunity costs; damage to business relationships; and irreparable injury on the grounds that the CO's failure to issue timely change orders or to grant its claim destroyed its personal and business finances (id. at 2-3).

7. By letter dated 30 November 2015, the CO issued a final decision denying Thorington's claim dated 16 July 2015 (R4, tab 55). Thorington appealed to the Board on 26 February 2016, and reduced its amount in dispute to $3.75 million. We have docketed this appeal as the present case.

DISCUSSION

Thorington's 16 July 2015 claim was untimely because, as demonstrated by its 28 April 2009 claim letter, Thorington knew or should have known the basis for this claim by 28 April 2009 at the latest, meaning that it fell outside of the CDA's six-year statute of limitations. Thorington's assertion that the 2015 claim was merely an amendment to the 2009 claim, permissible under FED. R. CIV. P. 15(c) is misguided, to say the least. Rule 15(c ), governing the amendment of pleadings before federal courts, has no bearing upon the statute of limitations for filing a claim before a CO, and the statute of limitations may not be evaded by submitting a late "amendment" to a timely claim long since denied.

I. The Standards for Summary Judgment

The standards for summary judgment before the Board are well established3 and need little elaboration here. Summary judgment should be granted if it has been shown that there are no genuine issues of material fact and the moving party is entitled to judgment as a matter oflaw. Celotex Corp. v. Catrett, 477 U.S. 317, 322 (1986). A non-movant seeking to defeat summary judgment by suggesting conflicting facts

2 In the parties' settlement agreement, it states that the claim is dated 17 July 2015; however, the document in the record is dated 16 July 2015 (R4, tab 52). 3 Board Rule 7(c)(2) provides that the Board looks to FED. R. C1v. P. 56 for guidance in

deciding motions for summary judgment.

3 "must set forth specific facts showing that there is a genuine issue for trial." Anderson v. Liberty Lobby, Inc., 4 77 U.S. 242, 248 ( 1986) (quoting First National Bank ofArizona v. Cities Service Co., 391 U.S. 253, 288-89 (1968)). Put another way, ifthe non-moving party carries the burden of proof at trial for elements of its case and fails to provide such proof at the motion for summary judgment, the moving party is entitled to summary judgment. Dairyland Power Co-op v. United States, 16 F.3d 1197, 1202 (Fed. Cir. 1994). We do not resolve controversies, weigh evidence, or make determinations of credibility. Liberty Lobby, 477 U.S. at 255. All reasonable inferences are drawn in favor of the non-movant. Id.

II.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hornsby v. United States
77 U.S. 224 (Supreme Court, 1870)
First Nat. Bank of Ariz. v. Cities Service Co.
391 U.S. 253 (Supreme Court, 1968)
Pure Gold, Inc. v. Syntex (u.s.a.), Inc.
739 F.2d 624 (Federal Circuit, 1984)
Dairyland Power Cooperative v. United States
16 F.3d 1197 (Federal Circuit, 1994)
Renda Marine, Inc. v. United States
65 Fed. Cl. 152 (Federal Claims, 2005)
Design & Production, Inc. v. United States
33 Cont. Cas. Fed. 74,406 (Court of Claims, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
Thorington Electrical and Construction Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/thorington-electrical-and-construction-company-asbca-2017.