Unified Contractor, Inc. v. Albuquerque Housing Auth.

CourtNew Mexico Court of Appeals
DecidedApril 24, 2017
Docket34,826
StatusPublished

This text of Unified Contractor, Inc. v. Albuquerque Housing Auth. (Unified Contractor, Inc. v. Albuquerque Housing Auth.) is published on Counsel Stack Legal Research, covering New Mexico Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Unified Contractor, Inc. v. Albuquerque Housing Auth., (N.M. Ct. App. 2017).

Opinion

1 IN THE COURT OF APPEALS OF THE STATE OF NEW MEXICO

2 Opinion Number: __________

3 Filing Date: April 24, 2017

4 NO. 34,826

5 UNIFIED CONTRACTOR, INC.,

6 Plaintiff/Counterdefendant-Appellant,

7 v.

8 ALBUQUERQUE HOUSING 9 AUTHORITY, a political subdivision,

10 Defendant/Counterclaimant-Appellee.

11 APPEAL FROM THE DISTRICT COURT OF BERNALILLO COUNTY 12 Valerie A. Huling, District Judge

13 Calvert Menicucci, P.C. 14 Sean R. Calvert 15 Albuquerque, NM

16 for Appellant

17 City of Albuquerque 18 Jessica M. Hernandez, City Attorney 19 John E. DuBois, Assistant City Attorney 20 Kevin A. Morrow, Assistant City Attorney 21 Albuquerque, NM

22 for Appellee 1 OPINION

2 WECHSLER, Judge.

3 {1} This litigation and appeal result from a contractual dispute between Appellant

4 Unified Contractor, Inc. (Unified) and Appellee Albuquerque Housing Authority

5 (AHA). Unified appeals from the district court’s ruling that both parties breached the

6 contract (the Contract) between them and that both parties were liable for damages.

7 {2} In its letter decision, the district court made various factual findings and legal

8 conclusions. It also instructed the parties to submit requested findings of fact and

9 conclusions of law within fourteen days. Neither party timely submitted findings of

10 fact and conclusions of law.

11 {3} Unified characterizes several of its appellate arguments as either questions of

12 law or mixed questions of law and fact. As discussed in detail below, to the extent

13 that Unified’s appellate arguments simply re-purpose questions of fact as questions

14 of law, they are not well-taken.

15 {4} Unified does, however, raise legal arguments related to (1) its entitlement to

16 notice of deficient performance and the opportunity to cure such deficient

17 performance (notice and opportunity to cure) under the Contract and general

18 principles of contract law, (2) the district court’s decision to allow AHA to raise

19 grounds for termination of the Contract other than those articulated as the basis for 1 termination prior to trial, (3) the district court’s method of calculating damages, and

2 (4) the district court’s refusal to consider Unified’s motion for reconsideration. With

3 the exception of Unified’s argument as to the district court’s method of calculating

4 damages, these arguments lack merit. As to the calculation of damages, we adopt and

5 apply the “contract price limitation rule” to the facts of this case; a decision requiring

6 that we reverse the district court’s judgment in favor of AHA in the amount of

7 $33,281.37 and remand to the district court for entry of a final judgment in favor of

8 AHA in the reduced amount of $22,257.34.

9 {5} Finally, Unified argues that it is entitled to statutory interest pursuant to the

10 Prompt Payment Act. NMSA 1978, §§ 57-28-1 to -11 (2001, as amended through

11 2007). For the reasons discussed herein, we disagree. We therefore affirm in part,

12 reverse in part, and remand to the district court for entry of a final judgment

13 consistent with this opinion.

14 BACKGROUND

15 The Contract

16 {6} Unified submitted a bid in response to AHA’s invitation for bids number

17 B13001 (IFB B13001). IFB B13001 called for various construction services at four

18 residential properties owned by AHA. The physical addresses of the properties in

2 1 Albuquerque are 514 Morris NE, 716 Morris NE, 903 Nakomis NE, and 2905

2 Chelwood NE.

3 {7} Section 2.0 of IFB B13001 outlined the scope of work and technical

4 specifications for the project. Subsection 2.3 provided that bidders could propose to

5 substitute for products specified in IFB B13001 so long as the substitute product was

6 “substantially equivalent or exceeding to the product[] identified.” Subsection 2.4.1.5

7 required the bidder to “[p]aint [the] entire exterior of [each] building with one coat

8 of [a]crylic base primer and one coat of elastomeric coating.” Subsection 2.4.6.1.2.8

9 defined elastomeric coating by reference to “El Rey elastomeric coating, or equal[.]”

10 IFB B13001 did not define a “coat” of elastomeric coating.

11 {8} AHA accepted Unified’s bid, and the parties entered the Contract on July 15,

12 2013. The Contract expressly incorporated Form HUD-5370 (11/2006), which

13 outlines general conditions for the termination of a construction contract due to

14 default by the contractor or for the convenience of the agency. The Contract also

15 contained various clauses related to billing and payment, including (1) a prompt

16 payment clause, which required payment for “properly completed invoice[s]” within

17 thirty days, and (2) a disputed billings clause, which required AHA to pay any

18 undisputed portions of billings and to formally notify Unified of any disputed billings

19 within ten days of receipt.

3 1 {9} On August 8, 2013, Unified submitted an elastomeric coating manufactured by

2 UltraKote Products, Inc. for use in the project. AHA did not approve this product for

3 use. On September 3, 2013, Unified submitted an elastomeric coating manufactured

4 by ParexUSA for use in the project. Although disputes as to which product AHA

5 approved continued throughout the litigation, the record shows that AHA approved

6 ParexUSA elastomeric coating for use on the project on September 9, 2013.1

7 ParexUSA elastomeric coating can be applied in one or two coats by spray, brush, or

8 roller over porous or smooth surfaces. The stucco surfaces at issue in this case were

9 porous. Using the “one coat” method, each pail of ParexUSA elastomeric coating

10 would cover 125-180 square feet of a porous surface. Using the “two coat” method,

11 each pail of ParexUSA elastomeric coating would cover 250-375 square feet of a

12 porous surface.

13 The Project

14 {10} In September 2013, Unified began work at 716 Morris NE and 903 Nakomis

15 NE. The contract price for these properties was $278,349. Unified submitted its first

1 16 Significant confusion exists as to whether El Rey elastomeric coating and 17 ParexUSA elastomeric coating are identical products. We refer to ParexUSA 18 elastomeric coating throughout this opinion because it is the product approved by 19 AHA for use on the project and purchased by Unified. Whether AHA intended to 20 approve ParexUSA elastomeric coating for use on the project is unclear but 21 immaterial to this opinion.

4 1 itemized invoices for work at these locations on September 24, 2013. Attachments to

2 these invoices indicate that Unified had not yet patched stucco or applied elastomeric

3 coating at either location. AHA paid these invoices in full.

4 {11} On October 16, 2013, AHA’s site inspections revealed deficiencies in the

5 appearance of the finished walls at 716 Morris NE and 903 Nakomis NE. AHA sent

6 numerous emails and a letter between October 16, 2013 and November 13, 2013

7 requesting confirmation that the approved elastomeric coating was being installed in

8 accordance with the manufacturer’s recommendations. Unified repeatedly responded

9 in the affirmative.

10 {12} On October 24, 2013, Unified submitted a second set of itemized invoices for

11 work at 716 Morris NE and 903 Nakomis NE. Attachments to these invoices indicate

12 that Unified had completed eighty-eight percent of stucco patching and elastomeric

13 coating application at each location.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

College Point Boat Corp. v. United States
267 U.S. 12 (Supreme Court, 1925)
Servants of the Paraclete v. Does
204 F.3d 1005 (Tenth Circuit, 2000)
Rivera v. American General Financial Services, Inc.
2011 NMSC 033 (New Mexico Supreme Court, 2011)
Eker Bros. Inc. v. Rehders
2011 NMCA 092 (New Mexico Court of Appeals, 2011)
Duran v. Montoya
242 P.2d 492 (New Mexico Supreme Court, 1952)
City of Santa Fe v. Komis
845 P.2d 753 (New Mexico Supreme Court, 1992)
Blea v. Sandoval
761 P.2d 432 (New Mexico Court of Appeals, 1988)
Cockrell v. Cockrell
871 P.2d 977 (New Mexico Supreme Court, 1994)
Blaine Economic Development Authority v. Royal Electric Co.
520 N.W.2d 473 (Court of Appeals of Minnesota, 1994)
Castricone v. Michaud
583 N.E.2d 1184 (Appellate Court of Illinois, 1991)
Public Service Co. v. Diamond D Construction Co.
2001 NMCA 082 (New Mexico Court of Appeals, 2001)
People v. Covington
19 P.3d 15 (Supreme Court of Colorado, 2001)
Paiz v. State Farm Fire & Casualty Co.
880 P.2d 300 (New Mexico Supreme Court, 1994)
Deaton v. Gutierrez
2004 NMCA 043 (New Mexico Court of Appeals, 2003)
Cerrillos Gravel Products, Inc. v. Board of County Commissioners
2005 NMSC 023 (New Mexico Supreme Court, 2005)
Collado v. City of Albuquerque
2002 NMCA 048 (New Mexico Court of Appeals, 2002)
Giuffre Hyundai, Ltd. v. Hyundai Motor America
756 F.3d 204 (Second Circuit, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
Unified Contractor, Inc. v. Albuquerque Housing Auth., Counsel Stack Legal Research, https://law.counselstack.com/opinion/unified-contractor-inc-v-albuquerque-housing-auth-nmctapp-2017.