Eker Bros. Inc. v. Rehders

2011 NMCA 092, 263 P.3d 319, 150 N.M. 542
CourtNew Mexico Court of Appeals
DecidedAugust 2, 2011
Docket29,839
StatusPublished
Cited by11 cases

This text of 2011 NMCA 092 (Eker Bros. Inc. v. Rehders) is published on Counsel Stack Legal Research, covering New Mexico Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Eker Bros. Inc. v. Rehders, 2011 NMCA 092, 263 P.3d 319, 150 N.M. 542 (N.M. Ct. App. 2011).

Opinion

OPINION

BUSTAMANTE, Judge.

{1} Eker Brothers, Inc. (Subcontractor) sued John G. Rehders, General Contractor, Inc. (General) seeking payment for work Subcontractor had performed. The district court found that Subcontractor was owed $74,964.05 and that General had incurred $42,448.20 in damages, but that Subcontractor’s “claims [were] barred by its willful, material^] and anticipatory breach of the parties’ contract.” The court awarded General $42,448.29. 1 We conclude that the district court erred by not offsetting General’s damages against the benefit General received from Subcontractor’s unpaid work, and reverse.

I. BACKGROUND

{2} Subcontractor submitted a bid to General to perform site and concrete work necessary to construct an elementary school for the Archdiocese of Santa Fe. After Subcontractor agreed to reduce the site work bid by $100,000, General verbally accepted the bid and work began on the project. General paid Subcontractor’s first invoice, covering work from July 1 to July 31, in full. Subcontractor continued work through August, and on September 2, Subcontractor tendered an invoice for $126,358.95 covering work performed between August 1 and August 31.

{3} On September 8, Subcontractor ceased all work on the project. Four days later, on September 12, General offered to pay $58,947.95 for the work Subcontractor had performed. Subcontractor did not accept this payment. On September 14, Subcontractor submitted an invoice for the work it had performed from August 1 to September 7 in the amount of $122,099.45. General did not pay this invoice and this lawsuit followed.

{4} The district court concluded that the value of the work performed by Subcontractor between August 1 and September 7 and invoiced on September 14 was $74,964.05. To arrive at this number, the court began with the $122,099.45 from Subcontractor’s September 14 invoice. The court then subtracted (1) $28,900 for grading work that had not actually been performed; (2) $7656 for curbs that were of poor quality; (3) $3,036.90 to cover General’s cost to remove the defective curbs; (4) $5,512.50 for General’s cost to re-stake an area that had been impacted by Subcontractor’s departure; and (5) $2030 to cover half of the cost of fixing footings that had been damaged due to rain.

{5} The district court next turned to General’s damages. It found that General had “incurred [an extra] $50,194.45 in additional expenses due to [Subcontractor’s] failure to complete the concrete work.” It also found that General had mitigated its damages by completing the site work for $7,746.25 less than it would have paid Subcontractor. Subtracting the savings from the additional costs, the district court concluded that General’s damages were $42,448.20. The district court did not offset the amount owed to Subcontractor against the damages, but instead entered judgment against Subcontractor for the full amount of the damages.

II. DISCUSSION

{6} Subcontractor contends that the district court’s decision that his claims were “barred by its willful, materialf,] and anticipatory breach” was error as a matter of law, and that “[d]espite its breach, [it] was entitled to restitution for the value of the benefits its performance conferred.” Subcontractor argues that New Mexico follows Restatement (Second) of Contracts § 374 (1981), which allows a breaching party to obtain restitution for benefits conferred in excess of damages. As we understand it, General’s response is that the $74,964.05 of unpaid work performed by Subcontractor did not constitute a benefit to General and therefore should not be offset against General’s damages. General also argues that its damages exceeded any benefit. Subcontractor has also made a substantial evidence argument, which we do not address because we agree with Subcontractor’s legal argument.

A. The Nature of Restitution

{7} Both parties have framed the issue of whether restitution must be awarded here as if it were equitable in nature, deriving from unjust enrichment. The district court denied Subcontractor’s request for equitable relief in the form of restitution for unjust enrichment. That does not, however, end our analysis. To the extent that the requested restitution refers to an offset of compensatory damages by the amount of any benefit conferred, it is a legal issue which we review de novo. See Primetime Hospitality, Inc. v. City of Albuquerque, 2009-NMSC-011, ¶ 10, 146 N.M. 1, 206 P.3d 112. As an initial matter, we must determine whether the damages question at issue here is legal or equitable in order to select the appropriate standard of review.

{8} Traditionally, restitution is thought of as an equitable remedy. See, e.g., Arena Res., Inc. v. OBO, Inc., 2010-NMCA-061, ¶ 15, 148 N.M. 483, 238 P.3d 357. However, in the context of offsetting compensatory damages, at least one court has found that restitution is a legal remedy. See Ducolon Meek, Inc. v. Shinstine/Fomess, Inc., 77 Wash.App. 707, 893 P.2d 1127, 1129 (1995). A popular treatise notes that “[t]he remedy of restitution, ... [cannot] properly be described as either ‘legal’ or ‘equitable’ in any narrowly restricted signification of those terms.” 12 Arthur Linton Corbin, Corbin on Contracts § 1103, at 10 (interim ed.2002). Our Supreme Court has also noted the dual nature of restitution. See C.R. Anthony Co. v. Loretto Mall Partners, 112 N.M. 504, 512 n. 10, 817 P.2d 238, 246 n. 10 (1991). As Corbin observes, modern restitution is a mixture whose rules “are the rules of equity wherever they differ from those of the common law.” See Corbin on Contracts, supra, § 1103, at 5 (emphasis added).

{9} Nevertheless, equity may still intervene, as it apparently did here. See Builders Contract Interiors, Inc. v. Hi-Lo Indus., Inc., 2006-NMCA-053, ¶8, 139 N.M. 508, 134 P.3d 795. The district court ruled that Subcontractor was barred from recovering, effectively working a forfeiture on Subcontractor for the value of its work from August 1 to September 7. Our Supreme Court has observed that “a forfeiture declaration is essentially an equitable remedy.” Cortez v. Cortez, 2009-NMSC-008, ¶25, 145 N.M. 642, 203 P.3d 857 (alteration omitted) (internal quotation marks omitted). “The question of whether, on a particular set of facts, the district court is permitted to exercise its equitable powers is a question of law, while the issue of how the district court uses its equitable powers to provide an appropriate remedy is reviewed only for abuse of discretion.” United Props. Ltd. v. Walgreen Props., Inc., 2003-NMCA-140, ¶ 7, 134 N.M. 725, 82 P.3d 535.

B. Our Case Law About Compensatory Damages and Restitution

{10} We begin our discussion with the question of damages. As we have noted, this is a legal question, and will determine the outcome unless equity intervenes. Subcontractor contends that in Famiglietta v. Ivie-Miller Enters., Inc., 1998-NMCA-155, 126 N.M.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gonzagowski v. Steamatic of Albuquerque, Inc.
New Mexico Supreme Court, 2023
Gonzagowski v. Steamatic of Albuquerque
New Mexico Supreme Court, 2023
Cent. Mkt, Ltd. v. Multi-Concept Hosp., LLC
New Mexico Court of Appeals, 2022
Abraham v. WPX Energy Production, LLC
20 F. Supp. 3d 1244 (D. New Mexico, 2014)
Wagner v. Galbreth
500 B.R. 42 (D. New Mexico, 2013)
Wagner v. Pruett (In re Vaughan Co., Realtors)
477 B.R. 206 (D. New Mexico, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
2011 NMCA 092, 263 P.3d 319, 150 N.M. 542, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eker-bros-inc-v-rehders-nmctapp-2011.