This text of 2009 NMSC 011 (Primetime Hospitality, Inc. v. City of Albuquerque) is published on Counsel Stack Legal Research, covering New Mexico Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Primetime Hospitality, Inc. v. City of Albuquerque, 2009 NMSC 011, 206 P.3d 112, 146 N.M. 1 (N.M. 2009).

Opinion

OPINION

CHAVEZ, Chief Justice.

{1} Primetime Hospitality, Inc. (Prime-time) had begun constructing a hotel on its Albuquerque property when it accidentally ruptured an encroaching City of Albuquerque (the City) waterline, causing it to incur excess construction costs and delaying the hotel’s opening. The City stipulated to liability for inverse condemnation, admitting that it deprived Primetime of all use and enjoyment of its property for the duration of the taking. As the issue of liability is not before us, the only question we must address is whether Primetime’s lost profits and excess construction costs may be awarded as damages in inverse condemnation proceedings. The district court found Primetime’s losses to be the direct result of the City’s taking and awarded it damages, along with expert witness costs. The Court of Appeals reversed, holding that although lost profits might be considered, the direct award of lost profits in this case would constitute the impermissible award of the full measure of tort damages, and that the portion of the excess construction costs covering Primetime’s damage-mitigating buttress wall must be subject to a test of reasonableness. Primetime Hospitality, Inc. v. City of Albuquerque, 2007-NMCA-129, ¶¶ 23-26, 35, 40, 142 N.M. 663, 168 P.3d 1087. The Court of Appeals also vacated the award of expert costs. Id. ¶¶ 23, 24. We granted certiorari to consider these issues.

{2} We hold that in an inverse condemnation proceeding, lost profits may be recovered when they are the best measure of the value of the lost use and enjoyment of condemned land. In addition, in such proceedings, excess construction costs directly resulting from a temporary taking are awardable. Accordingly, we reverse the Court of Appeals and reinstate the district court’s award of damages and costs.

I. BACKGROUND

{3} The facts in this case are not in dispute. Primetime is a New Mexico corporation that develops hotels. It owned land in Albuquerque and had taken significant steps toward building a hotel on its land. Prior to construction, Primetime entered into a license agreement with Hilton Inns that obligated Primetime to construct a Hilton Garden Inn or face $385,000 in liquidated damages. In preparation for construction, Primetime hired an architect to draw up plans and employed a general contractor at a cost of $130,000 each. To finance the hotel’s construction, Primetime took out a construction loan of $4,435,000.

{4} Not long after construction began in the spring of 2001, Primetime’s contractor accidentally breached a 24-inch city waterline, flooding the property. Shortly thereafter, Primetime discovered a 12-ineh waterline on the property as well. The City subsequently removed both waterlines and Primetime sued, seeking damages under New Mexico’s inverse condemnation statute, NMSA 1978, § 42A-1-29 (1983), or, in the alternative, for trespass.

{5} Before trial, the City stipulated to liability for inverse condemnation and Prime-time did not oppose the City’s motion to dismiss its trespass claim. The district court then granted partial summary judgment regarding disputed elements of damages, ruling that lost profits “are a proper element of damages with respect to [Primetime’s] claims for inverse condemnation in the amount to be determined at trial.” At trial, over the City’s continuing objection, Primetime and the City presented conflicting expert testimony on the proper measure of lost profits, with the City arguing for a before-and-after method of calculation and Primetime favoring a measure that would compensate it based on calculations of the profits it would have earned had the hotel opened as scheduled.

{6} At the conclusion of trial, the district court made several findings of fact that are not challenged on appeal. It found that construction was delayed 142 days, that the amount of lost profits due to the delay was $456,242, and that Primetime also incurred additional construction costs in the amount of $153,518.45 due to the delay. The additional construction costs included the costs of repairing water damage, the costs of the delayed construction, and the costs of constructing a buttress wall that had not been in the original design. Addressing the issue of lost profits, the district court concluded that “[w]hen reliable proof of damage and its amount is presented by a methodology other than a before and after appraisal, such proof is admissible on the damage issue,” and found that evidence of lost profits was “reasonably ascertainable” with Primetime’s methodology. Pursuant to its findings, the district court awarded damages for the additional construction costs and lost profits, and awarded the costs of Primetime’s experts.

{7} The City appealed the district court’s decision, claiming that the court erred in awarding lost profits, excess construction costs, and expert fees because such damages are consequential, and thus not recoverable in an inverse condemnation action. Prime-time, 2007-NMCA-129, ¶ 1, 142 N.M. 663, 168 P.3d 1087. The Court of Appeals affirmed in part and reversed in part. Id. Discussing the award of damages for excess construction costs, the Court of Appeals held that generally speaking, repair and restoration expenses should be allowed, to put “the landowner in the same pecuniary position as though the taking had not occurred.” Id. ¶23. Specifically, regarding the buttress wall, the Court of Appeals held that since the wall was an effort to mitigate damages, it was “not strictly required by the City’s taking,” id. ¶24, and the district court should have applied a test of “reasonableness under the circumstances” to decide whether it was compensable, id. ¶ 26. The Court explained that in condemnation cases, unlike contract or tort actions, mitigation expenses are not per se recoverable, id. ¶ 25, but they should not be denied completely, which would undermine a landowner’s incentive to reduce losses, id. ¶ 26. Thus, the Court of Appeals remanded to the district court to determine reasonableness, perhaps by comparing “the cost of the mitigation effort to the value of the harm averted,” taking caution to avoid double recovery. Id. ¶¶ 26, 27.

{8} Next, the Court of Appeals considered the award of lost profits, observing that no single measure of damages could apply in all temporary takings cases. Id. ¶ 22. However, finding guidance in federal cases, it held that rental value would be an appropriate measure in this ease. Id. ¶¶ 37, 38. In defining rental value, the Court of Appeals held that the ultimate question must be “[w]hat would an objective property owner accept to delay construction of a hotel facility in this circumstance for a period of 142 days?” Id. ¶41. Under this standard, the Court held that lost profits should not be directly allowed, but might be considered as a component of rental value. Id. ¶¶ 39^10. As a result, the Court remanded the case to the district court to apply this measure, leaving “the details of the calculation to the parties’ accounting and economics experts.” Id. ¶ 41.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kiehne v. N.M. Dep't of Game & Fish
New Mexico Court of Appeals, 2026
State v. City of Rio Rancho
New Mexico Court of Appeals, 2025
State v. Powell
New Mexico Supreme Court, 2024
CBS MN Properties, LLC v. County of Hennepin
Court of Appeals of Minnesota, 2024
City of Albuquerque v. Tecolote Res.
New Mexico Court of Appeals, 2023
Stanley v. N.M. Game Comm'n
New Mexico Court of Appeals, 2023
Stanley v. N.M. Game Commission
New Mexico Court of Appeals, 2023
Wittman v. City of Billings
2022 MT 129 (Montana Supreme Court, 2022)
Morga v. FedEx Ground Package Sys., Inc.
New Mexico Supreme Court, 2022
State v. Wilson
2021 NMSC 022 (New Mexico Supreme Court, 2021)
City of Albuquerque v. SMP Props., LLC
2021 NMSC 011 (New Mexico Supreme Court, 2021)
City of Albuquerque v. SMP Properties
2019 NMCA 4 (New Mexico Court of Appeals, 2018)
City of Albuquerque v. SMP Props., LLC
433 P.3d 336 (New Mexico Court of Appeals, 2018)
State v. Ortiz
New Mexico Court of Appeals, 2017
State v. Steven B.
2015 NMSC 020 (New Mexico Supreme Court, 2015)
State v. Seda
New Mexico Court of Appeals, 2014
Moongate Water Co., Inc. v. City of Las Cruces
2013 NMSC 18 (New Mexico Supreme Court, 2013)
Janet v. Marshall
2013 NMCA 037 (New Mexico Court of Appeals, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
2009 NMSC 011, 206 P.3d 112, 146 N.M. 1, Counsel Stack Legal Research, https://law.counselstack.com/opinion/primetime-hospitality-inc-v-city-of-albuquerque-nm-2009.