Gonzagowski v. Steamatic of Albuquerque

CourtNew Mexico Supreme Court
DecidedJune 22, 2023
DocketS-1-SC-38872
StatusPublished

This text of Gonzagowski v. Steamatic of Albuquerque (Gonzagowski v. Steamatic of Albuquerque) is published on Counsel Stack Legal Research, covering New Mexico Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gonzagowski v. Steamatic of Albuquerque, (N.M. 2023).

Opinion

Office of the Director 10:10:05 2023.08.23 New Mexico Compilation '00'06- Commission 2020.005.30514 IN THE SUPREME COURT OF THE STATE OF NEW MEXICO

Opinion Number: 2023-NMSC-016

Filing Date: June 22, 2023

No. S-1-SC-38872

RICHARD JAMES GONZAGOWSKI,

Plaintiff-Petitioner/Cross-Respondent,

v.

STEAMATIC OF ALBUQUERQUE, INC., d/b/a STEAMATIC OF ALBUQUERQUE & SANTA FE, INC., and GEB, INC.,

Defendants-Respondents/Cross-Petitioners,

and

ALLSTATE INDEMNITY COMPANY and GERARD BECKER,

Defendants.

ORIGINAL PROCEEDING ON CERTIORARI Clay Campbell, District Judge

Santillanes & Neidhhardt, P.C. Janet Santillanes Olivia Neidhardt James T. Roach Albuquerque, NM

The Roehl Law Firm P.C. Jerrald J. Roehl Katherine C. Roehl Albuquerque, NM

for Petitioner/Cross-Respondent

Sutin Thayer & Browne, P.C. Mariposa Padilla Sivage Albuquerque, NM BatesCarey LLP Agelo L. Reppas Chicago, IL

for Respondents/Cross-Petitioners

OPINION

VIGIL, Justice.

{1} New Mexico does not permit a civil plaintiff to recover duplicate compensatory damages for the same injuries. Hood v. Fulkerson, 1985-NMSC-048, ¶ 12, 102 N.M. 677, 699 P.2d 608. The collateral source rule presents an exception to the prohibition of double recovery, permitting a plaintiff to recover the same damages from both a defendant and a collateral source. Sunnyland Farms, Inc. v. Cent. N.M. Elec. Coop., Inc., 2013-NMSC-017, ¶ 48, 301 P.3d 387. We have held that the payor of the prejudgment settlement of a claim qualifies as a collateral source and that the payment does not reduce the same damages the plaintiff may recover from an adjudicated wrongdoer. McConal Aviation, Inc. v. Com. Aviation Ins. Co., 1990-NMSC-093, ¶¶ 15, 17, 110 N.M. 697, 799 P.2d 133; Sanchez v. Clayton, 1994-NMSC-064, ¶ 10, 117 N.M. 761, 877 P.2d 567. The current proceedings invite us to consider whether a payment in postjudgment settlement of a claim by an adjudicated wrongdoer qualifies as a collateral source.

{2} Although our precedent has already limited the collateral source rule to prejudgment settlements, see Sanchez, 1994-NMSC-064, ¶ 10, we clarify that the collateral source rule has no application to a postjudgment payment made by an adjudicated wrongdoer. We hold that the payment, which Plaintiff Richard Gonzagowski received in a postjudgment settlement with one defendant, Allstate Indemnity Company (Allstate), satisfied a portion of Plaintiff’s damages and extinguishes Plaintiff’s right to recover the same damages from a second defendant, GEB, Inc., d/b/a Steamatic of Albuquerque and Santa Fe, Inc. (Steamatic). Applying our opinion in Sanchez, 1994- NMSC-064, we also explain that the share of damages fully satisfied by Allstate must offset the damages Plaintiff may recover from Steamatic. We affirm, in part, and reverse, in part, the opinion of the Court of Appeals in Gonzagowski v. Steamatic of Albuquerque, Inc., 2021-NMCA-056, 497 P.3d 1202. We remand to the district court for further proceedings consistent with our opinion.

I. BACKGROUND

{3} After Plaintiff’s home sustained water damage in a hailstorm, he asked his insurer Allstate to cover the loss; consequently, Steamatic was hired to perform water abatement and mold remediation services. Plaintiff claimed that the mold was not remediated properly and that he developed a severe and permanent lung condition as a result. {4} Plaintiff filed suit against Allstate and Steamatic for his personal injuries. Plaintiff’s claim against Allstate was for breach of contract on the basis that his injuries were a consequence of Allstate’s failure to adhere to the mold remediation provisions in his homeowner’s insurance policy. Plaintiff asserted claims against Steamatic for breach of contract and negligence, asserting that the company failed to properly repair and remediate the mold in his home. Plaintiff abandoned his breach of contract claim against Steamatic before trial. Thus, Plaintiff’s claim against Allstate was for breach of contract and his claim against Steamatic was for negligence. Although Plaintiff asserted different theories of liability against each defendant, Plaintiff sought the same compensatory damages from both Allstate and Steamatic.

{5} During the jury instructions conference, the three parties and the district court discussed potential issues arising from Plaintiff’s attempt to recover the same damages from both defendants. With input from the parties, the district court set out to craft a special verdict form that would permit the jury to allocate responsibility for damages as between the parties.

{6} The special verdict form began by asking the jury to answer a series of interrogatories on the substantive elements of the parties’ claims and defenses. As relevant to the current appeal, the jury found that Steamatic was an independent contractor, that Allstate breached its contract, and that Steamatic was negligent. Allstate’s breach and Steamatic’s negligence were also found to have caused Plaintiff’s injuries.

{7} The jury determined that Plaintiff had failed to mitigate his damages with respect to Allstate’s breach and Steamatic’s negligence. Two interrogatories on the special verdict form asked the jury to compare each defendant’s conduct to Plaintiff’s failure to mitigate “and find a percentage that each party’s conduct contributed to [Plaintiff’s] damages.” In response to Question No. 5, the jury found that Allstate’s conduct contributed 60% and that Plaintiff’s failure to mitigate contributed 40%. In response to Question No. 9, the jury found that Steamatic’s negligence contributed 80% and Plaintiff’s failure to mitigate contributed 20%.

{8} The jury was asked to identify Plaintiff’s “total compensatory damages.” The jury set the amount of Plaintiff’s compensatory damages at $2.5 million. Question No. 12 asked the jury to “[i]dentify the total percentage of compensatory damages caused by each of” the three parties. The jury answered that, of Plaintiff’s total compensatory damages, Allstate caused 30%, Steamatic caused 55%, and Plaintiff caused 15%.

{9} After trial, the parties disagreed about the proper allocation of damages in light of the jury’s findings. Plaintiff argued that the jury’s verdict was inconsistent with the jury findings, that Questions No. 5 and 9 reflected the proper allocation of damages as to each defendant, and that Question No. 12 was “surplusage.” The defendants argued that the jury’s verdict was consistent, in that the jury allocated responsibility for causing Plaintiff’s injuries (Question No. 12), and also found that Plaintiff failed to mitigate his damages as to each defendant (Questions No. 5 and 9). {10} The district court resolved this dispute by concluding that Question No. 12 expressed the jury’s findings on the allocation of damages. Thus, the district court found that Plaintiff suffered $2.5 million in total compensatory damages, of which Allstate caused 30%, Steamatic caused 55%, and Plaintiff caused 15%. The district court entered final judgment accordingly, adjudicating Allstate liable for $0.75 million and Steamatic liable for $1.375 million.

{11} Following entry of the final judgment, Allstate settled with Plaintiff and secured full satisfaction and release from the judgment. The record does not reflect the amount of Allstate’s postjudgment payment to Plaintiff. But, significantly, no party appealed or sought to amend the final judgment against Allstate, and no party disputes Allstate’s full satisfaction of the judgment.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Eker Bros. Inc. v. Rehders
2011 NMCA 092 (New Mexico Court of Appeals, 2011)
Hood v. Fulkerson
699 P.2d 608 (New Mexico Supreme Court, 1985)
Vaca v. Whitaker
1974 NMCA 011 (New Mexico Court of Appeals, 1974)
Central SEC. and Alarm Co., Inc. v. Mehler
918 P.2d 1340 (New Mexico Court of Appeals, 1996)
Trujillo v. Chavez
417 P.2d 893 (New Mexico Supreme Court, 1966)
Fortuna Corp. v. Sierra Blanca Sales Co., Inc.
548 P.2d 865 (New Mexico Supreme Court, 1976)
Smith v. FDC Corp.
787 P.2d 433 (New Mexico Supreme Court, 1990)
Rose v. Hakim
335 F. Supp. 1221 (District of Columbia, 1971)
Hale v. Basin Motor Co.
795 P.2d 1006 (New Mexico Supreme Court, 1990)
McConal Aviation, Inc. v. Commercial Aviation Insurance
799 P.2d 133 (New Mexico Supreme Court, 1990)
Sanchez v. Clayton
877 P.2d 567 (New Mexico Supreme Court, 1994)
Payne v. Hall
2006 NMSC 029 (New Mexico Supreme Court, 2006)
Safeway, Inc. v. Rooter 2000 Plumbing & Drain SSS
2016 NMSC 9 (New Mexico Supreme Court, 2016)
State v. Fernandez Co.
28 N.M. 425 (New Mexico Supreme Court, 1923)
Sanchez v. Clayton
877 P.2d 567 (New Mexico Supreme Court, 1994)
Summit Properties, Inc. v. Public Service Co.
2005 NMCA 090 (New Mexico Court of Appeals, 2005)
Gonzagowski v. Steamatic of Albuquerque, Inc.
2021 NMCA 056 (New Mexico Court of Appeals, 2021)

Cite This Page — Counsel Stack

Bluebook (online)
Gonzagowski v. Steamatic of Albuquerque, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gonzagowski-v-steamatic-of-albuquerque-nm-2023.