Cuba Soil & Water Conservation Dist. v. Granite RE, Inc.

CourtNew Mexico Court of Appeals
DecidedFebruary 1, 2023
DocketA-1-CA-39129
StatusUnpublished

This text of Cuba Soil & Water Conservation Dist. v. Granite RE, Inc. (Cuba Soil & Water Conservation Dist. v. Granite RE, Inc.) is published on Counsel Stack Legal Research, covering New Mexico Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cuba Soil & Water Conservation Dist. v. Granite RE, Inc., (N.M. Ct. App. 2023).

Opinion

This decision of the New Mexico Court of Appeals was not selected for publication in the New Mexico Appellate Reports. Refer to Rule 12-405 NMRA for restrictions on the citation of unpublished decisions. Electronic decisions may contain computer- generated errors or other deviations from the official version filed by the Court of Appeals.

IN THE COURT OF APPEALS OF THE STATE OF NEW MEXICO

No. A-1-CA-39129

CUBA SOIL AND WATER CONSERVATION DISTRICT,

Plaintiff/Counterdefendant-Appellee,

v.

GRANITE RE, INC., as bond holder for VIGIL CONTRACTING SERVICES, INC.; and VIGIL CONTRACT SERVICES, INC.,

Defendants/Counterclaimants-Appellants.

APPEAL FROM THE DISTRICT COURT OF SANDOVAL COUNTY James A. Noel, District Court Judge

TMP Legal, LLC Timothy M. Padilla Albuquerque, NM

for Appellee

Calvert – Menicucci, P.C. Sean R. Calvert Albuquerque, NM

for Appellants

MEMORANDUM OPINION

BOGARDUS, Judge.

{1} Defendants Vigil Contracting Services, Inc. (Vigil) and Granite RE, Inc. (Granite) appeal the district court’s judgment awarding damages to Plaintiff Cuba Soil and Water Conservation District based on Vigil’s breach of a construction contract. Defendants argue the district court erred by (1) holding Vigil liable for the cost of correcting deficient work and relying on certain expert testimony to calculate the cost of correcting the work; and (2) holding Granite liable for its obligations, as surety, under a performance bond. We affirm.

BACKROUND

{2} This case arises from a construction dispute. In October 2011, Plaintiff contracted with Vigil, a contractor, to erect an office building and make site improvements for Plaintiff for $875,386.77. The construction contract required Vigil to obtain a performance bond (the bond), which Vigil purchased from Granite.

{3} Construction proceeded, and, after receiving a certificate of occupancy from the State, Plaintiff moved into the building in October 2012. In the meantime, the project’s architect had created a “punch list” of items that needed correction and had concerns related to site compaction and final gradations at the site. These concerns were unresolved as of September 2012, and the architect never issued a final certificate for payment because work remained to be done. Plaintiff refused Vigil’s final application for payment because of multiple deficiencies in Vigil’s work, and in November 2013, Plaintiff demanded that Granite perform its obligation under the bond.

{4} Plaintiff sued Vigil and Granite, claiming that Vigil breached the Construction Contract1 and owed payment for nonconforming work, and that Granite failed to fulfill its payment obligations under the bond. The district court determined that Vigil had substantially completed the work as defined in the Construction Contract in July 2012 and was entitled to its final payment. The district court also determined that Vigil had breached the Construction Contract and failed to substantially perform all its obligations, and awarded Plaintiff $169,500 to correct site work, concrete, and asphalt deficiencies. Finally, the district court determined that Plaintiff notified Granite as required by the bond and entered judgment “against Vigil and Granite.” Defendants appeal.

DISCUSSION

I. Vigil’s Liability

A. The District Court Did Not Err in Determining That Vigil Was Liable for the Cost of Correcting Deficient Work

{5} The district court determined that Vigil was entitled to its final payment under the Construction Contract but that Plaintiff was entitled to recover damages based on the cost to correct deficiencies in Vigil’s work. Defendants acknowledge that Plaintiff may be entitled to damages for “imperfections in Vigil’s performance,” but argue the district court erred by awarding Plaintiff damages based on the cost of repair. Instead,

1The Construction Contract consists of the AIA Document A201, General Conditions of the Contract for Construction (2007) (General Conditions Document) and the AIA Document A101, Standard Form of Agreement Between Owner and Contractor (2007), as well as Supplemental General Conditions, Technical Specifications, Addendum No. 1 and Drawings. Defendants contend, damages should have been based on the difference in value between the work called for in the contract and the value of the performance received. In support of this contention, Defendants point to language in the Construction Contract and the district court’s finding that Vigil substantially completed the work, and argue the district court erred by not taking into account the impact of substantial completion on Vigil’s liability. We are unpersuaded.

{6} Because Vigil and Plaintiff’s agreement is governed by the Construction Contract, we look to terms of the contract to determine whether the district court erred in awarding damages based on the cost to correct deficient work. “Contract interpretation is a matter of law that we review de novo.” Rivera v. Am. Gen. Fin. Servs., Inc., 2011- NMSC-033, ¶ 27, 150 N.M. 398, 259 P.3d 803. “The primary objective in construing a contract is to ascertain the intent of the parties.” J.R. Hale Contracting Co. v. Union Pac. R.R., 2008-NMCA-037, ¶ 49, 143 N.M. 574, 179 P.3d 579 (internal quotation marks and citation omitted). “We view the contract as a harmonious whole, give meaning to every provision, and accord each part of the contract its significance in light of other provisions.” Benz v. Town Ctr. Land, LLC, 2013-NMCA-111, ¶ 31, 314 P.3d 688 (alteration, internal quotation marks, and citation omitted).

{7} The General Conditions Document demonstrates an intent that the contractor (Vigil) remain liable to the owner (Plaintiff) for the cost of correcting defective work, regardless of whether the work was substantially complete. See General Conditions Document, supra, § 12.2.1 (providing that, before or after substantial completion, costs of correcting work rejected by the architect, including the cost of uncovering and replacement, shall be at the contractor’s expense); accord id. § 12.2.2.1 (providing that if within one year after substantial completion of the work any of the work is found to be not in accordance with the requirements of the contract documents, and, after notice, the contractor fails to correct nonconforming work within a reasonable time, the owner may correct it in accordance with Section 2.4); id. § 2.4 (permitting, subject to certain requirements, the owner to carry out the work in the event the contractor defaults or neglects to carry out the work in accordance with the contract documents, and providing that the owner may (a) deduct the reasonable cost of correcting such deficiencies from payments due the contractor, or (b) if payments due the contractor are insufficient to cover the amount, requiring the contractor to pay the difference to the owner). These contract provisions correspond with New Mexico’s approach to damages arising from defective or unfinished construction, which are typically calculated based on the reasonable cost of completing the construction called for in the contract. See UJI 13- 850 NMRA comm. cmt.; Unified Contractor, Inc. v. Albuquerque Hous. Auth., 2017- NMCA-060, ¶ 60, 400 P.3d 290.

{8} Defendants, however, point to Sections 9.8.4 and 9.8.5 of the General Conditions Document to support their contention that damages should have been based on the difference in value between the work called for in the contract and the value of the performance received. These sections provide that the architect shall prepare a Certificate of Substantial Completion, General Conditions Document, supra, § 9.8.4, and [t]he Certificate of Substantial Completion shall be submitted to [Plaintiff] and [Vigil] for their written acceptance of responsibilities assigned to them in such Certificate.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rivera v. American General Financial Services, Inc.
2011 NMSC 033 (New Mexico Supreme Court, 2011)
Sandoval v. Baker Hughes Oilfield Operations, Inc.
2009 NMCA 095 (New Mexico Court of Appeals, 2009)
Benz v. Town Center Land, LLC
2013 NMCA 111 (New Mexico Court of Appeals, 2013)
Normand by and Through Normand v. Ray
109 N.W. 403 (New Mexico Supreme Court, 1990)
Casias v. Dairyland Insurance
1999 NMCA 046 (New Mexico Court of Appeals, 1999)
Plains White Truck Company v. Steele
399 P.2d 642 (New Mexico Supreme Court, 1965)
In Re McCain
506 P.2d 1204 (New Mexico Supreme Court, 1973)
Shaeffer v. Kelton
619 P.2d 1226 (New Mexico Supreme Court, 1980)
State Ex Rel. Mountain States Mutual Casualty Co. v. KNC, Inc.
740 P.2d 690 (New Mexico Supreme Court, 1987)
Crutchfield v. New Mexico Department of Taxation & Revenue
2005 NMCA 022 (New Mexico Court of Appeals, 2004)
Jaramillo v. Gonzales
2002 NMCA 072 (New Mexico Court of Appeals, 2002)
J.R. Hale Contracting Co. v. Union Pacific Railroad
2008 NMCA 037 (New Mexico Court of Appeals, 2007)
KidsKare v. Mann
2015 NMCA 064 (New Mexico Court of Appeals, 2015)
Allred v. N.M. Dep't of Transp.
2017 NMCA 19 (New Mexico Court of Appeals, 2016)
Ballou v. Walker
2017 MT 197 (Montana Supreme Court, 2017)
Unified Contractor, Inc. v. Albuquerque Housing Auth.
2017 NMCA 60 (New Mexico Court of Appeals, 2017)
Progressive Cas. Ins. Co. v. Vigil
413 P.3d 850 (New Mexico Supreme Court, 2018)
Progressive Cas. Co. v. Vigil
2018 NMSC 14 (New Mexico Supreme Court, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
Cuba Soil & Water Conservation Dist. v. Granite RE, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/cuba-soil-water-conservation-dist-v-granite-re-inc-nmctapp-2023.