Blaine Economic Development Authority v. Royal Electric Co.

520 N.W.2d 473, 1994 Minn. App. LEXIS 784, 1994 WL 425191
CourtCourt of Appeals of Minnesota
DecidedAugust 16, 1994
DocketC5-93-2505
StatusPublished
Cited by7 cases

This text of 520 N.W.2d 473 (Blaine Economic Development Authority v. Royal Electric Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Blaine Economic Development Authority v. Royal Electric Co., 520 N.W.2d 473, 1994 Minn. App. LEXIS 784, 1994 WL 425191 (Mich. Ct. App. 1994).

Opinion

PETERSON, Judge.

Appellant Blaine Economic Development Authority (Blaine E.D.A.) sued respondent Royal Electric Co., Inc. (Royal) for breach of a construction contract. Royal counterclaimed for wrongful termination of the contract and damages. The district court granted partial summary judgment in favor of Royal on the issue of liability for wrongful termination of the contract. Following trial on the issue of damages, the district court awarded Royal $36,235, which included $21,-656 for lost profits. Blaine E.D.A. appeals the grant of partial summary judgment and the award of lost profits. We affirm.

FACTS

Blaine E.D.A. and Royal entered into a construction contract. Under the contract, Royal agreed to act as the electrical contrac *475 tor for the construction of the Blaine Senior Housing Project. The contract contained the following termination provision:

[I]f the Contractor persistently or repeatedly refuses or fails, except in cases for which extension of time is provided, to supply enough properly skilled workers or proper materials, * * * or otherwise is guilty of a substantial violation of a provision of the Contract Documents, and fails within seven days after receipt of written notice to commence and continue correction of such default, neglect or violation with diligence and promptness, the Owner * * * may, after seven days following receipt by the Contractor of an additional written notice * * * terminate the employment of the Contractor and take possession of the site and of all materials, equipment, tools, construction equipment and machinery thereon owned by the Contractor and may finish the Work by whatever methods the Owner may deem expedient.

In November 1990, Royal began performing electrical work. A number of disagreements arose between Royal and Blaine E.D.A. relating to Royal’s performance under the contract. On January 25, 1991, the project manager sent Michael Gannucci, Royal’s president, the following letter:

This letter is to serve as notice that you, Mike Gannucci of Royal Electric, are required to attend a meeting on Tuesday, January 29, 1991 at 11:00 A.M. at the City Hall in Blaine.
Discussion will be held regarding the continuous conflict between Royal Electric and the contract/scheduling delays. These problems are jeopardizing your contract on this project.
Your failure to attend this meeting will only support the existing problems we’re experiencing with your company.

At the meeting on January 29, 1991, Gan-nucci received the following written agenda:

BLAINE COURT/ROYAL ELECTRIC AGENDA

1/29/91 — 11:00 a.m.

PRESENT: Mike Gannucci

Sharon Witt

Arden Holzheimer

John Kaiser

Doug Moe

I. Royal Electric Daily Progress Schedule

A.John to read outline schedule

II. Temp Power <& Lights

A. 12/10/90 - Arden requested temp outlet

B. 12/17/90 - Power outlet & temp light requested

C. 12/28/90 - Power outlet & temp light requested

D. 1/2/91 - Mike of Royal meet at the City hall and stated he would install immediately the temp lights as per specs

E. 1/4/91 - One man installed lights, but not as per specs

F. 1/16/91 - In writing, Arden requested temp power & lights (As of 1/25/91 the 2nd & 3rd floor were not done)

III. Construction Schedule

A. Engineered Shops

1) 11/9/90 - signed contract sent to Royal

2) 1/3/91 - Mike showed the City a preliminary shop for the purpose of temp lighting & outlet location only.

3) 1/8/91 - Mike & A1 (low voltage rep) did not show up at a scheduled City meeting.

4) 1/25/91 - Royal still did not have the final shops to R.A. Morton, Doug Moe, or the City.

5) 12/13/90 - Received mechanical shops.

B. Man Power

1) 12/27/90 - Ready for electric (mechanical started)

2) 12/27/90 thru 1/25/91-one man alone worked a total of 7 days.

3) Construction Schedule

*476 IV. Change Orders

A. Corridor Lights
B. Exterior Lights

. C. Upcoming (sub out)

V. Contract
A. Signed contract (Royal/Blaine)
B. Bond
VI. Mise.

On February 1, 1991, at Gannueci’s request, Donald Poss, Blaine E.D.A.’s executive director, met with Gannucci to discuss the possibility of mutual termination of the contract. At both the January 29, 1991 meeting and the February 1, 1991 meeting, Gannucci made statements to the effect that he was losing money on the project.

On February 5,1991, Royal received a stop work order and a notice of intent to terminate contract from Blaine E.D.A. Pursuant to the stop work order, Royal left the job site. Blaine E.D.A. then hired J.T. Electric to complete electrical work on the project.

Blaine E.D.A. sued Royal for breach of contract. Royal counterclaimed, alleging that Blaine E.D.A. breached the contract. Royal brought a motion for partial summary judgment, asking the court to find that Blaine E.D.A. had wrongfully terminated the contract. The district court granted Royal’s motion, holding that Blaine E.D.A. wrongfully terminated the contract by not providing Royal with a written “notice to cure” seven days prior to the stop work order.

The issue of damages suffered by Royal due to Blaine E.D.A.’s wrongful termination of the contract was tried to the court. The district court awarded Royal $36,235 in damages, including $21,656 for lost profits.

ISSUES

1. Did Blaine E.D.A. give Royal the required written notice to cure before terminating the contract?

2. Did the district court properly determine the amount of Royal’s damages?

ANALYSIS

1. Liability

On appeal from summary judgment, this court must determine: whether there are any genuine issues of material fact and whether the district court erred in applying the law. Offerdahl v. University of Minn. Hosps. & Clinics, 426 N.W.2d 425, 427 (Minn.1988).

In granting partial summary judgment on the issue of liability, the district court held that Blaine E.D.A. wrongfully terminated the contract by not providing Royal with a written notice to cure pursuant to the contract’s termination provision.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Derosier v. Utility Systems of America, Inc.
780 N.W.2d 1 (Court of Appeals of Minnesota, 2010)
Schlichte v. Kielan
599 N.W.2d 185 (Court of Appeals of Minnesota, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
520 N.W.2d 473, 1994 Minn. App. LEXIS 784, 1994 WL 425191, Counsel Stack Legal Research, https://law.counselstack.com/opinion/blaine-economic-development-authority-v-royal-electric-co-minnctapp-1994.