J.A. McDonald, Inc. v. Waste Systems International Moretown Landfill, Inc.

189 F. Supp. 2d 174, 2001 U.S. Dist. LEXIS 23231, 2001 WL 1819644
CourtDistrict Court, D. Vermont
DecidedDecember 13, 2001
Docket2:99-cv-00172
StatusPublished

This text of 189 F. Supp. 2d 174 (J.A. McDonald, Inc. v. Waste Systems International Moretown Landfill, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Vermont primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J.A. McDonald, Inc. v. Waste Systems International Moretown Landfill, Inc., 189 F. Supp. 2d 174, 2001 U.S. Dist. LEXIS 23231, 2001 WL 1819644 (D. Vt. 2001).

Opinion

OPINION AND ORDER

SESSIONS, District Judge.

This matter is before the Court on Plaintiff J.A. McDonald, Inc.’s (“McDonald” or “Contractor”) motion for partial summary judgment in its claim of wrongful termination of contract against Defendant Waste Systems International Moretown Landfill, Inc. (“WSI-Moretown” or “Owner”). McDonald argues that as a matter of law WSI-Moretown wrongfully terminated the contract by failing to follow certain termination procedures allegedly required by the contract. For the reasons set forth below, McDonald’s motion for partial summary judgment is DENIED.

I. Background

A. Facts

The following facts are construed, as they must be on a motion for summary judgment, in the light most favorable to the nonmoving party, WSI-Moretown.

McDonald is a construction company with its principle place of business in Caledonia County, Vermont. WSI-Moretown is a Delaware corporation that owns and operates a landfill in Moretown, Vermont. On July 23, 1998 McDonald entered into a contract (“the Contract”) 1 with WSI-Moretown to construct a lined landfill cell in Moretown, Vermont. The project involved excavation to create the cell and the installation of underdrains and clay and synthetic liners. The Contract also required McDonald to construct certain other facilities at the site.

The landfill cell was to be WSI-More-town’s second one at the site, replacing the first cell, which was nearing capacity. As a result, it was important to WSI-More-town that the project be completed quickly. The Contract specified that the work must be completed by January 1, 1999. In addition, it stated that the time of completion was an “essential condition” of the Contract. Agreement ¶ 4.

Lamoroux & Dickinson (“L & D” or “Engineer”) was WSI-Moretown’s engineer for the project. L & D’s relationship with WSI-Moretown was the subject of a separate agreement (the “Administration Agreement”) between the two. The Contract also outlined a number of responsibilities of L & D. Most important to the present dispute were the Engineer’s responsibilities to decide “questions as to the acceptable fulfillment of this Agreement on the part of the Contractor,” Agreement ¶ 6, and questions regarding the “quality and acceptability of ... [the] WORK performed.” General Conditions ¶ 27.1.

*176 The Contract permitted the Contractor to avoid liquidated damages for work delayed by certain unforeseeable causes if written notice was provided to the Owner or Engineer. Agreement ¶ 5; General Conditions ¶ 15.4. Similar written notice to the Engineer or the Owner was required for other changes to the Contract terms. See e.g., General Conditions ¶ 11.3 (changes caused by emergencies affecting safety of workers); General Conditions ¶ 17.1 (permitting equitable adjustment of Contract prices caused by unexpected subsurface conditions). In general, any change to the work or prices under the Contract was to be effected through a change order. See e.g., General Conditions ¶ 8.1 (Contractor’s substitution of materials, articles, or equipment); General Conditions ¶ 14.0 (changes in the contract price, generally).

Unfortunately, McDonald did not complete the cell by the January 1, 1999 deadline. The cause of the delay is disputed by the parties, 2 but is not at issue in this motion.

On November 3, 1998 McDonald sent WSI-Moretown a letter indicating that it would be delayed in completing the work and that it faced additional costs as a result. (Paper 31, Ex. F). The letter stated that “it is J.A. McDonald’s position that due to adverse weather conditions ... the costs associated with [certain measures taken as a result of these conditions] will be processed as a Change Order to the Contract” which “will increase both the contract amount due and the time required for performance of the work.” Id. McDonald sent a second letter on November 17,1998 providing “formal notice according to the terms of the contract” that the work would be delayed and asking for additional time to complete the project. (Paper 31, Ex. G). However, no change order was granted and, as winter conditions set in, work on the project was halted.

On January 6, 1999, at WSI-Moretown’s request, L & D provided it with a memorandum listing the incomplete work at the project site as of January 1, 1999. (Paper 31, Ex. L). This list included McDonald’s failure to complete ten of the thirteen acres of the lined cell, as well as various other facilities. WSI-Moretown did not ask L & D to evaluate whether good cause existed for the delay. Thus, the memorandum did not provide reasons for the incomplete work nor did it conclude that grounds for termination of the contract did or did not exist.

On January 11, 1999, WSI-Moretown’s parent corporation, Waste System’s International, Inc., issued a “notice of default” to McDonald. The notice stated that the default was “[b]y reason of Contractor’s failure to comply with the terms of the Agreement, as more particularly described in the attached Memorandum Dated January 6, 1999 from [L & D], Contractor has breached its obligations under the [Contract] and accordingly, Contractor is hereby given this NOTICE OF DEFAULT.” (Paper 31, Ex. M). In a January 15, 1999 letter to Waste Systems International, McDonald contended that it was not in default under the Contract, that “a more detañed explanation” of the reasons for the alleged default was necessary, and that liquidated damages were to be paid only “as determined by the engineer.” (Paper 31, Ex. N).

At a January 28, 1999 meeting and a subsequent February 1999 meeting, the *177 parties failed to resolve their differences. The L & D engineer’s notes from the January meeting state that she told the parties: “L & D does not want to intrude in the dispute. L & D are [sic] available to render non-binding opinion to assist in resolving the dispute.” (Paper 31, Ex. 0).

In late February, WSI-Moretown hired L & D’s subconsultant, Golder Associates, as the engineer for the project and continued to retain L & D for certain limited services related to the project. On March 23, 1999 Waste Systems International issued a “notice of termination” to McDonald. This letter invoked paragraph 16, see Part B infra, of the Agreement for the termination and referenced the January 11,1999 “notice of default” letter for explanation of the grounds for termination. (Paper 31, Ex. S). Shortly thereafter WSI-Moretown retained a new contractor to complete the project.

On May 28, 1999 McDonald filed the instant action against WSI-Moretown and Frontier Insurance Co. (“Frontier”) 3 in Washington County Superior Court. J.A. McDonald, Inc. v. Waste Systems Int’l Moretown Landfill, Inc., No. 288-5-99 (Vt.Sup.Ct. May 28, 1999)(Paper 3). WSI-Moretown and Frontier removed the case to federal court on June 28,1999.

B. Contract Provisions

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Erie Railroad v. Tompkins
304 U.S. 64 (Supreme Court, 1938)
First Nat. Bank of Ariz. v. Cities Service Co.
391 U.S. 253 (Supreme Court, 1968)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Morrisseau v. Fayette
670 A.2d 820 (Supreme Court of Vermont, 1995)
Hill v. City of Burlington
597 A.2d 792 (Supreme Court of Vermont, 1991)
Blaine Economic Development Authority v. Royal Electric Co.
520 N.W.2d 473 (Court of Appeals of Minnesota, 1994)
Isbrandtsen v. North Branch Corp.
556 A.2d 81 (Supreme Court of Vermont, 1988)
United Railway Supply & Service, Ltd. v. Boston & Maine Corp.
535 A.2d 325 (Supreme Court of Vermont, 1987)
Karlen Communications, Inc. v. Mt. Mansfield Television, Inc.
433 A.2d 290 (Supreme Court of Vermont, 1981)
Ianelli v. Standish
592 A.2d 901 (Supreme Court of Vermont, 1991)
GTM, Inc. v. Transcontinental Insurance
5 F. Supp. 2d 219 (D. Vermont, 1998)
Bausch & Lomb Inc. v. Bressler
977 F.2d 720 (Second Circuit, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
189 F. Supp. 2d 174, 2001 U.S. Dist. LEXIS 23231, 2001 WL 1819644, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ja-mcdonald-inc-v-waste-systems-international-moretown-landfill-inc-vtd-2001.