White Sands Constr., Inc. v. City of Las Cruces

New Mexico Court of Appeals·Decided April 27, 2023·Unpublished

Opinion

The slip opinion is the first version of an opinion released by the Chief Clerk of the Supreme Court. Once an opinion is selected for publication by the Court, it is assigned a vendor-neutral citation by the Chief Clerk for compliance with Rule 23-112 NMRA, authenticated and formally published. The slip opinion may contain deviations from the formal authenticated opinion.

1 IN THE COURT OF APPEALS OF THE STATE OF NEW MEXICO 2 Opinion Number: _____________ 3 Filing Date: April 27, 2023 4 No. A-1-CA-39429

5 WHITE SANDS CONSTRUCTION, INC., 6 a New Mexico corporation,

7 Plaintiff-Appellee, 8 v.

9 CITY OF LAS CRUCES, a New Mexico 10 home rule municipality,

11 Defendant-Appellant.

12 APPEAL FROM THE DISTRICT COURT OF DOÑA ANA COUNTY 13 Marci E. Beyer, District Court Judge

14 Jackson Loman Stanford Downey & Stevens-Block, P.C. 15 Leah M. Stevens-Block 16 Kara Shair-Rosenfield 17 Albuquerque, NM

18 for Appellee

19 Martin & Lutz, P.C. 20 David P. Lutz 21 Las Cruces, NM

22 for Appellant 1 OPINION 2 WRAY, Judge. 3 {1} This appeal involves contract interpretation in the context of the Prompt 4 Payment Act (PPA), see NMSA 1978, §§57-28-1 to -11 (2001, as amended through 5 2007). Under the PPA, with few exceptions, “all construction contracts shall provide 6 that payment for amounts due shall be paid within twenty-one days after” receipt of 7 an undisputed application for payment. Section 57-28-5(A). If prompt payment is 8 not made as required, an interest penalty begins to accrue “on the twenty-second day 9 after payment was due,” which is “computed at one and one-half percent of the 10 undisputed amount per month or fraction of a month.” Id. The statutory penalty in 11 Section 57-28-5(A) continues “until the payment is issued.” 12 {2} Defendant the City of Las Cruces (the City) appeals from the district court’s 13 decision following a bench trial, which concluded that the City owed Plaintiff White 14 Sands Construction, Inc. (White Sands) $160,379.51 under the PPA, arising from 15 the City’s late payments to White Sands on a construction contract. The City argues 16 to this Court that White Sands waived its right to interest under the PPA and in the 17 alternative, that the district court miscalculated the amount of interest owed based 18 on an incorrect reading of the PPA and the parties’ agreements. We affirm in part, 19 reverse in part, and remand for further proceedings.

1 BACKGROUND 2 {3} In 2015, the City entered into a $10,000,000 contract (the Contract) with 3 White Sands to perform site development and to construct a Public Safety Complex 4 (the Project), a 35,000 square foot fire station and police substation. The Contract 5 involved three participants: the City as the “Owner,” White Sands as the 6 “Contractor,” and an individual identified as the “Architect.” The Contract required 7 White Sands to submit applications for payment to the Architect, who would review 8 and issue certificates for payment, and the City would make payments “not later than 9 twenty-one (21) days after the Architect receive[d] the [a]pplication for [p]ayment.” 10 In the event that the Project’s “substantial completion” date was delayed, White 11 Sands would owe “liquidated damages” calculated at a daily rate. 12 {4} The Project quickly ran into problems. The district court found that the Project 13 was significantly late reaching substantial completion and that the City failed to 14 make timely payments on twenty-three out of twenty-six of White Sands’ payment 15 applications. At trial, White Sands introduced evidence that the City’s chronic late 16 payments caused significant delays in construction, because White Sands needed the 17 funds from the City to pay the subcontractors who were “threatening to pull off the 18 job.” The district court found that the City additionally directed White Sands to 19 perform extra-contractual work throughout the Project and failed to adjust the 20 payments accordingly, even though White Sands contemporaneously submitted

1 change order requests. The district court also found that “the City chose to wait until 2 the end of the Project to settle the change orders in order to retain contract payments 3 to cover” amounts owed by White Sands at the end of the Project to compensate the 4 City for delayed completion (liquidated damages). By the time the Project neared 5 completion, to resolve mutual dissatisfaction and to finalize the Project, the parties 6 engaged in negotiations (the Negotiations). 7 {5} As part of the Negotiations, White Sands offered to forgo interest under the 8 PPA in return for the City abandoning any claim for liquidated damages. The City 9 responded to White Sands’ offer and informed White Sands, orally and in writing, 10 that any PPA claim should be raised with the risk management division apart from 11 the Negotiations. The parties entered into a settlement agreement and a final change 12 order (Change Order No. 2). The parties’ settlement agreement did not mention a 13 PPA claim and only released White Sands—not the City—from liability. Change 14 Order No. 2 includes as compensation for the City, a “Credit for Additional Time 15 extension beyond original substantial completion date,” which represented the 16 liquidated damages assessed against White Sands. The line item in which White 17 Sands had proposed zeroing out the PPA claim, however, was crossed out by the 18 City. 19 {6} White Sands filed a complaint and alleged a violation of the PPA to recover 20 statutory interest that had accrued on the City’s late payments. At trial, the City

1 argued that White Sands had waived recovery under the PPA in the Negotiations. 2 The parties also disputed the proper method for calculating any interest owed, 3 including the event that triggered the interest to begin to accrue, whether interest 4 accrued by the day or the month, and the date that interest stopped accruing. 5 Following the bench trial, the district court emailed the parties with its decision and 6 reasoning. The district court determined that White Sands had not waived PPA 7 interest, which the City owed to White Sands. Moving on to the “[p]roper method 8 of calculation of interest,” the district court concluded that interest began to accrue 9 twenty-two days after White Sands submitted a payment application to the Architect, 10 the City owed a full month of interest on the first day of each month that a payment 11 was overdue, and PPA interest stopped accruing three days before White Sands 12 received payments from the City. The district court later entered a written order 13 holding that under the PPA, the City owed White Sands $160,379.57 in interest and 14 reasonable attorney fees and costs. Between the district court’s email ruling and the 15 final written order, the City filed a “Motion for Clarification” related to the 16 calculation of interest and whether the three days the district court subtracted to 17 arrive at a payment date were calendar or business days. The district court denied 18 the motion but confirmed at a hearing that the three days were calendar days. The 19 City appeals.

Free access — add to your briefcase to read the full text and ask questions with AI

White Sands Constr., Inc. v. City of Las Cruces, (N.M. Ct. App. 2023).

White Sands Constr., Inc. v. City of Las Cruces (White Sands Constr., Inc. v. City of Las Cruces) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Schultz v. POJOAQUE TRIBAL POLICE DEPT.
242 P.3d 259 (New Mexico Supreme Court, 2010)
Kilgore v. FUJI HEAVY INDUSTRIES LTD.
2009 NMCA 078 (New Mexico Court of Appeals, 2009)
New Mexico Real Estate Commission v. Barger
2012 NMCA 81 (New Mexico Court of Appeals, 2012)
GEA Integrated Cooling Technology v. State Taxation & Revenue Dep't
2012 NMCA 10 (New Mexico Court of Appeals, 2011)
Baker v. Hedstrom
2013 NMSC 043 (New Mexico Supreme Court, 2013)
GCM, Inc. v. Kentucky Central Life Insurance
947 P.2d 143 (New Mexico Supreme Court, 1997)
Romero v. Earl
810 P.2d 808 (New Mexico Supreme Court, 1991)
Orcutt v. S & L Paint Contractors, Ltd.
791 P.2d 71 (New Mexico Court of Appeals, 1990)
Coates v. Wal-Mart Stores, Inc.
1999 NMSC 013 (New Mexico Supreme Court, 1999)
Tatsch v. Hamilton-Erickson Manufacturing Co.
418 P.2d 187 (New Mexico Supreme Court, 1966)
Melnick v. State Farm Mutual Automobile Insurance
749 P.2d 1105 (New Mexico Supreme Court, 1988)
Estrada Ex Rel. Estrada v. Cuaron
599 P.2d 1080 (New Mexico Court of Appeals, 1979)
Public Service Co. v. Diamond D Construction Co.
2001 NMCA 082 (New Mexico Court of Appeals, 2001)
Talbott v. Roswell Hospital Corp.
2005 NMCA 109 (New Mexico Court of Appeals, 2005)
J.R. Hale Contracting Co. v. Union Pacific Railroad
2008 NMCA 037 (New Mexico Court of Appeals, 2007)
Gallup Westside Development, LLC v. City of Gallup
2004 NMCA 010 (New Mexico Court of Appeals, 2003)
Durell v. Miles
206 P.2d 547 (New Mexico Supreme Court, 1949)
Ballou v. Walker
2017 MT 197 (Montana Supreme Court, 2017)
Unified Contractor, Inc. v. Albuquerque Housing Auth.
2017 NMCA 60 (New Mexico Court of Appeals, 2017)
Hill v. Long
299 P.2d 472 (New Mexico Supreme Court, 1956)