McDonnell Douglas Corp. v. United States

76 Fed. Cl. 385, 2007 U.S. Claims LEXIS 140, 2007 WL 1362449
CourtUnited States Court of Federal Claims
DecidedMay 3, 2007
DocketNo. 91-1204C
StatusPublished
Cited by4 cases

This text of 76 Fed. Cl. 385 (McDonnell Douglas Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McDonnell Douglas Corp. v. United States, 76 Fed. Cl. 385, 2007 U.S. Claims LEXIS 140, 2007 WL 1362449 (uscfc 2007).

Opinion

ORDER AND OPINION

HODGES, Judge.

The United States contracted with McDonnell Douglas and General Dynamics to design and build stealth aircraft for the Navy, then abruptly terminated the contractors for default. The contractors sued to convert the default to termination for convenience of the Government. The A-12 contract was technically complex, as might be expected of a major new weapons system, and the parties anticipated many years of development. The projected cost exceeded $4 billion in the initial stages. The purpose of the Full-Scale Engineering and Development (or FSED) contract was to design, develop, manufacture, and test eight A-12 aircraft. The eighth plane would serve as a prototype for subsequent production aircraft. Upon successful completion of the FSED effort, the Government could direct plaintiffs to begin a production phase. A series of options authorized the A-12 production phase in the contract by which the Government could purchase production “Lots” of aircraft. At termination, the Navy had exercised its contractual right to order six production aircraft, known as Lot I.

Almost from the beginning, the contractors encountered problems that caused them to fall behind schedule. McDonnell Douglas and General Dynamics were to deliver the first test aircraft in June 1990. It became apparent well before then that the contractors would not meet that schedule. The first test aircraft was a key milestone in development of the A-12 known as first flight. The parties were unable to agree on rescheduling [388]*388first flight and the succeeding seven aircraft of the FSED phase. The Navy extended the delivery dates unilaterally to accommodate the delayed prototypes. This unilateral modification of the contract’s schedule was designated P00046. P00046 lies at the heart of this dispute.

The issue on remand is “whether the Government’s default termination was justified.” McDonnell Douglas Corp. v. United States, 323 F.3d 1006, 1014 (Fed.Cir.2003). FAR 52.249-9 describes the Government’s authority to terminate a research and development contract for default. That section authorizes the Government to terminate a contract if the contractor fails to “prosecute the work so as to endanger performance of th[e] contract.” FAR 52.249-9(a)(1)(ii).

We review defendant’s default termination according to the “Lisbon standard.” McDonnell Douglas, 323 F.3d at 1015; see Lisbon Contractors, Inc. v. United States, 828 F.2d 759 (Fed.Cir.1987). The Lisbon standard permits termination for default if the Government demonstrates that the contracting officer had a reasonable belief “ ‘that there was no reasonable likelihood that the contractor[s] could perform the entire contract effort within the time remaining for contract performance.’” McDonnell Douglas, 323 F.3d at 1016 (quoting Lisbon, 828 F.2d at 765). The Court of Appeals for the Federal Circuit emphasized the importance of “decid[ing] the actual performance that the contract requires and the amount of time remaining for performance” before making that determination. Id. at 1017 (citing Lisbon, 828 F.2d at 766). In fact, the Circuit observed:

Unless the contracting officer had determined the entire effort required under the contract and the time left to complete the contract, it would be difficult, if not impossible, for him to resolve whether there was no reasonable likelihood that the contractor could perform the entire contract effort within the time remaining for contract performance.

Id. (internal quotation marks and citation omitted). The parties disagree about the meaning of the Circuit’s remand directing the court to apply the Lisbon test in this research and development contract.

The contractors urge the court to employ a strict interpretation of the Circuit’s remand. That is, “the entire contract effort” must be all-inclusive, comprising the eight FSED aircraft, the six Lot I production aircraft and years of follow-on testing, aircraft maintenance, and contractor support for the Navy. Plaintiff McDonnell Douglas argues that no contracting officer could reasonably have terminated the A-12 contract for default for failure to make progress if he did not know the work left to be done and the time left to do it.

The Government offers a more flexible approach. The “entire contract effort” as used by the Circuit represents a convenient and enforceable yardstick this court can use to evaluate the contractors’ progress at termination. Time was of the essence in the A-12 contract, and plaintiffs had an obligation to make enough progress to insure performance was not endangered. This court should decide whether the weight of the evidence in the record shows that the contracting officer was reasonably justified in feeling insecure about the contract’s timely completion.

Defendant’s argument is important in that the size of the yardstick does not matter. That is, the “entire contract effort” need not include every segment of work envisaged by the contract, but may be any objective measure of the contractors’ progress at termination. Defendant’s suggestion that we use a reasonable yardstick to measure performance is attractive for its flexibility and its simplicity, but it may be foreclosed by earlier rulings of the Federal Circuit.

The A-12 contract did not define “the time remaining for contract performance,” as plaintiffs have interpreted that phrase. The contract has no “time remaining for contract performance” as in .supply, service, and construction contracts. Defendant cannot prevail if the law requires an enforceable contract completion date at termination. That is, if the date we must look to in measuring the contractors’ progress can occur no earlier than after completion of plaintiffs’ contract requirements, we would vacate the termination for default. See Divecon Servs., LP v. [389]*389Dep’t of Commerce, GSBCA No. 15997, 04-2 BCA ¶32,656, 2004 WL 1405648 (June 22, 2004) (“Without a ... specific completion date, the Government could not rationally terminate for default for failure to make progress, since there was no objective against which the contractor’s progress could be judged.”). The contracting officer did not know in January 1991 when contract completion might occur.

Defendant’s burden of proof does not necessarily require the Government to provide a completion date for the entire contract effort, however. The FAR default provision does not refer to contract completion. The Circuit emphasized the importance of that requirement repeatedly, but the court also suggested other factors for consideration. Comparison of the percentage of work completed with the time remaining is only one consideration. McDonnell Douglas, 323 F.3d at 1016-17. The time remaining for performance is part of the “objective inquiry” under Lisbon. Id. Defendant’s inability to establish a completion date for the A-12 contract does not compel a ruling for plaintiffs.

The ruling in this case depends on a discrete element of contract performance used as a yardstick to measure the contractors’ progress at termination. The Navy’s unilateral modification known as P00046 serves this purpose.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sikorsky Aircraft Corporation v. United States
122 Fed. Cl. 711 (Federal Claims, 2015)
General Dynamics Corp. v. United States
131 S. Ct. 1900 (Supreme Court, 2011)
Pinckney v. United States
88 Fed. Cl. 490 (Federal Claims, 2009)
McDonnell Douglas Corp. v. United States
567 F.3d 1340 (Federal Circuit, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
76 Fed. Cl. 385, 2007 U.S. Claims LEXIS 140, 2007 WL 1362449, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcdonnell-douglas-corp-v-united-states-uscfc-2007.