CJP Contractors, Inc. v. United States

45 Fed. Cl. 343, 1999 U.S. Claims LEXIS 274, 1999 WL 1077092
CourtUnited States Court of Federal Claims
DecidedNovember 19, 1999
DocketNos. 95-126C, 95-786C
StatusPublished
Cited by17 cases

This text of 45 Fed. Cl. 343 (CJP Contractors, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CJP Contractors, Inc. v. United States, 45 Fed. Cl. 343, 1999 U.S. Claims LEXIS 274, 1999 WL 1077092 (uscfc 1999).

Opinion

OPINION

FIRESTONE, Judge.

The present consolidated actions were brought pursuant to the Contract Disputes Act of 1978, 41 U.S.C. §§ 601-613 (1994). The contractor, CJP Contractors, Inc. (“CJP”), was default terminated before the contract’s completion date for failure to make progress. In this action, CJP is seeking to convert the termination for default into a termination for the convenience of the government. Defendant, the General Services Administration (“GSA”), argues that the termination for default should be upheld and is seeking $917,539.62 in excess reprocurement costs, administrative expenses, and liquidated damages arising from its termination decision. Trial in this matter was held in Washington, D.C., from July 12 to July 23, 1999. For the reasons that follow, the court finds that the termination for default decision is not sustainable and must therefore be reversed.

I. BACKGROUND FACTS

A. Contract Requirements and Award

On July 23, 1993, GSA solicited bids for fixed-price contract No. GS-11P93MK0081 for the replacement of the heating system at the GSA storage depot in Springfield, Virginia. The contract required, among other things, the contractor to install the piping needed for a new gas-fired heating system, remove and demolish the storage facility’s existing oil-based heating system, and install the new gas-fired industrial furnaces and ac[347]*347companying duct work. The contract divided performance into two phases. Phase A of the contract required the contractor to install and energize the new gas piping at the six buildings1 that make up the storage depot before beginning work on Phase B. Phase B required the contractor to demolish and dispose of the existing oil-fired heating units and then replace those units with the new gas-fired furnaces. Only after the new units were functioning would the contractor be authorized to dismantle and dispose of the existing heating oil-lines and oil storage tanks.2 Under the terms of the contract, Phase A was to be completéd within 170 days of the notice to proceed, and Phase B was to be completed within 310 days of the notice to proceed.

On August 20, 1993, CJP submitted the low bid on the contract.3 In fact, CJP’s bid of $632,300 was 28% below the government’s $878,300 estimate for the work and 21% lower than the average of the next two lowest bids. Concerned about the accuracy of CJP’s bid, Joy Walker, the Contracting Officer (“CO”) for GSA,4 requested that CJP verify its bid before making an award. CJP confirmed its bid and was awarded the contract on September 23, 1993.5

B. Phase A—Disputes and Delays in Connection with Installation of the New Gas Pipeline and Procuring the Replacement Gas-fired Units.

From the beginning of the project, the relationships between Paul Tully, CJP’s president, and GSA’s on-site representatives, William (“Bill”) Henry, the construction engineer, and Stephen Disselkoen, the construction quality manager, were strained.6 It was clear from Mr. Disselkoen’s testimony that he and Mr. Henry believed that CJP did not have the right crew, equipment, or attitude [348]*348for the job. Mr. Disselkoen’s testimony throughout the trial reflected his view that CJP never properly performed the contract. Problems between CJP and GSA began with concerns over CJP’s delay in getting started with Phase A.

C. The Gas Meter Details

After receiving the contract award, CJP, in accordance with the contract, submitted a bar chart progress schedule to GSA that established a time line for each of the major project tasks.7 CJP’s November 29, 1993 schedule indicated that CJP would start work on January 4, 1994. CJP did not, however, mobilize to the site on that date. Instead, by letter dated December 27, 1993, CJP notified GSA that it would not be able to begin work on January 4, 1994. The letter informed GSA that the weeks of January 3, 1994, January 10, 1994, and January 17, 1994, CJP would be in Georgia working on other government jobs. Despite this change in schedule, the letter went on to assure GSA that CJP would begin work on January 24, 1994, and would establish a “rigid” schedule. Further, the letter stated that CJP’s “delay in starting work on site will not delay completion of the project.”

While acknowledging the delay, Mr. Tully wrote further:

It is our hope that this delay in starting will allow you to provide the connection details at the Gas Meter in Bay 4B. As discussed, we need to confirm that 14" off the wall to the center of the 8" pipe is acceptable to the Gas Company and the elevation above the floor for the 8" Flange we will provide on the 8" main to connect to the meter.

At trial Mr. Tully explained that even if CJP was not delayed by other ongoing contracts, CJP could not have started work on the GSA project because of GSA’s failure to provide CJP with certain essential details of the project. Specifically, Mr. Tully stated that in order to begin installing the gas piping he needed to know where the gas meter for the Washington Gas Company would be set so he could determine how far off the wall the pipe should be installed. Mr. Tully stated that he needed this information in order to fabricate the brackets that would support the pipe. Mr. Tully explained that for efficiency purposes he planned to use the same size brackets for all of the piping, and as a result, he needed to know how far off the wall the meter would be set before CJP could begin to hang any of the piping.

When he failed to receive a response from Mr. Henry, Mr. Tully sent Mr. Henry a letter on January 6, 1994, stating that CJP intended to install the pipe 14 inches off the wall. Mr. Henry’s response to the letter is contained in a handwritten note at the bottom of the letter stating, “I advised Paul not to fabricate any material based on any understanding that the pipe will be 14" off the wall. The meter is scheduled to be set the week of 1/10/94.” Mr. Tully testified further that he notified Mr. Henry that because CJP could not begin the job without the gas meter details, CJP intended to work on other jobs during the early part of January. Mr. Tully stated that Mr. Henry told him that he “saw no problem” with this plan. After receiving the gas meter details on January 13, 1994, Mr. Tully ordered the brackets. Once the brackets were available, CJP started work on February 7, 1994.

At trial Mr. Francis Woods of Summer Engineering, the architecVengineer (“A & E”) for this project, testified that CJP’s contention that it needed the gas meter details to begin work was not supported because CJP could have used adjustable standard brackets to hang all of the gas piping. Ac[349]*349cording to Mr. Woods, the final connection to the gas meter could wait until the meter was set without impeding the progress of the gas pipe installation. As a result, Mr. Woods concluded that the gas meter details in no way delayed CJP’s start date.

Mr. Christopher Gilley, plaintiffs expert witness,8 disagreed with Mr. Woods’s contention that CJP did not need the gas meter details, but concurred with Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gilbane Federal v. United Infrastructure Projects FZCO
275 F. Supp. 3d 1180 (N.D. California, 2017)
5860 Chicago Ridge, LLC v. United States
104 Fed. Cl. 740 (Federal Claims, 2012)
Martin Construction, Inc. v. United States
102 Fed. Cl. 562 (Federal Claims, 2011)
Armour of America v. United States
96 Fed. Cl. 726 (Federal Claims, 2011)
Richard E. Lambert, Ltd. v. City of Tucson Department of Procurement
221 P.3d 375 (Court of Appeals of Arizona, 2009)
Universal Shelters of America, Inc. v. United States
87 Fed. Cl. 127 (Federal Claims, 2009)
McDonnell Douglas Corp. v. United States
76 Fed. Cl. 385 (Federal Claims, 2007)
R.P. Wallace, Inc. v. United States
63 Fed. Cl. 402 (Federal Claims, 2004)
Lassiter v. United States
60 Fed. Cl. 265 (Federal Claims, 2004)
CEMS, Inc. v. United States
59 Fed. Cl. 168 (Federal Claims, 2003)
PCL Construction Services, Inc. v. United States
47 Fed. Cl. 745 (Federal Claims, 2000)
Becho, Inc. v. United States
47 Fed. Cl. 595 (Federal Claims, 2000)
Libertatia Associates, Inc. v. United States
46 Fed. Cl. 702 (Federal Claims, 2000)
Professional Services Supplier, Inc. v. United States
45 Fed. Cl. 808 (Federal Claims, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
45 Fed. Cl. 343, 1999 U.S. Claims LEXIS 274, 1999 WL 1077092, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cjp-contractors-inc-v-united-states-uscfc-1999.