Richard E. Lambert, Ltd. v. City of Tucson Dept. of Procurement

Court of Appeals of Arizona·Decided December 4, 2009·No. 2 CA-CV 2009-0022·Published

Opinion

FILED BY CLERK

DEC -4 2009

IN THE COURT OF APPEALS COURT OF APPEALS STATE OF ARIZONA DIVISION TWO DIVISION TWO

RICHARD E. LAMBERT, LTD., ) 2 CA-CV 2009-0022 ) DEPARTMENT A

Plaintiff/Appellee, )

) OPINION

v. )

)

CITY OF TUCSON DEPARTMENT OF ) PROCUREMENT, )

)

Defendant/Appellant. )

)

APPEAL FROM THE SUPERIOR COURT OF PIMA COUNTY Cause No. C20073264

Honorable John F. Kelly, Judge REVERSED AND REMANDED

Durazzo & Eckel, P.C. By Patric E. Durazzo and Eric Hawkins Tucson Attorneys for Plaintiff/Appellee

Mesch, Clark & Rothschild, P.C. By Melvin C. Cohen, Scott H. Gan and Tucson Paul A. Loucks Attorneys for Defendant/Appellant

H O W A R D, Chief Judge.

¶1 Appellant City of Tucson appeals from the superior court’s judgment partially overturning the City Procurement Director’s determination upholding liquidated damages assessed against appellee, Richard E. Lambert, Ltd. (hereinafter REL). The City also appeals the superior court’s order granting REL’s request for attorney fees. Because substantial evidence supports the Director’s decision, we reverse the superior court.

Facts and Procedural History

¶2 We view the facts in the light most favorable to upholding the administrative decision of the City Procurement Director. See Whiteco Outdoor Adver. v. City of Tucson, 193 Ariz. 314, ¶ 7, 972 P.2d 647, 650 (App. 1998) (appellate court bound by board’s factual findings); cf. Pingitore v. Town of Cave Creek, 194 Ariz. 261, ¶ 18, 981 P.2d 129, 132 (App. 1998) (we affirm administrative decision if supported by credible evidence); see also Special Fund Div. v. Indus. Comm’n, 182 Ariz. 341, 346, 897 P.2d 643, 648 (App. 1994). REL contracted with the City of Tucson to improve the city-owned Northwest Mansfield Park Neighborhood Center. Under the terms of the contract, REL was to improve a gymnasium building and add irrigation and landscaping to the sports fields surrounding the center. The contract required REL to begin work by January 5, 2004, and to work “promptly, regularly, diligently and uninterruptedly at such rate of progress as will insure full completion thereof within the time specified.” The contract further provided: “If the Contractor is delayed on any portion of the Work for any reason whatsoever, he shall expeditiously proceed on other

Portions of the Work which are not affected by such delay.” After numerous extensions, REL was required to substantially complete the project by February 3, 2005.

¶3 REL completed the project on December 19, 2005, 319 days after the agreed upon completion date. Pursuant to the terms of the contract, the City then assessed REL $500 per day in liquidated damages and retained the final $108,305.95 due on the project. REL appealed that decision to the City Contract Officer. The Contract Officer determined that REL was responsible for the delay in completion of the project and, therefore, found that the City was entitled to assess liquidated damages under the terms of the contract.

¶4 Pursuant to the terms of the Tucson City Procurement Code, REL appealed the Contract Officer’s decision to the City Director of Procurement. See Tucson City Proc. Code § 28-76 (“Appeals from the decisions of the Contract Officer may be made to the Director” of Procurement.). The Director appointed a hearing officer, who held an evidentiary hearing and ultimately agreed with the Contract Officer that the City was entitled to liquidated damages. See Tucson City Proc. Code § 28-113(1) (director shall appoint hearing officer to decide matter). The hearing officer then submitted this recommendation to the Procurement Director, who affirmed it. See Tucson City Proc. Code § 28-114(2) (director may affirm, modify or reject recommendation of hearing officer).

¶5 REL filed a special action in superior court, 1 challenging the Director of Procurement’s decision, relying upon a term of the contract granting REL a time extension

1 Neither party challenged this procedure and we do not decide its propriety.

in the event of “unforeseeable causes beyond the control and without the fault or negligence of the Contractor” such as “acts of God” and “acts of the City.” See also Tucson City Proc. Code § 28-117. Both the City and REL filed cross-motions for summary judgment. The superior court granted REL’s motion in part, concluding that the Procurement Director’s factual findings were arbitrary, capricious, and unsupported by the facts, reduced the liquidated damages to $13,500 and awarded REL its attorney fees. The City appeals from this decision. See A.R.S. § 12-2101(B).

Evidentiary Hearing

¶6 Relying upon Rule 4(f), Ariz. R. P. Spec. Actions, the City preliminarily contends that the superior court erred in granting partial summary judgment in favor of REL without holding an evidentiary hearing. Rule 4(f) states that if “a triable issue of fact is raised in an action under this Rule, it shall be tried subject to special orders concerning discovery.” (Emphasis added.)

¶7 In granting partial summary judgment in favor of REL, the superior court did not resolve issues of fact. Rather, the court resolved legal issues involving whether substantial evidence supported the City Procurement Director’s findings. See Havasu Heights Ranch and Dev. Corp. v. Desert Valley Wood Prods., Inc., 167 Ariz. 383, 387, 807 P.2d 1119, 1123 (App. 1990) (whether substantial evidence supports administrative officer’s findings is question of law). Accordingly, no evidentiary hearing was required, and we address the merits of the City’s appeal.

Summary Judgment

¶8 The City argues that the Procurement Director’s findings were supported by substantial evidence and therefore contends the superior court erred in setting them aside by granting partial summary judgment in REL’s favor. Summary judgment is appropriate if “no genuine issues of material disputed facts remain and the moving party is entitled to judgment as a matter of law.” Woerth v. City of Flagstaff, 167 Ariz. 412, 416, 808 P.2d 297, 301 (App. 1990). We review the superior court’s decision to grant summary judgment de novo. Liberty Mut. Fire Ins. Co. v. Mandile, 192 Ariz. 216, 222, 963 P.2d 295, 301 (App. 1997).

¶9 When reviewing an administrative decision, the superior court must determine whether the administrative officer’s “determination was arbitrary and capricious or an abuse of discretion.” Robertson v. Superior Court, 136 Ariz. 440, 442, 666 P.2d 540, 542 (App. 1983), citing Ariz. R. P. Spec. Actions 3(c); cf. Caretto v. Ariz. Dep’t of Transp., 192 Ariz. 297, ¶ 7, 965 P.2d 31, 34 (App. 1998). In determining whether an administrative decision is arbitrary or capricious, the superior court “may not weigh the evidence on which the decision was based” and must affirm if the decision is supported by substantial evidence. Ariz. Dep’t of Pub. Safety v. Dowd, 117 Ariz. 423, 426, 429, 573 P.2d 497, 500, 503 (App. 1977). And the superior court errs when it substitutes its own judgment for that of the administrative officer. See Black v. City of Phoenix, 157 Ariz. 93, 96, 754 P.2d 1268, 1371 (App. 1988); see also Smith v. Ariz. Dep’t of Transp., 146 Ariz. 430, 432, 706 P.2d 756, 758 (App. 1985).

¶10 Like the superior court, this court also determines whether the record contains any evidence to support the administrative decision. Dowd, 117 Ariz. at 426, 573 P.2d at 500; see also Potter v. Ariz. Dep’t of Transp., 204 Ariz. 73, ¶ 8, 59 P.3d 837, 840 (App. 2002). We do not re-weigh the evidence; we merely determine if substantial evidence exists to support the administrative officer’s conclusions. Dowd, 117 Ariz. at 426, 429, 573 P.2d at 500, 503. In determining whether substantial evidence exists, “it is necessary to determine whether the [administrative] decision sought to be reviewed is without any evidence to support it, or is absolutely contrary to uncontradicted and unconflicting evidence upon which it purports to rest.” Id. at 426, 573 P.2d at 500. Construction Delay Law

Free access — add to your briefcase to read the full text and ask questions with AI

Richard E. Lambert, Ltd. v. City of Tucson Dept. of Procurement, (Ark. Ct. App. 2009).

Richard E. Lambert, Ltd. v. City of Tucson Dept. of Procurement (Richard E. Lambert, Ltd. v. City of Tucson Dept. of Procurement) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Paul Hardeman, Inc. v. The United States
406 F.2d 1357 (Court of Claims, 1969)
Caretto v. Arizona Department of Transportation
965 P.2d 31 (Court of Appeals of Arizona, 1998)
Robertson v. SUPERIOR CT. STATE OF ARIZ.
666 P.2d 540 (Court of Appeals of Arizona, 1983)
Pingitore v. Town of Cave Creek
981 P.2d 129 (Court of Appeals of Arizona, 1998)
Arizona Department of Public Safety v. Dowd
573 P.2d 497 (Court of Appeals of Arizona, 1977)
Winter v. Coor
695 P.2d 1094 (Arizona Supreme Court, 1985)
Blake v. City of Phoenix
754 P.2d 1368 (Court of Appeals of Arizona, 1988)
New Pueblo Constructors, Inc. v. State
696 P.2d 185 (Arizona Supreme Court, 1985)
Special Fund Division v. Industrial Commission
897 P.2d 643 (Court of Appeals of Arizona, 1994)
Woerth v. City of Flagstaff
808 P.2d 297 (Court of Appeals of Arizona, 1990)
Whiteco Outdoor Advertising v. City of Tucson
972 P.2d 647 (Court of Appeals of Arizona, 1998)
Smith v. Arizona Department of Transportation
706 P.2d 756 (Court of Appeals of Arizona, 1985)
Liberty Mutual Fire Insurance v. Mandile
963 P.2d 295 (Court of Appeals of Arizona, 1997)
Clark v. Compania Ganadera De Cananea, S. A.
387 P.2d 235 (Arizona Supreme Court, 1963)
Eastern Vanguard Forex Ltd. v. Arizona Corp. Commission
79 P.3d 86 (Court of Appeals of Arizona, 2003)
Potter v. Arizona Department of Transportation
59 P.3d 837 (Court of Appeals of Arizona, 2002)
Youngdale & Sons Construction Co. v. United States
38 Cont. Cas. Fed. 76,467 (Federal Claims, 1993)
Blinderman Construction Co. v. United States
42 Cont. Cas. Fed. 77,210 (Federal Claims, 1997)
CJP Contractors, Inc. v. United States
45 Fed. Cl. 343 (Federal Claims, 1999)