Pingitore v. Town of Cave Creek

981 P.2d 129, 194 Ariz. 261, 273 Ariz. Adv. Rep. 18, 1998 Ariz. App. LEXIS 115
CourtCourt of Appeals of Arizona
DecidedJuly 7, 1998
Docket1 CA-CV 97-0311
StatusPublished
Cited by19 cases

This text of 981 P.2d 129 (Pingitore v. Town of Cave Creek) is published on Counsel Stack Legal Research, covering Court of Appeals of Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pingitore v. Town of Cave Creek, 981 P.2d 129, 194 Ariz. 261, 273 Ariz. Adv. Rep. 18, 1998 Ariz. App. LEXIS 115 (Ark. Ct. App. 1998).

Opinion

*262 EHRLICH, Judge.

¶ 1 The Town of Cave Creek, its Town Council and its Board of Adjustment appeal from the superior court’s entry of summary judgment in favor of George and Kris Pingitore. The Pingitores sought relief from the court after the Board affirmed two orders issued by the Town halting construction of the Pingitores’ residence. In granting the Pingitores summary judgment, the court concluded that (1) the Town’s zoning ordinance is unconstitutionally vague, (2) the Pingitores have a vested right to complete construction of their residence at the planned site and (3) the Town is estopped from enforcing certain zoning restrictions precluding the Pingitores from building their home at that site. For the reasons discussed below, we affirm the judgment.

FACTUAL AND PROCEDURAL BACKGROUND

¶ 2 The Pingitores own property on Black Mountain in Cave Creek on which they want to build a home. In July 1992, they applied to the Town for a permit to extend Old Schoolhouse Road up the side of the mountain for use as a driveway to the site of their future residence. In October 1992, after the Town Engineer had reviewed their plans, the Town issued the Pingitores a permit for construction of the driveway.

¶ 3 At this time, the property was zoned R-70. Under this zoning, the Pingitores were allowed to build their residence on the property as long as their plans met the requirements of the Hillside Development Overlay District (“Hillside . Regulations”) and the yard, height and lot size requirements of the R-70 zoning classification.

¶ 4 In February 1993, after a plan review of the project, the Town advised the Pingitores that their driveway, as now partially built, potentially violated the Hillside Regulations. After Mr. Pingitore met with the Town’s Supervising Engineer and the Town Manager to discuss the Town’s concerns, the Town staff advised the Pingitores to apply to the Board for a variance allowing them to complete the driveway.

¶ 5 The Pingitores duly applied for the variance, seeking permission to pave a driveway that exceeded the Hillside Regulations’ width and height limitations for exposed cut- and-fill slopes. In December 1993, the Board approved the variance, subject to additional requirements that the Pingitores re-vegetate disturbed areas within 18 months of the date of the variance and install a large water-storage tank on the property to comply with fire-safety standards applicable to their planned residence.

¶ 6 In January 1994, the Town Mayor told the Board that, if it did not reconsider the variance with the imposition of additional conditions, the Town Council would appeal the grant of the variance to the superior court. The Pingitores then agreed to pave the driveway within the 18 months in which they were to complete the revegetation and landscaping work. Approximately $60,000 has been expended in constructing the driveway.

¶ 7 In October 1994, the Town Engineer sent a memorandum to the Town Manager explaining that the property owners on Black Mountain would have to excavate two to three acres of the mountain to install a proper wastewater system. The engineer warned that such an excavation would scar the mountain for several years, but he added that scarring could be avoided if the property owners connected to the Town’s wastewater system through underground sewer lines. He advised that the easiest and most cost-effective method of installing such sewer lines was to run them along the driveway being constructed by the Pingitores. Thereafter, the Pingitores agreed to extend a sewer line to the site of their residence and applied for the required permit. The Town granted this permit in December 1994, and the Pingitores finished the backfill of the trench dug for the installation of the sewer line in April 1995, expending approximately $11,000 in installing the line.

¶8 In August 1995, the Pingitores applied for a building permit to install the water-storage tank and booster-pump stations dictated by the Town to comply with its fire-safety standards. The Town granted *263 this permit, and the Pingitores spent approximately $8800 installing these items.

¶ 9 About this time, the Town approved a zoning clearance for the Pingitores’ residence conditioned upon their satisfaction of minimum setback requirements. This required the Pingitores to obtain a lot-line adjustment prior to the issuance of a building permit. To comply with these provisos, the Pingitores joined 2.5 acres of a five-acre parcel adjacent to their property, which they purchased for $220,000, to the five-acre parcel on which they intended to build their residence.

¶ 10 A later Town Planning Staff report said that the Pingitores’ proposed lot-line adjustment now conformed to the zoning requirements. Thus, the Pingitores applied for a building permit to construct their residence, including with their application a complete set of plans and drawings for review by the Town’s engineering staff. In September 1995, a Town official advised the Pingitores’ architect that certain changes to the plans were needed before the Town could approve the plans and issue a building permit.

¶ 11 On September 25, 1995, the Pingitores posted a grading bond of $8250. On October 2, the Town declared that the conditions of the zoning clearance had been satisfied, and it granted the Pingitores a permit for the grading of their site. The Pingitores contracted with a grading company for preparation of the site. The price for this work is $45,000, and the Pingitores have paid the first bill of $7068.09.

¶ 12 The Pingitores also hired Desert Southwest Construction as the contractor for the construction of them residence. Under this contract, they face $96,000 in liability.

¶ 13 In July 1994, while the Pingitores were in the midst of this project, the Town adopted an ordinance creating a new zoning district, the Mountain Preservation Zone (“MP Zone”), which includes the Pingitores’ property. In the MP Zone, structures may not be constructed above the twenty-degree-horizontal plane of any “ridge line,” which term is undefined.

¶ 14 On October 23, 1995, the Town Zoning Administrator issued a stop-work order directing that the Pingitores cease construction of their residence. The Town’s stated basis for the order was the Pingitores’ failure to comply with the time limitations for completing the revegetation and paving stipulations attached to the driveway variance. However, the Town Manager later admitted that the order was actually issued because the Town was uncertain whether the building restrictions imposed by the MP Zone applied to the Pingitores’ property.

¶ 15 The Pingitores appealed the Zoning Administrator’s stop-work order to the Board. On November 28, the Town Zoning Administrator issued the Pingitores a second stop-work order for violating the MP Zone provisions. The Pingitores also appealed the issuance of this order to the Board.

¶ 16 On December 12, the Board heard the Pingitores’ appeal of both orders. At this proceeding, the Pingitores were advised for the first time that the Town Zoning Administrator had determined that they were building on a ridge line in violation of the MP Zone ordinance. The Pingitores asserted that the Town’s Zoning Ordinance and Map were invalidly adopted and therefore void.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Silk v. Blodgett
Court of Appeals of Arizona, 2023
McGeary v. City of Sedona
Court of Appeals of Arizona, 2022
Nova v. Mesa Board
Court of Appeals of Arizona, 2021
Maricopa v. Rana
Court of Appeals of Arizona, 2020
Adams v. Giguere
Court of Appeals of Arizona, 2017
Warner v. Phx Board
Court of Appeals of Arizona, 2017
Levine v. phoenix/suns
Court of Appeals of Arizona, 2016
Flood Control v. Abc Sand
Court of Appeals of Arizona, 2014
Gorman v. Pima County
287 P.3d 800 (Court of Appeals of Arizona, 2012)
Stagecoach Trails MHC, L.L.C. v. City of Benson
278 P.3d 314 (Court of Appeals of Arizona, 2012)
Scenic Arizona v. City of Phoenix Board of Adjustment
268 P.3d 370 (Court of Appeals of Arizona, 2012)
Richard E. Lambert, Ltd. v. City of Tucson Department of Procurement
221 P.3d 375 (Court of Appeals of Arizona, 2009)
City of Tucson v. Clear Channel Outdoor, Inc.
181 P.3d 219 (Court of Appeals of Arizona, 2008)
Lowe v. Pima County
177 P.3d 1214 (Court of Appeals of Arizona, 2008)
Austin Shea (Arizona) 7th Street & Van Buren, L.L.C. v. City of Phoenix
142 P.3d 693 (Court of Appeals of Arizona, 2006)
Luther Construction Co. v. Arizona Department of Revenue
74 P.3d 276 (Court of Appeals of Arizona, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
981 P.2d 129, 194 Ariz. 261, 273 Ariz. Adv. Rep. 18, 1998 Ariz. App. LEXIS 115, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pingitore-v-town-of-cave-creek-arizctapp-1998.