United States of America, for the use and benefit of Timberline Construction Group, LLC v. APTIM Federal Services, LLC, et al.

CourtDistrict Court, M.D. Louisiana
DecidedFebruary 4, 2026
Docket3:24-cv-00669
StatusUnknown

This text of United States of America, for the use and benefit of Timberline Construction Group, LLC v. APTIM Federal Services, LLC, et al. (United States of America, for the use and benefit of Timberline Construction Group, LLC v. APTIM Federal Services, LLC, et al.) is published on Counsel Stack Legal Research, covering District Court, M.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States of America, for the use and benefit of Timberline Construction Group, LLC v. APTIM Federal Services, LLC, et al., (M.D. La. 2026).

Opinion

UNITED STATES DISTRICT COURT MIDDLE DISTRICT OF LOUISIANA UNITED STATES OF AMERICA, for the use and benefit of TIMBERLINE CONSTRUCTION GROUP, LLC CIVIL ACTION VERSUS NO. 24-669-JWD-EWD APTIM FEDERAL SERVICES, LLC, ET AL. RULING AND ORDER This matter comes before the Court on Timberline’s Motion for Summary Judgment (“Timberline’s MSJ”) (Doc. 117) filed by Timberline Construction Group, LLC (“Timberline”). APTIM Federal Services, LLC (“APTIM”) opposes the motion. (Doc. 133.) Timberline filed a reply. (Doc. 138.) APTIM filed a sur-reply. (Doc. 145.) Oral argument is not necessary. The Court has carefully considered the law, the facts in the record, and the arguments and submissions of the parties and is prepared to rule. For the following reasons, Timberline’s MSJ is denied. I. RELEVANT BACKGROUND A. Factual Background Following Hurricane Ian, the United States Army Corps of Engineers (“USACE”) undertook to build temporary housing (“the Project”) in Lee County, Florida. (Statement of Material Facts (“SMF”), Doc. 117-1 at 1, ¶ 1.)1 The Project was located on land owned by Habitat Harlem Heights, LLC (“Habitat”). (Id. at 1, ¶ 2.) The Federal Emergency Management Agency (“FEMA”) leased this land from Habitat. (Id.; see Doc. 133-1 at 1–2, ¶ 2.) At all relevant times, 1 Unless otherwise indicated (e.g., with a qualifying record citation), when the Court cites the Statement of Material Facts, APTIM has admitted the cited material. See M.D. La. Civ. R. 56(f). the USACE owned/was responsible for the Project. (See, e.g., Doc. 117-6 at 14 (Question: “[T]he entity that was in the role as owner for the [P]roject would have been the [USACE]?” Answer: “Correct.”).) The USACE hired Brice Aptim JV, LLC (“BAJV”) as general contractor. (Doc. 117- 1 at 1, ¶ 1.) BAJV subcontracted work to its member APTIM. (Id. at 2, ¶ 4.) In turn, APTIM subcontracted work to Timberline. (Id. at 2, ¶ 7.)

The contract between the USACE and BAJV (“the Prime Contract”) included a Federal Acquisition Regulations (“FAR”) provision commonly known as the Permits and Responsibilities Clause. (Id. at 2, ¶¶ 5–6 (citing Doc. 117-3 at 170 (quoting 48 C.F.R. § 52.236–7)).) It reads: The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses and permits, and for complying with any Federal, State, and municipal laws, codes, and regulations applicable to the performance of the work. The Contractor shall also be responsible for all damages to persons or property that occur as a result of the Contractor’s fault or negligence. The Contractor shall also be responsible for all materials delivered and work performed until completion and acceptance of the entire work, except for any completed unit of work which may have been accepted under the contract.

48 C.F.R. § 52.236–7; see also Doc. 117-3 at 170 (quoting 48 C.F.R. § 52.236–7). The subcontract between BAJV and APTIM contained several FAR “flow down” provisions, including the Permits and Responsibilities Clause. (Doc. 117-1 at 2, ¶ 5 (citing Doc. 117-7 at 198).) The subcontract between APTIM and Timberline (“the Timberline Subcontract”) provided that, absent any state laws governing the Prime Contract, the subcontract was to be “governed by and interpreted pursuant to the rules and laws of the state in which the Prime Contract work [was] performed” (i.e., Florida). (Id. at 2–3, ¶ 8 (citing Doc. 117-8 at 23).) The Prime Contract provided only that “United States breach of contract law shall apply.” (Id. at 3, ¶ 9 (citing Doc. 117-3 at 167).) The parties therefore agree that Florida law governs the Timberline Subcontract. (See Doc. 117-2 at 4 & n.1 (citing Doc. 28 at 9); see generally Docs. 117-2, 133 (analyzing and applying Florida law).) B. Procedural Background APTIM terminated the Timberline Subcontract on June 25, 2023. (Id. at 3, ¶ 10.) Timberline filed suit against APTIM in the Middle District of Florida on August 11, 2023. (Id. at 3, ¶ 12.) Then, on August 15, 2024, the Middle District of Florida transferred the case to this Court due to a forum-selection clause in the Timberline Subcontract. (Id. at 3, ¶ 13.) Shortly thereafter,

APTIM filed a Counterclaim against Timberline, alleging fraud and breach of contract, both state law claims. (Id. at 3, ¶¶ 14–15.) On May 16, 2025, APTIM responded to Timberline’s Requests for Admission, acknowledging that APTIM was not a licensed contractor under Florida law. (Id. at 4, ¶ 18 (citing Doc. 117-9); see also id. at 4, ¶¶ 20–21 (citing Docs. 117-9, 117-10).) A search of the Florida Department of Business & Professional Regulation’s website confirmed this admission. (Id. at 4, ¶ 19 (citing Doc. 117-10).) Thus, on May 22, 2025, Timberline moved to amend its Answer to APTIM’s Counterclaim to include the affirmative defense that, because APTIM was not licensed under Florida law, its claims are barred pursuant to Florida Statutes § 489.128. (Doc. 106 at 1–2; see also Doc. 106-2 at 10–11 (citing Fla. Stat. § 489.128).)2 On August 29, 2025, Timberline filed

this MSJ, raising the same argument and seeking dismissal of APTIM’s Counterclaim as well as several of its affirmative defenses to Timberline’s Complaint. (Doc. 117 at 3.) II. SUMMARY JUDGMENT STANDARD “The court shall grant summary judgment if the movant shows that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.” Fed. R. Civ. P. 56(a). “The movant bears the initial burden and must identify ‘those portions of the pleadings, depositions, answers to interrogatories, and admissions on file, together with the

2 The Magistrate Judge denied Timberline’s motion on December 23, 2025, but that decision did not dispose of the instant motion. (See Doc. 147 at 4–11 (denying leave to amend under Federal Rule of Civil Procedure 16).) affidavits, if any, which it believes demonstrate the absence of a genuine issue of material fact.’” Pioneer Expl., L.L.C. v. Steadfast Ins. Co., 767 F.3d 503, 511 (5th Cir. 2014) (quoting Celotex Corp. v. Catrett, 477 U.S. 317, 323 (1986) (internal quotation marks omitted)). “A movant for summary judgment need not set forth evidence when the nonmovant bears the burden of persuasion at trial.” Wease v. Ocwen Loan Servicing, L.L.C., 915 F.3d 987, 997 (5th

Cir. 2019) (citing Celotex, 477 U.S. at 323 (“[W]e find no express or implied requirement in Rule 56 that the moving party support its motion with affidavits or other similar materials negating the opponent’s claim.” (emphasis in original))). “The moving party may meet its burden to demonstrate the absence of a genuine issue of material fact by pointing out that the record contains no support for the non-moving party’s claim.” Id. (quoting Stahl v. Novartis Pharm. Corp., 283 F.3d 254, 263 (5th Cir. 2002)). If the movant bears its burden of showing that there is no genuine issue of material fact, “its opponent must do more than simply show that there is some metaphysical doubt as to the material facts. . . . [T]he nonmoving party must come forward with ‘specific facts showing that

there is a genuine issue for trial.’” Matsushita Elec. Indus.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lafreniere Park Foundation v. Broussard
221 F.3d 804 (Fifth Circuit, 2000)
Stahl v. Novartis Pharmaceuticals Corp.
283 F.3d 254 (Fifth Circuit, 2002)
Arismendez v. Nightingale Home Health Care, Inc.
493 F.3d 602 (Fifth Circuit, 2007)
Rogers v. McDorman
521 F.3d 381 (Fifth Circuit, 2008)
Pasco Ex Rel. Pasco v. Knoblauch
566 F.3d 572 (Fifth Circuit, 2009)
Christopher Scott Hughes v. Eleventh Judicial
377 F.3d 1258 (Eleventh Circuit, 2004)
Gibbons v. Ogden
22 U.S. 1 (Supreme Court, 1824)
Johnson v. Maryland
254 U.S. 51 (Supreme Court, 1920)
Hines v. Davidowitz
312 U.S. 52 (Supreme Court, 1941)
Leslie Miller, Inc. v. Arkansas
352 U.S. 187 (Supreme Court, 1956)
Public Util. Comm'n of Cal. v. United States
355 U.S. 534 (Supreme Court, 1958)
Perez. v. Campbell
402 U.S. 637 (Supreme Court, 1971)
Silkwood v. Kerr-McGee Corp.
464 U.S. 238 (Supreme Court, 1984)
North Dakota v. United States
495 U.S. 423 (Supreme Court, 1990)
Gade v. National Solid Wastes Management Assn.
505 U.S. 88 (Supreme Court, 1992)
Taylor v. Sturgell
553 U.S. 880 (Supreme Court, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
United States of America, for the use and benefit of Timberline Construction Group, LLC v. APTIM Federal Services, LLC, et al., Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-of-america-for-the-use-and-benefit-of-timberline-lamd-2026.