Florida Engineered Construction Products Corp v. United States

42 Cont. Cas. Fed. 77,355, 41 Fed. Cl. 534, 1998 U.S. Claims LEXIS 184, 1998 WL 437338
CourtUnited States Court of Federal Claims
DecidedJuly 31, 1998
DocketNo. 96-200C
StatusPublished
Cited by5 cases

This text of 42 Cont. Cas. Fed. 77,355 (Florida Engineered Construction Products Corp v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Florida Engineered Construction Products Corp v. United States, 42 Cont. Cas. Fed. 77,355, 41 Fed. Cl. 534, 1998 U.S. Claims LEXIS 184, 1998 WL 437338 (uscfc 1998).

Opinion

[536]*536OPINION

BRUGGINK, Judge.

Plaintiff Florida Engineered Construction Products Corporation (“Florida Engineered”) is assignee under a contract between QMS-EF and the United States by which QMS-EF was to provide wood pallet assemblies. Florida Engineered alleges that the United States breached that contract. Currently pending are the parties’ cross-motions for summary judgment. Oral argument was held in Washington, D.C., on August 5,1997.1

BACKGROUND

The facts of this matter are not substantially in dispute. The contract at issue here was entered by QMS-EF, a Florida corporation and debtor in bankruptcy proceedings before the U.S. Bankruptcy Court in the Middle District of Florida.2 Plaintiff Florida Engineered was assigned QMS-EF’s rights under the contract at issue by the trustee in that bankruptcy proceeding. On September 28, 1994, QMS-EF entered into Contract No. N00164-94-C-0214 with the United States worth $515,824.00 to supply various wood pallet assemblies to the Department of the Navy, Naval Surface Warfare Center, at Crane, Indiana.3 The contract contained numerous standard contract clauses under the Federal Acquisition Regulation (FAR), including paragraphs 52.249-8 (default), 52.232-16 (progress payments), and 52.242-13 (notice of progress payments).

The agency performed a preaward survey on September 23, 1994, which recommended a complete award of the contract to QMS-EF. The company received satisfactory ratings for technical capability, production capability, quality-assurance capability, and financial capability. With respect to financial capability, the preaward survey states:

BASED ON THE ANALYSIS OF ALL AVAILABLE INFORMATION, AWARD IS RECOMMENDED. QMS WILL HAVE TO MAKE CAPITAL EXPENDITURES IN EXCESS OF $130,000; HOWEVER, THE VENDOR HAS STATED THAT FINANCING IS AVAILABLE. ALTHOUGH THERE IS NO INCOME COMING INTO THE CORPORATION AT THIS TIME, THE CONTRACTOR HAS A NEGATIVE NET WORTH, AND THEIR BANKING ACCOUNT HAS A BALANCE OF $4,500, QMS HAS PROVIDED A LETTER FROM PALM HARBOR LUMBER GIVING THEM A $100,-000 LINE OF OPEN CREDIT AND A LETTER FROM BANKS FINANCIAL CORPORATION ALSO GIVING THEM A $100,000 LINE OF CREDIT. ALSO, PROGRESS PAYMENTS ARE AUTHORIZED.

The preaward survey did not examine QMS-EF’s accounting system.

On October 20, 1994, QMS-EF submitted its first request for a progress payment to cover the delivery of materials. On October 24, 1994, the administration of the contract was transferred from the Naval Surface Warfare Center to the Defense Logistics Agency’s Defense Contract Management Area Operations in Clearwater, Florida (DCMAO). On October 26, 1994, the administrative contracting officer (ACO) assigned to the contract requested that the Defense Contract Audit Agency (DCAA) audit QMS-EF’s accounting system. On November 14, 1994, the DCAA concluded that QMS-EF’s accounting system was inadequate to support progress payments, citing an inadequate system of labor charging, an incomplete accounting software package, an inadequate method of allocating indirect costs, and inadequate measures to segregate nonallowable costs. This report was provided to QMS-EF on November 23, 1994, along with a letter requesting that QMS-EF advise the DCMAO when the deficiencies cited in the report had been addressed.

[537]*537Another audit was performed, at QMS-EF’s request, and completed on December 15, 1994. This second audit identified five weaknesses in QMS-EF’s accounting system, including: inadequate segregation of indirect costs from direct costs, inequitable allocation of indirect costs, inadequate segregation of unallowable pool expenses, inadequate posting of monthly determinations of cost elements, and deficiencies in QMS-EF’s labor distribution system. The report was forwarded to QMS-EF on December 28, 1994.

After a third audit, performed sometime in January, DCAA issued a report on January 25, 1995, which found QMS-EF’s accounting system “generally adequate” to support progress payments, provided certain conditions were met. As a result, the ACO conditionally approved QMS-EF’s accounting system, citing the conditions noted in the DCAA’s third audit report.

On January 27, 1995, a pre-progress-payment review was conducted on site at QMS-EF by an agency industrial specialist. The industrial specialist noted that no work had been performed under the contract at that time and that QMS-EF did not intend to commence work until February 2, 1995. On January 31, 1995, the ACO concluded that the contractor was not making sufficient progress and that it would not be able to liquidate progress payments. On that same day, QMS-EF requested an extension of thirty days of the delivery schedule. On February 2, 1995, the agency provided a delivery prioritization to QMS-EF; no extension was granted. The agency specifically stated: “These instructions do not constitute a revision to the contract delivery schedule....” No progress payments were ever made to QMS-EF under the contract.

QMS-EF made partial shipments of the contract requirements on February 13, February 27, and March 6, 1995. On March 8, 1995, the first two shipments were rejected because they did not comply with the specification requirements. The third shipment was rejected on March 27, 1995, for noncompliance with specifications. A fourth shipment was received from the contractor on April 12, 1995.4 Plaintiff does not dispute that these shipments did not meet the contract delivery requirements.

On March 16, 1995, the terminating contracting officer (TOO) issued a show-cause letter to QMS-EF, citing the contractor’s failure to perform the contract within the time required by its terms. QMS-EF responded to the show-cause letter on March 23, 1995, recounting the entirety of QMS-EF’s problems on the contract and citing several reasons for its failure to perform. Those reasons can be summarized as follows: (1) QMS-EF was never contacted concerning a post-award conference or orientation; (2) QMS-EF was never contacted by a small-business specialist; (3) QMS-EF was unable to obtain progress payments under the contract; (4) two milling machines ordered for the contract were nonfunctional when delivered;5 (5) QMS-EF was able to successfully deliver some of the contract requirements; and (6) the inspection of the delivered materials was inadequate.

The agency, in making its determination to terminate the contract, addressed each of QMS-EF’s points in an internal memorandum entitled “Determination to Terminate a Contract for Default,” in which the agency outlined the history of the contract and addresses the support for termination. Regarding the post-award conference, the agency stated that QMS-EF never requested one. Regarding the small-business specialist, the agency stated that QMS-EF never requested such advice. Regarding the progress-payment issue, the agency stated:

[O]n 27 Jan 95 a prepayment review was made. Based on this review, the ACO made the determination that the contractor was not making sufficient progress on the performance of the contract nor did she expect QMS to be able to ship an [538]*538acceptable product that they could invoice against to liquidate the progress payments.

With respect to the problems with the milling machines, the agency noted that the purchase of two nonfunetioning milling machines was not its fault.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Emiabata v. United States
102 Fed. Cl. 787 (Federal Claims, 2012)
Becho, Inc. v. United States
47 Fed. Cl. 595 (Federal Claims, 2000)
Libertatia Associates, Inc. v. United States
46 Fed. Cl. 702 (Federal Claims, 2000)
CJP Contractors, Inc. v. United States
45 Fed. Cl. 343 (Federal Claims, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
42 Cont. Cas. Fed. 77,355, 41 Fed. Cl. 534, 1998 U.S. Claims LEXIS 184, 1998 WL 437338, Counsel Stack Legal Research, https://law.counselstack.com/opinion/florida-engineered-construction-products-corp-v-united-states-uscfc-1998.