Pigeon v. United States

27 Ct. Cl. 167, 1892 U.S. Ct. Cl. LEXIS 96, 1800 WL 1885
CourtUnited States Court of Claims
DecidedFebruary 23, 1892
DocketNo. 14235
StatusPublished
Cited by15 cases

This text of 27 Ct. Cl. 167 (Pigeon v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pigeon v. United States, 27 Ct. Cl. 167, 1892 U.S. Ct. Cl. LEXIS 96, 1800 WL 1885 (cc 1892).

Opinion

Weldon, J.,

delivered the opinion of the court:

The contract which is the foundation of this suit was made on the 25th day of October, 1880, by a duly authorized agent of the United States and the claimant.

It relates to a large amount of work in the improvement of the Schuylkill River, near the city of Philadelphia. By the terms of the agreement the claimant was to dredge from the bottom of that river 108,000 cubic yards of earth by the end of June, 1881, for which he was to receive 34 cents per cubic yard for a part of the work, and 29 cents per cubic yard for the balance. Although the contract was made on the 25th day of October, 1880, and was to be completed by the 30th of June following, nothing was done in the prosecution of the work until about the 1st of May, 1881. In June an extension of time for the completion of the contract, upon the application of the claimant, was made by the proper agent of the United States, and in September, upon a like application, the time for the completion of the agreement was again extended to the 30th of November, 1881.

The officer in charge, and the successor to the officer who made, the agreement on the part of the defendants, in August and September became dissatisfied with the progress of the work, but upon the assurance that more vigorous measures would be adopted made the last extension. On the 5th of October, 1881, the claimant made application to the officer in [173]*173charge for the payment of the estimate for labor done during the month of September, which the officer refused to pay, upon the ground that the work was not progressing as it should, and that he would retain not only the per cent but the compensation for the work as an indemnity to the defendants for the faithful performance of the agreement. He was notified by the claimant that without payment he was unable to proceed with the work. The officer also refused to assure claimant that he would be paid for the work-he might do in October and November. Whereupon the claimant refused to proceed with the work, and nothing further was done.

This suit was brought to recover the 10 per cent retained, the amount due for work done, and profits for the portion remaining unperformed.

To the recovery of any of those items the defendants interpose the defense that the claimant violated his agreement, and that the failure upon "the part of the claimant to perform his contract in damages is much more than any amount which the plaintiff can legally claim for labor performed by him under the contract. Much evidence was taken for the purpose of showing that the prosecution of the work was materially retarded by the unwarranted interference of the officer in charge; that in consequence of the unauthorized construction of the agreement on the part of the Government the price to the claimant of the work was increased; and that in consequence plaintiff has suffered damages, which should be added to his compensation for the work actually done.

The defendants say: “ It will be conceded that the claimant will have a right to recover his retained percentages and unpaid earnings less such damages to the defendants as were incident to his failure to perform the work.”

In the case of Kennedy (24 C. Cls. R., 122) we held, on a contract of a similar nature, that the 10 per cent reserved until the completion of the work, though declared forfeited by the agreement in the case of its annulment, must be treated as a penalty and not as liquidated damages.” The case in 24 Court of Claims follows the doctrine announced in the case of Van Buren v. Diggs (11 How., 361), in which it is said:

“In the refusal of the court to admit the evidence thus tendered we think they decided correctly. It would have been irregular in the court to go out' of the terms of the contract [174]*174and into tbe consideration of matters wholly extraneous,,and with nothing upon the face of the writing pointing to such matters as proper or necessary to obtain its construction or meaning. The clause of the contract providing for the forfeiture of ten per centum of the amount of the contract price upon a failure to complete the work by a given day can not be properly regarded as an agreement or settlement of liquidated damages. The term forfeiture imports a penalty; it has no necessary or natural connection with the measure or degree of injury which may result from a breach of contract or from an imperfect performance. It implies an absolute infliction, regardless of the nature or extent of the .causes by which it is superinduced.
“Unless, therefore, it shall have been expressly adopted and declared by the parties to be a measure of injury or compensation, it is never taken as such by courts of justice, who leave it to be enforced, where this can be done, in its real character, viz, that of penalty. In a defense like that attempted by the defendant in the Circuit Court, upon the essential justness and fairness of the acts of the parties, a positive immutable penalty could hardly be applied as a fair test of their merits.”

This case differs somewhat from the Kennedy case in this— in the Kennedy case, at the time of the declared forfeiture, the claimant was in full possession of the work, claiming the right to prosecute it; was interrupted in such prosecution by the forfeiture of the contract, and the assumption of possession on the part of the officers and agents of the Government. In this case-the claimant refused to perform the contract because of the failure on the part of the defendants, to keep, as he alleges, their agreement; and the forfeiture was not declared until the 2Gthof May, 1882, nearly eight months after the abandonment of the work on the part of the claimant.

Preliminary to the consideration of the question of the claim for compensation or damages on either side, we must settle the question which of the parties violated the agreement. The findings of the court eliminate all questions of the manner in which the officers in charge of the work for the defendants acted in the performance of their duties, as well as all claim for alleged improprieties upon the part of the claimant in the delay of the work; and the court has by those findings circumscribed the inquiry as to the right of the parties to, the time the work was abandoned, fixing the legal responsibility of each party because of and from that abandonment. At the time the [175]*175officer in charge refused to pay for what bad been done, or give any assurance of payment of wbat might be done in October and November, 1881, he was not intending to forfeit the contract, but to secure indemnity for the Government against the chances of probable failure upon the part of the contractor.

The law requires the right of forfeiture to be exercised in strict pursuance of the power and in apt time. It can not be founded upon a fault once forgiven, and upon the faith of which forgiveness the derelict party has ventured forward in the performance of his duty.

This controversy, crystallized into its legal essence, involves the question whether the refusal of the defendants to pay in monthly installments gave the claimant the right to abandon the further performance of the contract so as to save all his legal rights in the agreement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Highland Al Hujaz Co., Ltd.
Armed Services Board of Contract Appeals, 2016
Florida Engineered Construction Products Corp v. United States
42 Cont. Cas. Fed. 77,355 (Federal Claims, 1998)
Dano Resource Recovery, Inc. v. District of Columbia
620 A.2d 1346 (District of Columbia Court of Appeals, 1993)
Southeastern Airways Corp. v. United States
673 F.2d 368 (Court of Claims, 1982)
William Green Construction Co. v. United States
477 F.2d 930 (Court of Claims, 1973)
Northern Helex Co. v. United States
455 F.2d 546 (Court of Claims, 1972)
United States v. Lennox Metal Manufacturing Co.
131 F. Supp. 717 (E.D. New York, 1954)
S. R. H. Robinson & Son Contracting Co. v. United States
53 Ct. Cl. 536 (Court of Claims, 1918)
Gleason v. United States
33 Ct. Cl. 65 (Court of Claims, 1897)

Cite This Page — Counsel Stack

Bluebook (online)
27 Ct. Cl. 167, 1892 U.S. Ct. Cl. LEXIS 96, 1800 WL 1885, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pigeon-v-united-states-cc-1892.