Brooklyn & Queens Screen Manufacturing Co. v. United States

97 Ct. Cl. 532, 1942 U.S. Ct. Cl. LEXIS 61, 1942 WL 4342
CourtUnited States Court of Claims
DecidedOctober 5, 1942
DocketNo. 43115
StatusPublished
Cited by9 cases

This text of 97 Ct. Cl. 532 (Brooklyn & Queens Screen Manufacturing Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brooklyn & Queens Screen Manufacturing Co. v. United States, 97 Ct. Cl. 532, 1942 U.S. Ct. Cl. LEXIS 61, 1942 WL 4342 (cc 1942).

Opinion

Littleton, Judge,

delivered the opinion of the court:

Plaintiff brought this suit to recover $30,858.48 from the defendant for work performed and materials furnished and profit earned to October 28,1932. The amount of $16,078.31 represents the sum due from the defendant for materials furnished and work performed and not paid for in the amount of $10,780, which includes the 10 percent previously retained by the defendant from progress payments made, and $5,298.31, the value of the materials, tools, and equipment on the site which were taken and used by the defendant. The balance of $14,780.17 represents profit claimed to October 28,1932. The basis of the claim is that the defendant breached the contract by refusing to make progress partial payments, as stipulated in Article 16 of the contract, after the payment for the month of August 1932.

May 1,1939, the court entered findings of fact, conclusion of law, and opinion in which the court found and held that defendant had breached the contract; that the plaintiff was justified in stopping the work October 28, 1932 and proceeding no further with the contract and that the defendant did not have the right under Art. 9 or any other provision of the contract, after it had breached the contract, to terminate it for an alleged cause of which it had knowledge long prior to the attempted termination, and which it did not at any time, prior to and for at least a month after the plaintiff had stopped work, consider or assert as justifying termination of the contract. As a matter of fact, as the proof [540]*540shows, the termination of the contract on the ground asserted — namely, that the contractor was not diligently proceeding with the work or could not complete the contract within the period provided therein, was not justified. Judgment was entered May 1,1939, in favor of plaintiff for $7,380, which represented only the progress partial payment of $2,250, after deduction of 10 percent for work completed in September 1932, and the value of the work performed and completed amounting to $5,130, after deduction of 10 percent, during October 1932.

Plaintiff filed a motion for a new trial May 12, 1939, and the defendant filed a motion for a new trial June 10, 1939. These motions were overruled June 26, 1939. On June 1, 1939, there was instituted a suit against the defendant by the filing of a petition by the liquidator of the National Surety Company, which was the surety on plaintiff’s performance bond to the defendant, to recover $17,955.16, which included the amount of $16,078.31, value of work performed and material furnished, sued for by plaintiff, as well as the amount of $7,380 for which the court had entered judgment for plaintiff. Thereafter the defendant in August 1939, filed a motion for leave to file, accompanied by a second motion for a new trial, on the ground, that the second suit by the liquidator of the National Surety Company, instituted subsequent to the court’s opinion, asserted a right to recover certain of the same sums involved in plaintiff’s suit, and that the court should hold plaintiff’s case open until the second suit was tried and submitted in order that the court might consider both cases and determine who was entitled to the funds in the hands of the defendant. August 24, 1939, the court granted the motion for leave to file the second motion for a new trial in order to hold this case in abeyance until the second suit should be submitted.

The second suit, No. 44690, by the liquidator of the National Surety Company has been tried, submitted, and considered. The defendant’s second motion for a new trial in this case is allowed. The order of June 26, 1939 overruling plaintiff’s motion for a new trial is vacated and set aside. Plaintiff’s motion for a new trial is allowed and the former [541]*541findings, conclusion of law, and opinion of the court are vacated, set aside, and withdrawn, and new findings, conclusion of law, and opinion are this day filed.

The defendant now states in its brief in the case of Anderson, Liquidator for the National Surety Company, et al. v. United States, No. 44690, as follows:

Defendant admits having in its possession the sum of $17,955.16 as the unpaid balance under the contract in question. Its sole interest is to avoid double liability. The question before the court is the disposition of that fund between the plaintiff in this case [No. 44690] and The Brooklyn & Queens Screen Manufacturing Company, plaintiff in No. 43115.

The facts with reference to the contract between plaintiff and the defendant, the work performed thereon by the plaintiff and the reasons upon and. for which plaintiff ceased work under the contract, and the amount of $16,078.31 owing by the defendant, including the value of small tools and equipment taken over and used by the defendant, are set forth in the findings, which need not be restated here. Upon those facts we are of opinion, upon further consideration, that plaintiff is entitled to recover this sum of $16,078.31. The balance of $1,876.85 in defendant’s hands resulted from work performed by the National Surety Company.

Art. 16 of the contract provided that partial payments would be made to plaintiff by the defendant as the work progressed at the end of each calendar month, or as soon thereafter as practicable, on estimates made and approved by the contracting officer; that in preparing estimates for the purpose of progress payments, materials .delivered on the site and the preparatory work done should be taken into consideration, and that in making such partial payments there should be retained by the Government ten per cent of the estimated amount, until final completion and acceptance of work covered by the contract, with the- proviso that the contracting officer at any time after 50 percent of the work had been completed might make any of the remaining monthly partial payments in full.

Art. 9 of the contract provided that the contracting officer [542]*542might terminate tbe right of the contractor to proceed with the work under contract if the contractor refused or failed to prosecute the work with such diligence as would insure its completion within the period specified in the contract, or as extended, and not caused by acts of the Government or other excusable causes. This article further provided that if the right of the contractor to proceed was not terminated for the cause mentioned, the contractor should continue with the work, and if the same was not completed within the time specified the contractor would pay to the Government liquidated damages at a specified rate until the work was completed for any delay in completion, not excusable under the terms specified in the article, and for which the contractor was responsible. The right of the contracting officer to terminate the contract under Art. 9 did not arise prior to and did not exist, and was not claimed, on or prior to the date when plaintiff notified the contracting officer on October 26, 1932, that if he did not make the progress payment due and determined by him to be due, by October 28, 1932, the contractor would consider the contract breached by the defendant and that it would stop work and proceed no further with it. The contracting officer continued his refusal to pay. This was a breach of the contract. Plaintiff refused to proceed further with the work. About a month thereafter the defendant attempted under Art. 9 to determine the right of plaintiff to proceed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Environmental Safety Consultants, Inc. v. United States
95 Fed. Cl. 77 (Federal Claims, 2010)
Dano Resource Recovery, Inc. v. District of Columbia
620 A.2d 1346 (District of Columbia Court of Appeals, 1993)
Southeastern Airways Corp. v. United States
673 F.2d 368 (Court of Claims, 1982)
Johnson v. United States
618 F.2d 751 (Court of Claims, 1980)
National Eastern Corp. v. United States
477 F.2d 1347 (Court of Claims, 1973)
Northern Helex Co. v. United States
455 F.2d 546 (Court of Claims, 1972)
United States v. Lennox Metal Manufacturing Co.
131 F. Supp. 717 (E.D. New York, 1954)
Modern Industrial Bank v. United States
101 Ct. Cl. 808 (Court of Claims, 1944)

Cite This Page — Counsel Stack

Bluebook (online)
97 Ct. Cl. 532, 1942 U.S. Ct. Cl. LEXIS 61, 1942 WL 4342, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brooklyn-queens-screen-manufacturing-co-v-united-states-cc-1942.