S. R. H. Robinson & Son Contracting Co. v. United States

53 Ct. Cl. 536, 1918 U.S. Ct. Cl. LEXIS 83, 1918 WL 1008
CourtUnited States Court of Claims
DecidedJune 3, 1918
DocketNo. 32688
StatusPublished

This text of 53 Ct. Cl. 536 (S. R. H. Robinson & Son Contracting Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
S. R. H. Robinson & Son Contracting Co. v. United States, 53 Ct. Cl. 536, 1918 U.S. Ct. Cl. LEXIS 83, 1918 WL 1008 (cc 1918).

Opinion

BaRNey, Judge,

reviewing the facts found to be established, delivered the opinion of the court:

This suit arises out of a contract between plaintiff and the Government Reclamation Service. This contract was made February 15, 1907, and was for the construction of a diversion dam and head work on the North Platte project in Nebraska, a copy of the same being attached to and made a part of the petition herein. According to its terms the performance of the contract Avas to be completed April 1, 1908. Not long before the expiration of this time the plaintiff made strenuous application for an extension of this contract period, claiming that it had been delayed in its performance of the contract by the Government. The Government denied this delay on its part but finally concluded (as stated in the correspondence on this subject) to give the plaintiff the “benefit of the doubt,” and granted 10 days additional time in which to perform its contract. The plaintiff failed to perform the contract within the time provided for in the contract, including such extension of 10 days, and thereafter as long as the plaintiff continued work the Government refused to pay plaintiff the amount earned under paragraph 43 of the specifications except upon the deduction of the liquidated damages of $100 per day provided by paragraph 42 of the specifications. In consequence of this action on the part of the Government the plaintiff declined to proceed with the work under the contract and stopped such work May 29, 1908. On July 24, 1908, the Secretary of the Interior notified the plaintiff that if it did not resume work by August 15, 1908, the contract would be suspended under paragraph 22 of the specifications. Plaintiff did not resume work in accordance with this notice, and having refused to do so unless further deductions were not made for liquidated damages the Secretary of the Interior [544]*544notified the plaintiff that the contract was suspended and the work taken over by the Government; and it thereafter took possession of plaintiff’s plant and completed the work March 31, 1909.

In making up its final account with the plaintiff the Government charged it $100 per day for liquidated damages from April 11 to August 18, 1908, giving it credit for retained percentages under paragraph 43 of the specifications, thereby leaving it indebted to plaintiff in the sum of $2,713.64, which the plaintiff refused to accept.

The first question to be considered by the court is whether the Government had the right under the contract to charge the plaintiff with the $100 per day liquidated damages therein provided for after April 11, 1908, when the contract period, including the 10 days’ extension, expired. The answer to this question involves the right of the plaintiff to abandon work under the contract. If the Government had no right to withhold that sum from the monthly payments due under paragraph 43 of the specifications, we think the plaintiff had the right to abandon the work. Canal Co. v. Gordon, 6 Wall., 561; Pigeon v. United States, 27 C. Cls., 167. Otherwise it was not justified in doing so. Upon the decision of this question practically depends all of the issues in this case.

It is contended by the plaintiff that by the extension of the time for the performance of the contract by the Government owing to its delay the liquidated damages provided in the contract were thereby waived, and cites United States v. United Eng. & Con. Co., 234 U. S., 236, and Ittner v. United States, 43 C. Cls., 336, in support of that contention. This is a very important question which this court must decide when properly presented but will refrain from doing so before that time, and we do not think it is necessary in this case. Whatever may be the general rule upon that subject the parties to a contract certainly have the right to change it by proper provisions, and we think that has been done in the instant case. The following are the provisions of the specifications on that subject:

“ 21. Delays. — The contractor shall not be entitled to any compensation for delays or hindrances to the work, except [545]*545that if, in the judgment of the engineer, direct and unavoidable extra cost to the contractor of any part of the work, covered by these specifications is caused by the failure of the United States to provide right of way or material, then upon the presentation of a written claim by the contractor, not later than 30 days after the close of the month during which such extra cost is claimed to have been incurred, such claim, if found correct by the engineer, will be approved. Extension of time will be allowed for unavoidable delays that may result from unforeseen causes that, in the opinion of the egnineer, approved by the Secretary of the Interior, are undoubtedly beyond the control of the contractor. If the Avork be delayed by specific orders to stop work given by the Secretary of the Interior or by the engineer, or if any delay or hindrance be caused by their failure to provide’ material sufficient to carry on the work, or to provide necessary right of way, then such delay will entitle the contractor to an extension of time equivalent to the time lost in such delay, provided the contractor shall have submitted to the engineer written claim within 30 days from the cause thereof. Any extension of time, however, shall not release the sureties from their obligations, which shall remain in full force and effect until the discharge of the contract. Any application for an extension of time must be accompanied by the formal consent of the sureties thereto, or other sufficient sureties must be furnished by the contractor. Should the contractor fail to complete the work in the time agreed upon in the contract, or in such extra time as may have been allowed for delays as herein provided, the engineer will compute and appraise the direct damages for the loss sustained by the United States on account of further employment of engineers, inspectors, and other employes, including all disbursements on the engineering account, properly chargeable to the work. íhe amount so appraised and computed is hereby agreed upon as the damages for the delay, and will be deducted from ahy money due the contractor under his contract, añd the contractor and sureties shall be liable for any excess. The decision of the chief engineer as to the appraisal of such damages shall be final and binding on both parties. Any provisions in the detail specifications concerning deduction for delay shall be held as modifying or revoking the provisions of this paragraph.
“42. Deduction for failure to complete. — If the several parts of the work are not completed within the time agreed upon there will be deducted from any sum otherwise due under the contract the following amounts for each and every [546]*546day occupied in excess of the time agreed upon, viz, for the work included under schedule 1, $50 per day; for the work included under schedule 2, $50 per day. This deduction will be in lieu of that provided for in paragraph 21, and is agreed upon as liquidated damages for the loss to the United States on account of engineering, superintendence, and value of operation of the irrigation works dependent thereon.”

These two paragraphs must be read and construed together and both of them given effect as far as possible, as that is elementary in the construction of contracts.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Canal Co. v. Gordon
73 U.S. 561 (Supreme Court, 1868)
Pigeon v. United States
27 Ct. Cl. 167 (Court of Claims, 1892)
Ittner v. United States
43 Ct. Cl. 336 (Court of Claims, 1908)

Cite This Page — Counsel Stack

Bluebook (online)
53 Ct. Cl. 536, 1918 U.S. Ct. Cl. LEXIS 83, 1918 WL 1008, Counsel Stack Legal Research, https://law.counselstack.com/opinion/s-r-h-robinson-son-contracting-co-v-united-states-cc-1918.