Kennedy v. United States

24 Ct. Cl. 122, 1889 U.S. Ct. Cl. LEXIS 86, 1800 WL 1619
CourtUnited States Court of Claims
DecidedJanuary 28, 1889
DocketNo. 15034
StatusPublished
Cited by12 cases

This text of 24 Ct. Cl. 122 (Kennedy v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kennedy v. United States, 24 Ct. Cl. 122, 1889 U.S. Ct. Cl. LEXIS 86, 1800 WL 1619 (cc 1889).

Opinion

Weldon, J.,

delivered the opinion of the court:

In October and December of the year 1882 the claimant entered into two written contracts with the United States, both of which are alleged in extenso in the petition. Under those contracts the claimant was to perform a large amount of work in building levees on the Mississippi Kiver, in the State of. Louisiana, and for which he was to receive a stated compensation, to be paid by the defendants as the work progressed. In the making of said contracts Major Stickney represented the United States, and to him or his successors is reserved, by the terms of the contracts, much power and discretion, in the exercise of which the rights of the claimant mig'ht be very seriously affected. By the terms of the agreements the work on Kemp Breaks was to be commenced on or before the 9th day of October, 1882, and be finished by the 1st day of February, 1883 j but, under the power given fo said Stickney to extend the time for completion, there was an extension, from time to time, until the 1st of February, 1884. So with the contract for work on Hardscrabble and Bondurant, the time for its completion was extended by the officer of the Government, commensurate with the time allowed on Kemp Breaks.

About the 1st of January, 1884, Major Stickney became dissatisfied with the progress of the work, made some investigation by an inspection of its condition; on the 4th of January he declared the contract as to the Hardscrabble and Bondurant annulled, and on the 6th of the same month declared the same as to the work on Kemp Breaks. The power which he claimed and exercised is dependent upon the following provision of the contracts :

“ If in any event the party of the second part shall delay or fail to commence with the delivery of the material or performance of the work on the day specified herein, or shall, in the judgment of the engineer in charge, fail to prosecute faithfully and diligently the work in accordance with the specifications and requirements of this contract, then, in either case, the party of the first part or his successor, legally appointed, shall have power, with the sanction of the Chief of Engineers, to annul this contract by giving notice in writing to that effect to the party (or parties, or either of them) of the second part, and upon the giving of such notice all money or reserved percentage due or to become due to the party or parties of the second part, by reason of this contract, shall be and become forfeited [135]*135to the United States; and the party of the first part shall be thereupon authorized, if any immediate performance of the work or delivery of the material be, in his opinion, required by the public exigency, to proceed to provide for the same by open purchase or contract, as prescribed in section 3709 of the Revised Statutes of the United States.”

To that clause of the contract there is the following proviso:

“ That if the party or parties of the second part shall by freshets, ice, or other force or violence of the elements, and by no fault of his or their own, be prevented either from commenci ng or completing the work, or delivering the materials at the time agreed upon in this contract, such additional time may in writing be allowed him or them for such commencement or completion as in the judgment of the party of the first part, or his successor, shall be just and reasonable; but such allowance and extension shall in no manner affect the rights or obligations of the parties under this contract; but the same shall subsist and take effect and be enforceable precisely as if the new date for such commencement or completion had been the date originally herein agreed upon.”

By the terms of the contracts the claimant is to receive 28£ cents per cubic yard for embankment, and $35 per acre for felling timber on the “ Kemp Breaks” levee; and for the work embraced in the second contract he is to receive the sum of 28 cents per cubic yard for embankment, plus 10 per cent, for felling timber, as determined by the engineer in charge. Under the first agreement the amount of the work is about 340,000 cubic yards, and under the second about 330,000, aggregating the sum of 670,000 cubic yards.

The extent and quality of the work to be performed under both agreements are subject to following provision as to the power and duty of the officer in charge:

“All materials furnished or work done under this contract shall, before being accepted, be subject to a rigid inspection by an inspector appointed on the part of the Government; and such as does not conform to the specifications set forth in this contract shall be rejected. The decision of the engineer officer in charge as to quality and quantity shall be final.”

As the petition claims for extra work, it is necessary that we cite the provision of the contracts on that subject.

“ No claim whatever shall at any time be made upon the United States by the party or parties of the second part for or on account of any extra work or material performed or furnished, or alleged to have been performed or furnished, under or by virtue of this contract, and not expressly bargained for [136]*136and specifically included therein, unless such extra work or material shall have been expressly required, in writing, by the party of the first part or liis successor, the prices and quantities thereof having been first agreed upon by the contracting parties and approved by the Chief of Engineers.

Upon the subject of payments the said contracts provided as follows:

“ Payment shall be made to the said Patrick J. Kennedy at or near the end of each month (reserving 10 per cent, from each payment until the whole work shall have been delivered and accepted), on measurement of work done during the month, deducting the allowance for settling.”

These are the only clauses of the contracts which are necessary to be noticed in the present connection. After some effort in the War Department, upon the part of the claimant, to adj ust his alleged rights against the Government, the case was referred to this court by the Secretary of War under section 1063 of the Revised Statutes. Upon that reference the said claimant filed a petition, demanding an aggregate sum, composed of the following items:

“ The plaintiff claims that he is justly entitled to have and receive from the defendant the following sums of money:
1st. Money due plaintiff and withheld by defendant for work
done on Kemp Levee. $5,513.35
Money due plaintiff and withheld by defendant for work done
on Hardscrabble and Bondurant Levees. 14,906.06
For work done and earth placed under the contracts in December, 1883, for which defendant made no estimates. 23,000.00
For extra work done on Kemp Levee from December 22,1883, to
January 4, 1884 . 4,275.00
For clearing base on Kemp Levee. 750.00
For extra dirt wheeled at Potter’s Lake, on Kemp Levee. 570.00
For extra dirt wheeled at the stations 124 to 126, Kemp Levee. 285.00
For draining on Hardscrabble and Bondurant Levee, by order of Major Amos Stickney. 885.00

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tecom, Inc. v. United States
66 Fed. Cl. 736 (Federal Claims, 2005)
S&E Contractors, Inc. v. United States
406 U.S. 1 (Supreme Court, 1972)
Oltedale v. United States
39 F. Supp. 998 (D. Rhode Island, 1941)
Helvetia Milk Condensing Co. v. United States
39 F.2d 1012 (Court of Claims, 1930)
Penn Bridge Co. v. United States
59 Ct. Cl. 892 (Court of Claims, 1924)
John Thomson Press, & Manufacturing Co v. United States
57 Ct. Cl. 200 (Court of Claims, 1922)
Brinck v. United States
53 Ct. Cl. 170 (Court of Claims, 1918)
Mundy v. United States
35 Ct. Cl. 265 (Court of Claims, 1900)
Gleason v. United States
33 Ct. Cl. 65 (Court of Claims, 1897)
Pigeon v. United States
27 Ct. Cl. 167 (Court of Claims, 1892)

Cite This Page — Counsel Stack

Bluebook (online)
24 Ct. Cl. 122, 1889 U.S. Ct. Cl. LEXIS 86, 1800 WL 1619, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kennedy-v-united-states-cc-1889.